The Land Acquisition Bill is slated to be taken up for consideration and passing in the Lok Sabha today. The government had circulated an amendment list in the last session of Parliament. In a column in the Financial Express, MR Madhavan discusses the major features of the Land Acquisition Bill and the associated issues that Parliament may need to consider while deliberating on the Bill. Economic growth and job creation require efficient usage of land resources. It is important that a fair and transparent process for purchase and for acquisition of land is followed. For the purchase of land, a key concern is the authenticity of land titles, and the government has drafted a Land Titling Bill for this purpose. In the case of land acquisition, the following questions need to be addressed. What are the end-uses for which public interests will trump private property rights, and justify acquisition of land from a person who is not willing to part with it? What should be the process followed? Since there is no market mechanism of discovery of prices in these cases, how should compensation be computed? Is there a need to address non-land owners who may be displaced by the acquisition process? Does the acquisition process get completed in a reasonable amount of time, and is there finality to the acquisition? In sum, do both sides—the acquirer and the land owner—perceive the process to be fair? The current Bill addresses these questions in the following manner. It defines public purpose to include infrastructure projects (as defined by the finance ministry, with some exclusions); projects related to agriculture, agro-processing and cold storage; industrial corridors, mining activities, national investment and manufacturing zones; government administered or aided educational and research institutions; sports, healthcare, transport and space programmes. It also enables the government to include other infrastructural facilities to this list after tabling a notification in Parliament. The significant difference from the current Land Acquisition Act, 1894, is that land cannot be acquired for use by companies unless they satisfy any of the above end-uses. The Bill includes a requirement for consent of the land owners in some cases. If the land is acquired for use by a private company, 80% of land owners need to give consent. If it is for use by a public private partnership (PPP), 70% of the land owners have to agree to the acquisition. The rationale of having differential consent requirements based on ownership—including the lack of any such requirement if the land is for the use of the government or a public sector undertaking—is not clear. Why should a land owner, who is losing his land care, whether the intended project is to be executed by the government or a private company? The Bill specifies that the compensation will be computed in the following manner. Three factors are taken into account: the circle rate according to the Stamp Act; the average of the top 50% of sale deeds registered in the vicinity in the previous three years; the amount agreed upon, if any, in case of purchase by a private company or PPP. The higher of these three amounts is multiplied by a factor, which varies from 1 in urban areas to a number between 1 and 2 in rural areas, depending upon the distance from the urban centre. To this amount, the value of any fixed assets such as buildings, trees, irrigation channels etc is added. Finally, this figure is doubled (as solatium, i.e. compensation for the fact that the transaction was made with an unwilling seller). The justification given for the multiplier ranging from 1 to 2 is that many transactions are registered at a price significantly lower than the actual value in order to evade taxes—the moot question is whether such under-reporting is uniform across the country? The Bill states that all persons who are affected by the project should be rehabilitated and resettled (R&R). The R&R entitlements for each family includes a house, a one-time allowance, and choice of (a) employment for one person in the project, (b) one-time payment of R5 lakh, or (c) inflation adjusted annuity of R2,000 per month for 20 years. In addition, the resettlement areas should have infrastructure such as a school, post office, roads, drainage, drinking water, etc. The process has several steps. Every acquisition, regardless of size, needs a social impact assessment, which will be reviewed by an expert committee, and evaluated by the state government. Then a preliminary notification will be issued, land records will be updated, objections will be heard, rehabilitation and resettlement survey carried out, and a final declaration of acquisition issued. The owners can then claim compensation, the final award will be announced, and the possession of the land taken. The total time for this process can last up to 50 months. The big question is whether this time frame would hinder economic development and the viability of projects? The Bill provides for an Authority to adjudicate disputes related to measurement of land, compensation payable, R&R etc, with appeals to be heard by the High Court. There are several restrictions on the land acquired. The purpose for which land is acquired cannot be changed. If land is not used for five years, it would be transferred to a land bank or the original owners. Transfer of ownership needs prior permission, and in case of transfer in the first five years, 40% of capital gains have to be shared with the original owners. Recent cases of land acquisition have been followed by public protests, and the stalling of the acquisition. Whereas some of these may be driven by political agendas, the old Act was perceived to be unfair to land owners in several ways. The challenge for Parliament is to examine the new Bill and craft the law in such a way that it is fair (and perceived as such) to land owners, while making acquisition feasible and practical for projects that are required for economic development and other areas of public interest.

Last week, the Power Finance Corporation reported that state-owned power distribution companies across the country made financial losses amounting to Rs 68,832 crore in 2022-23.  This is four times higher than the losses witnessed in 2021-22, and roughly equivalent to the annual budget of a state like Uttarakhand.   This blog examines some of the causes and implications of such losses.

Overview of financial losses

For several years now, electricity distribution companies (discoms), which are mostly state-owned, have witnessed steep financial losses.  Between 2017-18 and 2022-23, losses accumulated to over three lakh crore rupees.  In 2021-22, discom witnessed substantial reduction in their losses, primarily because states released 1.54 lakh rupees in subsidies to clear pending dues.  State governments provide discoms with subsidies, so that domestic and agricultural consumers receive affordable power.  These payments are typically delayed which creates cash flow constraints, and leads to an accumulation of debt.  In addition, costs incurred by discoms in 2021-22 remained unchanged.

Note: Data from 2020-21 onwards does not include Odisha, and Dadra & Nagar Haveli and Daman and Diu since their distribution function was privatised in 2020-21.  Data for Ladakh is available from 2021-22 onwards.  Data for Jammu and Kashmir is not available.  The Delhi Municipal Council Distribution Utility has been included from 2020-21 onwards.
Sources: Power Finance Corporation reports for various years; PRS.

As of 2022-23, losses have increased again to reach Rs 68,832 crore.   This increase has been driven by rising costs.  At a per unit level, the cost of supplying one kilowatt of electricity rose from 7.6 rupees in 2021-22, to 8.6 rupees in 2022-23 (See Table 1).

Table 1: Financial details of state-owned power distribution companies

Details

2019-20

2020-21

2021-22

2022-23

Average cost of supplying power (ACS)

7.4

7.7

7.6

8.6

Average revenue realised (ARR)

6.8

7.1

7.3

7.8

Per unit loss (ACS-ARR)

0.6

0.6

0.3

0.7

Total losses (in Rs crore)

-60,231

-76,899

-16,579

-68,832

Note: Data from 2020-21 onwards does not include Odisha, and Dadra & Nagar Haveli and Daman and Diu since their distribution function was privatised in 2020-21.  Data for Ladakh is available from 2021-22 onwards.  Data for Jammu and Kashmir is not available.  The Delhi Municipal Council Distribution Utility has been included from 2020-21 onwards.
Sources: Power Finance Corporation reports for various years; PRS.

Purchase of electricity from generation companies (gencos) forms about 70% of a discom’s total costs, and coal is the primary source for generating electricity.  The following chain of events took place in 2022-23: (i) consumer demand for electricity rose by 10% over the previous year, as compared to a 6% year-on-year increase in the past 10 years, (ii) coal had to be imported to meet the increased demand, and (iii) global coal prices were elevated.

Coal imported at elevated prices to keep up with rising electricity demand

In 2022-23, demand for electricity increased by 10% over 2021-22.  Between 2008-09 and 2018-19, demand increased at an annual growth rate (CAGR) of 6%.  Electricity demand grew as the economy grew (at 7%), and largely came from domestic and agricultural consumers.  These consumer categories account for 54% of the total electricity sales, and their demand rose by 7%.

Sources: Central Electricity Regulatory Commission; PRS.

Electricity cannot be stored at scale, which means that generation must be scheduled depending on anticipated demand.  The Central Electricity Authority anticipates annual demand for each year.  It estimated that demand in 2022-23 would be at 1,505 billion units.   However, the actual demand was higher than anticipated in the first few months of 2022-23 (See Figure 3).

To meet this demand, electricity generation had to be ramped up.  Coal stocks had already depleted from 29 million tonnes in June 2021 to eight million tonnes in September 2021, on account of high demand in 2021-22.  To ensure uninterrupted supply of power, the Ministry of Power directed gencos to import coal.  The Ministry noted that without imports, widespread power cuts and blackouts would have occurred.

Sources:  Load Generation Balance Report 2022 and 2023, Central Electricity Authority; PRS.

Coal imports rose by about 27 million tonnes in 2022-23.  While this constituted only 5% of the overall coal used in the sector, the price at which it was imported significantly impacted the sector.  In 2021-22, India imported coal at an average price of Rs 8,300 per tonne.   This rose to Rs 12,500 per tonne in 2022-23, a 51% increase.  Coal was primarily imported from Indonesia, and prices shot up due to the Russia-Ukraine war, and demand surge by countries like India and China.   

Sources: Ministry of Power; Ministry of Statistics and Programme Implementation; PRS.

Coal import situation going forward

In January 2023, the Ministry of Power advised gencos to import 6% of the required coal, to ensure sufficient stock until September 2023.   It noted that due to floods and variable rainfall in various parts of the country, hydro generation capacity reduced by about 14%.   This put additional burden on coal based thermal generation in 2023-24.  Following this, in October 2023, the Ministry directed all gencos to continue using at least 6% imported coal until March 2024.  

image

Sources: Ministry of Coal; PRS.

Structural issues in the power sector and its impact on state finances

Discoms witness persistent financial losses due to certain structural issues.  Their costs are typically high because of old contracts with generation companies (gencos).  Power purchase costs in these contracts  do not account for production efficiencies over the years, and costs remain unchanged.  Tariffs are only revised every few years, to ensure that consumers are protected from supply chain shocks.  As a result, costs are carried forward for a few years.  In addition, discoms sell electricity to certain consumers such as agricultural and residential consumers, below cost.  This is supposed to primarily be recovered through subsidy grants provided by state governments.  However, states often delay subsidy payments leading to cash flow issues, and accumulation of debt.  In addition, tariff recovery from the power sold is not optimal.  

Losses reported in the generation sector have also increased.  In 2022-23, state-owned gencos reported losses worth Rs 7,175 crore, as compared to the Rs 4,245 crore in 2021-22.  Rajasthan accounted for 87% of these, at Rs 6,278 crore.  Note that under the Late Payment Surcharge Rules, 2022, discoms are required to make upfront payments to gencos.  

Risk to state finances

Persistent financial losses, high debt and guarantees extended by states continue to pose a risk to state finances.  These are contingent liabilities for state governments, i.e., in the event a discom is unable to repay its debt, the state would have to take it over.  

Several such schemes have been introduced in the past to bail discoms out (See Table 2).  As of 2022-23, discoms have an outstanding debt worth Rs 6.61 lakh crore, 2.4% of the national GDP.  Debt is significantly high in states such as Tamil Nadu (6% of GSDP), Rajasthan (6% of GSDP), and Uttar Pradesh (3% of GSDP).  Previous Finance Commissions have recognised that strengthening discom finances is key in minimising the risk to state finances.    

Table 2: Key government schemes for the turnaround of the distribution sector over the years

Year

Scheme

Details

2002

Bailout Package

States take over the debt of state electricity boards worth Rs 35,000 crore, 50% waiver of interest payable by state electricity boards to central PSUs

2012

Financial Restructuring Package

States take over 50% of the outstanding short-term liabilities worth Rs 56,908 crore

2015

Ujwal Discom Assurance Yojana (UDAY)

States take over 75% of the debt of discoms worth Rs 2.3 lakh crore and also provide grants for any future losses

2020

Liquidity Infusion Scheme

Discoms get loans worth Rs 1.35 lakh crore from Power Finance Corporation and REC Limited to settle outstanding dues of generators, state governments provide guarantee

2022

Revamped Distribution Sector Scheme

Central government to provide result-linked financial assistance worth Rs 97,631 crore for strengthening of supply infrastructure

Sources: NITI Aayog, Press Releases of the Ministry of Power; PRS.

For more details on the impact of discom finances on state finances, see here.  For more details on structural issues in the power distribution sector, see here.  
 

ANNEXURE

Table 3: Cost and revenue structure of discoms on energy sold basis (in Rs per kw)

Details

2019-20

2020-21

2021-22

2022-23

Average cost of supplying power (ACS)

7.4

7.7

7.6

8.6

    of which

       

    Cost of procuring power 

5.8

5.9

5.8

6.6

Average revenue realised (ARR)

6.8

7.1

7.3

7.8

    of which

       

    Revenue from sale of power

5.0

4.9

5.1

5.5

    Tariff subsidy

1.3

1.4

1.4

1.5

       Regulatory income and revenue grant under UDAY

0.3

0.1

0.0

0.2

Per unit loss

0.6

0.6

0.3

0.7

Total financial losses

-60,231

-76,899

-16,579

-68,832

Sources: Power Finance Corporation reports for various years; PRS.

Table 4: State-wise profit/loss of power distribution companies (in Rs crore)

State/UT

2017-18

2018-19

2019-20

2020-21

2021-22

2022-23

Andaman and Nicobar Islands

-605

-645

-678

-757

-86

-76

Andhra Pradesh

-546

-16,831

1,103

-6,894

-2,595

1,211

Arunachal Pradesh

-429

-420

NA

NA

NA

NA

Assam

-259

311

1,141

-107

357

-800

Bihar

-1,872

-1,845

-2,913

-2,966

-2,546

-10

Chandigarh

321

131

59

79

-101

NA

Chhattisgarh

-739

-814

-571

-713

-807

-1,015

Dadra & Nagar Haveli and Daman & Diu

312

-149

-125

NA

NA

NA

Delhi

NA

NA

NA

98

57

-141

Goa

26

-121

-276

78

117

69

Gujarat

426

184

314

429

371

147

Haryana

412

281

331

637

849

975

Himachal Pradesh

-44

132

43

-153

-141

-1,340

Jharkhand

-212

-730

-1,111

-2,556

-1,721

-3,545

Karnataka

-2,439

-4,889

-2,501

-5,382

4,719

-2,414

Kerala

-784

-135

-270

-483

98

-1,022

Ladakh

NA

NA

NA

NA

-11

-57

Lakshadweep

-98

-120

-115

-117

NA

NA

Madhya Pradesh

-5,802

-9,713

-5,034

-9,884

-2,354

1,842

Maharashtra

-3,927

2,549

-5,011

-7,129

-1,147

-19,846

Manipur

-8

-42

-15

-15

-22

-146

Meghalaya

-287

-202

-443

-101

-157

-193

Mizoram

87

-260

-291

-115

-59

-158

Nagaland

-62

-94

-477

-17

24

33

Puducherry

5

-39

-306

-23

84

-131

Punjab

-2,760

363

-975

49

1,680

-1,375

Rajasthan

-11,314

-12,524

-12,277

-5,994

2,374

-2,024

Sikkim

-29

-3

-179

-34

NA

71

Tamil Nadu

-12,541

-17,186

-16,528

-13,066

-9,130

-9,192

Telangana

-6,697

-9,525

-6,966

-6,686

-831

-11,103

Tripura

28

38

-104

-4

-127

-193

Uttar Pradesh

-5,269

-5,902

-3,866

-10,660

-6,498

-15,512

Uttarakhand

-229

-808

-323

-152

-21

-1,224

West Bengal

-871

-1,171

-1,867

-4,261

1,045

-1,663

State Sector

-56,206

-80,179

-60,231

-76,899

-16,579

-68,832

Dadra & Nagar Haveli and Daman & Diu

NA

NA

NA 

242

148

104

Delhi

109

657

-975

1,876

521

-76

Gujarat 

574

307

612

655

522

627

Odisha 

NA

NA

-842

-853

940

746

Maharashtra 

NA

590

1,696

-375

360

42

Uttar Pradesh 

182

126

172

333

256

212

West Bengal 

658

377

379

398

66

-12

Private Sector

1,523

2,057

1,042

2,276

2,813

1,643

All-India

-54,683

-78,122

-59,189

-77,896

 -13,766 

 -67,189 

Note: Minus sign (-) indicates loss; Dadra & Nagar Haveli and Daman & Diu discom was privatised on April 1, 2022; New Delhi Municipal Council Distribution utility has been added from 2020-21 onwards. 
Sources: Power Finance Corporation reports for various years; PRS.