The Union Cabinet approved the implementation of Seventh Pay Commission recommendations yesterday.  The Commission was tasked with reviewing and proposing changes to the pay, pension and efficiency of government employees. These recommendations will apply to 33 lakh central government employees, in addition to 14 lakh armed forces personnel and 52 lakh pensioners.  This will take effect from January 1, 2016. Number of Employees Pensioners                 Pay, Allowances and Pension of central government employees In relation to an employee, the Commission proposed to increase (i) the minimum salary to Rs 18,000 per month, and (ii) the maximum salary to Rs 2,50,000 per month. It also recommended moving away from the existing system of pay bands and grade pay, which is used to determine an employee’s salary.  Instead, it proposed a new pay matrix which will take into account the hierarchy of employees, and their pay progression during the course of employment.  The Commission also suggested that this matrix should be reviewed periodically, with a frequency of less than 10 years. The Pay Commission also suggested a linkage between performance and remuneration of an employee.  For this, it proposed the introduction of performance related pay which will be based on an annual appraisal of the employee.  In addition, it recommended that annual increments of an employee should be withheld, if he is unable to meet the benchmark required for regular promotion or career progression. The Commission also sought to abolish or merge some of the allowances that may be given to employees by various government departments.  It suggested that, of the 196 allowances that exist, 52 should be abolished and 36 should either be merged under existing heads, or be included under proposed allowances.  Some of these allowances involved payment of a meagre amount of close to Rs 100 per month. In addition, the rates of House Rent Allowance (HRA) were revised.  The Commission proposed a methodology to increase the HRA rates every time the Dearness Allowance given to employees increased to 50% or 100%.  Dearness Allowance is given to employees in lieu of increases in the cost of living, on account of inflation. The Commission had also proposed a new methodology for computing pension for pensioners who retired before January 1, 2016.  This is aimed at bringing parity between past and current pensioners.  As part of the new methodology, two options for calculation of pension have been prescribed, and the pensioner may opt for either one. Financial Impact on the government Table 7CPCThe implementation of the Seventh Pay Commission recommendations is expected to cost the government Rs 1,02,100 crore.  Of this amount, 72% will be borne by the central government, and 28% by the railways. As a result, the overall expenditure is expected to increase by 23.6%, with a 16% increase in expenses on pay, 63% in allowances and 24% in pension. Addressing the issue of vacancy VacancyAs of 2014, the central government had a job vacancy of 18.5%.[i]  These vacancies may need to be filled or abolished, if required, to reduce redundancy.[ii] It may be noted that the Second Administrative Reforms Commission had observed that reducing the number of government employees is necessary for modern and professional governance.  Further, it had expressed concern that the increasing expenditure on salaries of government employees may be at the cost of investment in priority areas such as infrastructure development and poverty alleviation.[iii] Inducting specialised personnel in the government The Second Administrative Reforms Commission had also observed that some senior positions in the central government require specific skill sets (including technical and administrative know-how).[iii] One way of developing these skill-sets is to recruit personnel directly into these departments so that they can over a period of time develop the required skills.  For example, personnel from the Central Engineering Service (Roads) may aspire and be qualified to hold senior positions in the Ministry of Road, Transport and Highways or a body like the National Highways Authority of India. However, another view is that special skill-sets may be inducted in the government through lateral entry of experts from outside government.  This will allow for widening of the pool of candidates and greater competition for these positions.[iii] The Second Administrative Reforms Commission had also recommended that senior positions in the government should be open to all services. The last Pay Commission’s recommendations, in 2008, led to an increased demand in the automobile, consumer products and real estate related sectors.  With the Seventh Pay Commission’s recommendations expected to take effect from January 1, 2016, their impact on the economy and the consumer market will become known in due course of time.     [i] Report of the Seventh Central Pay Commission, Ministry of Finance, 2015 http://finmin.nic.in/7cpc/7cpc_report_eng.pdf. [ii] “Union govt has 729,000 vacancies: report”, Live Mint, November 30, 2015, http://www.livemint.com/Home-Page/X6U6xFe5oR2pW4simMmAhK/Union-govt-has-729000-vacancies-report.html. [iii] 10th and 13th Reports of the Second Administrative Reforms Commission, 2008 and 2009.  

Recently, the central government launched the Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya).[i],[ii]  The scheme seeks to ensure universal household electrification (in both rural and urban areas) by providing last mile connectivity.  The scheme is expected to cover three crore households.  Note that currently about four crore households are un-electrified.  A rural electrification scheme has also been under implementation since 2005.  In light of this, we discuss the current situation of, and key issues related to rural electrification in the country.

Regulatory and policy framework

Under the Electricity Act, 2003, the central and state governments have the joint responsibility of providing electricity to rural areas.  The 2003 Act also mandates that the central government should, in consultation with the state governments, provide for a national policy on (i) stand-alone power systems for rural areas (systems that are not connected to the electricity grid), and (ii) electrification and local distribution in rural areas.  Consequently, the Rural Electrification Policy was notified in August 2006.[iii]

The Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), launched in 2005, was the first scheme on rural electrification.  In December 2014, Ministry of Power launched the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), which subsumed the RGGVY.[iv]  Components of DDUGJY include: (i) separation of agricultural and non-agricultural electricity feeders to improve supply for consumers in rural areas, (ii) improving sub-transmission and distribution infrastructure in rural areas, and (iii) rural electrification by carrying forward targets specified under the RGGVY.

The total financial outlay for DDUGJY over the implementation period (until 2021-22) is Rs 82,300 crore which includes budgetary support of Rs 68,900 crore.  The central government provides 60% of the project cost as grant, the state power distribution companies (discoms) raise 10% of the funds, and 30% is borrowed from financial institutions and banks.

Status of rural electrification

As of August 2017, about 1% of the villages in India remain un-electrified (3,146 villages).  However, with regard to households, around 23% (4.1 crore households) are yet to be electrified.  Table 1 at the end of this post shows the status of rural electrification across all states.

Issues with rural electrification

Definition of an electrified village

An electrified village is defined as one that has the following: (i) provision of basic infrastructure such as distribution transformers and lines in the inhabited locality, (ii) provision of electricity in public places like schools, panchayat office, health centers, dispensaries, and community centers, and (iii) at least 10% of the total number of households in the village are electrified.[iv]

Therefore, a village is considered to be electrified if 10% of the total number of households in the village have been electrified.  This is apart from the basic infrastructure and electrification of certain public centers in the village.  The Standing Committee on Energy (2013) had observed that according to this definition, a village would be called electrified even if up to 90% of households in it do not have an electricity connection.[v]  It also noted that the infrastructure being provided under the scheme is highly inadequate, unreliable and unsustainable.  The Committee recommended that the actual electrification requirement of villages must be assessed, and it should be ensured that the state discoms provide electricity to the remaining households in the village.

Supply of electricity

The Standing Committee had also noted that while the rural electrification scheme looks at creating infrastructure, the actual supply of electricity to households rests with the state discoms.[v]  These discoms are already facing huge financial losses and hence are unable to supply electricity to the villages.  Discoms continue to supply subsidised power to agricultural and residential consumers, resulting in revenue losses.  Further, the average technical and commercial losses (theft and pilferage of electricity) (AT&C losses) are at around 25%.  While the Ujjwal Discom Assurance Yojana (UDAY) has eased off some of the financial losses of the discoms, it remains to be seen whether discoms are able to reduce the cost-tariff gap and AT&C losses in the future.

It has been recommended that generation capacity should be augmented so that states can meet the additional demand under the rural electrification schemes. Further, the assistance to financially weaker states should be increased so that they can better implement the scheme.[v]

Electricity to below poverty line (BPL) households

Under the rural electrification scheme, the cost for providing free electricity connection per BPL household is Rs 3,000.  It has been observed that this cost per household may be inadequate.[v]  Due to the low cost, the quantity and the quality of work has been getting compromised leading to poor implementation of the scheme.  It has been recommended that the Ministry should revisit the cost provided under the scheme.[v]

The new electrification scheme: Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya)

The new scheme, Saubhagya, seeks to ensure universal household electrification, that is, in both rural and urban areas.  Under Saubhagya, beneficiaries will be identified using the Socio Economic and Caste Census (SECC) 2011 data.  The identified poor households will get free electricity connections.  Other households not covered under the SECC, will be provided electricity connections at a cost of Rs 500.  This amount will be collected by the electricity distribution companies in 10 instalments.

The total outlay of the scheme will be Rs 16,320 crore, of which the central government will provide Rs 12,320 crore.  The outlay for the rural households will be Rs 14,025 crore, of which the centre will provide Rs 10,588 crore.  For urban households the outlay will be Rs 2,295 crore of which the centre will provide Rs. 1,733 crore.

The state discoms will execute the electrification works through contractors or other suitable agencies.  Information technology (mobile apps, web portals) will be used to organise camps in villages to identify beneficiaries.  In order to accelerate the process, applications for electricity connections will be completed on the spot.

So far the focus of electrification schemes has been on rural areas, where typically last mile connectivity has been difficult to provide.  Saubhagya extends the ambit of electrification projects to urban areas as well.  While DDUGJY has focused on the village as the principal unit to measure electrification, the new scheme shifts the targets to household electrification.  While the target for ensuring electricity connection in each household will be a significant step towards ensuring 24×7 power, the question of continuous and quality supply to these households will still rest on the ability of the discoms to provide electricity.  Further, while the scheme provides for free connections, the ability of these households to pay for the electricity they consume may be a concern.

Table 1: Status of rural electrification across states (as of August 2017)

Fig 1 edit

* all villages in Telangana were declared electrified before the bifurcation of the state.
Sources:  Ministry of Power; PRS.

 

[i] “PM launches Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 25, 2017.

[ii] “FAQs on Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 27, 2017.

[iii].  Rural Electrification Policy, Ministry of Power, August 23, 2006, http://powermin.nic.in/sites/default/files/uploads/RE%20Policy_1.pdf.

[iv].  “Office memorandum: Deendayal Upadhyaya Gram Jyoti Yojana”, Ministry of Power, December 3, 2014, http://powermin.nic.in/rural_electrification/pdf/Deendayal_Upadhyaya_Gram_Jyoti_Yojana.pdf.

[v].  “41st Report: Implementation of Rajiv Gandhi Grameen Vidyutikaran Yojana”, Standing Committee on Energy, December 13, 2013, http://164.100.47.134/lsscommittee/Energy/15_Energy_41.pdf.