According to news reports, the Prime Minister recently chaired a meeting with ministers to discuss an alternative plan (“Plan B”) for the National Food Security Bill, 2011 (hereinafter “Bill”).  The Bill is currently pending with the Standing Committee of Food, Consumer Affairs and Public Distribution.  It seeks to deliver food and nutritional security by providing specific entitlements to certain groups.  The alternative proposal aims to give greater flexibility to states and may bind the centre to a higher food subsidy burden than estimates provided in the Bill.  It suggests changes to the classification of beneficiaries and the percentage of the national population to be covered by the Bill, among others. Classification of beneficiaries The Bill classifies the population into three groups: priority, general and excluded.  Individuals in the priority and general groups would receive 7 kg and 3 kg of foodgrain per person per month respectively at subsidized prices. Plan B suggests doing away with the priority-general distinction.  It classifies the population on the basis of 2 categories: included and excluded.  Those entitled to benefits under the included category will receive a uniform entitlement of 5 kg per person per month. Coverage of population Experts have suggested that the Bill will extend entitlements to roughly 64% of the total population.  Under the Bill, the central government is responsible for determining the percentage of people in each state who will be entitled to benefits under priority and general groups. Plan B suggests extending benefits to 67% of the total population (33% excluded), up from 64% in the Bill.  The Ministry has outlined two options to figure out the number of people in each state that should be included within this 67%.  The first option envisages a uniform exclusion of 33% in each state irrespective of their poverty level.  The second option envisages exclusion of 33% of the national population, which would imply a different proportion excluded in each state depending on their level of prosperity. The Ministry has worked out a criterion to determine the proportion of the population to be included in each state.  The criterion is pegged to a monthly per capita expenditure of Rs 1,215 in rural areas and Rs 1,502 in urban areas based on the 2009-10 NSSO survey. Thus, persons spending less than Rs 40 in rural areas and Rs 50 in urban areas per day will be entitled to foodgrains under the alternative being considered now. Financial estimates Newspaper reports have indicated that the revised proposal will add Rs 7,000 to Rs 10,000 crore per year to the current food subsidy estimate of Rs 1.1 lakh crore.  According to some experts, the total cost of the Bill could range anywhere between Rs 2 lakh crore to Rs 3.5 lakh crore (see here and here).

Recently, the government issued letters de-allocating coal blocks of various companies, based on the recommendations of the  Inter Ministerial Group (IMG).  This post discusses the history behind the de-allocations, the parameters the IMG used while examining the progress of various coal blocks and the action that has been taken by the government. The Comptroller and Auditor General (CAG) released a performance audit report on 'Allocation of Coal Blocks and Augmentation of Coal Production' on August 17, 2012.  Some of the key findings of the Report were:

  • The government failed to conduct competitive bids for the allocation of coal blocks.  This resulted in a benefit of  Rs 1.86 lakh crore (approx.) to private allottees.  The government could have tapped some of this financial benefit by expediting the decision on competitive bidding for allocation of coal blocks.
  • The implementation schedule of a number of coal blocks has been delayed by one to ten years.  This schedule relates to the time frame within which the Mining Plan for the block has to be approved, various clearances have to be submitted, land acquired, etc.
  • From 2005, the Ministry of Coal (MoC) required the allottees to provide bank guarantees which would be encashed if they failed to meet the above mentioned milestones.  The CAG observed that there was a delay in introducing the bank guarantee and linking it with milestones.

The IMG on Coal was constituted for the periodic review of the development of coal blocks and end use plants.  The IMG had requested a status paper from the Coal Controller, MoC.  This has been submitted to the IMG but is not available.  The IMG will decide if private allottees have made substantial progress based on certain parameters.  The parameters used by IMG are:  approval of Mining Plan, status of environment and forest clearance, grant of mining lease and progress made in land acquisition. They are also examining the physical status of End Use Plant (EUP), investment made and the expected date of opening of the mine and commissioning of EUP. The IMG has made the following recommendations:

  • The coal blocks of companies that have not made substantial progress should be de-allocated.  Additionally, they have recommended the deduction of bank guarantee in the cases where the private companies have not reached the milestones as per the time line decided upon.  As of November 22, 2012, the IMG has recommended the de-allocation of the coal blocks listed in Table 1 and the deduction of bank guarantees for the coal blocks in Table 2.
  • Since, the system of bank guarantee was only introduced in March 2005, not all coal blocks had submitted a bank guarantee.  Where a bank guarantee has not been provided but there is substantial progress in meeting the milestones, the IMG may require the allottee to submit a bank guarantee.

[table id=1 /]

 

[table id=5 /]

 

Of the coal blocks that the IMG has recommended for de-allocation, until now the government has accepted the de-allocation of the following: Bramhadih block, Gourangdih, New Patrapara, Chinora block, Warora (Southern Part) block, Lalgarh (North) block, Bhaskarpara block, Dahegaon/Makardhokra-IV block, Gondkhari block and Ramanwara North block.  The government has accepted the deduction of bank guarantees for blocks such as Moitra, Jitpur, Bhaskarpara, Durgapur II/Sariya, Dahegaon/Makardhokra-IV, Marki Mangli II, III and IV, Gondhkari, Lohari, Radhikapur East, Bijahan and Nerad Malegaon. The letters issued by the government de-allocating coal blocks and deducting bank guarantees are available here.

For a detailed summary of the CAG Report, click here.