Over the last couple of weeks, MNREGA is back in the spotlight. The Union Minister for Rural Development wrote to certain states regarding potential misuse of funds, and it was announced that rural development schemes are open to CAG audit.  In large schemes like MNREGA, officials at all levels of government - central, state, district, block, panchayat - have roles to play. This can make it difficult to locate the responsible authority in case implementation issues arise. We list the responsibilities of different government agencies involved in implementation of MNREGA in the Table below.

Stakeholder Responsibilities
Gram Sabha (a) recommending works; (b) conducting social audits on implementation every six months; and (c) functioning as a forum for sharing information.
Gram Panchayat (a) planning works; (b) receiving applications for registration; (c) verifying applications; (d) registering households; (e) issuing job cards, (f) receiving applications for employment; (g) issuing detailed receipts; (h) allotting employment within 15 days of application; (i) executing works; (j) maintaining records; (k) convening Gram Sabha for social audit; and (l) monitoring implementation at the village level.
Intermediate Panchayat (a) consolidating Gram Panchayat plans into a Block plan and (b) monitoring and supervision at the block level.
Programme Officer (PO) (a) ensuring work to applicants within 15 days; (b) scrutinising Gram Panchayat annual development plans; (c) consolidating proposals into a Block plan and submitting to intermediate panchayat; (d) matching employment opportunities with demand for work at the Block level; (e) monitoring and supervising implementation; (f) disposing of complaints; (g) ensuring that Gram Sabha conducts social audits; and (h) payment of unemployment allowance.
District Panchayat (a) finalizing district plans and labour budget; and (b) monitoring and supervising at district level.
District Programme Coordinator (DPC) (a) ensuring that the scheme is implemented according to the Act at the district level; (b) information dissemination; (c) training; (d) consolidating block plans into a district plan; (e) ensuring that administrative and technical approval for projects are obtained on time; (f) release and utilisation of funds; (g) ensuring monitoring of works; (h) muster roll verifications; and (i) submitting monthly progress reports.
State Employment Guarantee Council (SEGC) (a) advising the state government on implementation; (b) evaluate and monitor implementation; (c) determining the "preferred works" to be taken up; (d) recommending the proposal of works to be submitted to the state government; and (e) prepare an annual report to the state legislature.
State Government (a) wide communication of the scheme; (b) setting up the SEGC; (c) setting up a State Employment Guarantee Fund; (d) ensuring that dedicated personnel are in place for implementation, including Gram Rozgar Sahayak, Programme Officer, and technical staff; (e) ensuring state share of the scheme budget is released on time; (f) delegation of financial and administrative powers to the DPC and Programme Officer if necessary; (g) training; (h) establishing a network of professional agencies for technical support and quality control; (i) regular review, monitoring, and evaluation of processes and outcomes; and (j) ensuring accountability and transparency.
Central Employment Guarantee Council (a) advising the central government on MNREGA matters; (b) monitoring and evaluating implementation of the Act; and (c) preparing annual reports on implementation and submitting them to Parliament.
Ministry of Rural Development (a) ensuring resource support to states and the CEGC; (b) regular review, monitoring, and evaluation of processes and outcomes;  (c) maintaining and operating the MIS to capture and track data on critical aspects of implementation; (d) assessing the utilization of resources through a set of performance indicators; (e) supporting innovations that help in improving processes towards the achievement of the objectives of the Act; (f) support the use of Information Technology (IT) to increase the efficiency and transparency of the processes as well as improve interface with the public;  and (g) ensuring that the implementation of NREGA at all levels is sought to be made transparent and accountable to the public..
Source: Operational Guidelines, National Rural Employment Guarantee Scheme, Ministry of Rural Development.

There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,