Over the last couple of weeks, MNREGA is back in the spotlight. The Union Minister for Rural Development wrote to certain states regarding potential misuse of funds, and it was announced that rural development schemes are open to CAG audit.  In large schemes like MNREGA, officials at all levels of government - central, state, district, block, panchayat - have roles to play. This can make it difficult to locate the responsible authority in case implementation issues arise. We list the responsibilities of different government agencies involved in implementation of MNREGA in the Table below.

Stakeholder Responsibilities
Gram Sabha (a) recommending works; (b) conducting social audits on implementation every six months; and (c) functioning as a forum for sharing information.
Gram Panchayat (a) planning works; (b) receiving applications for registration; (c) verifying applications; (d) registering households; (e) issuing job cards, (f) receiving applications for employment; (g) issuing detailed receipts; (h) allotting employment within 15 days of application; (i) executing works; (j) maintaining records; (k) convening Gram Sabha for social audit; and (l) monitoring implementation at the village level.
Intermediate Panchayat (a) consolidating Gram Panchayat plans into a Block plan and (b) monitoring and supervision at the block level.
Programme Officer (PO) (a) ensuring work to applicants within 15 days; (b) scrutinising Gram Panchayat annual development plans; (c) consolidating proposals into a Block plan and submitting to intermediate panchayat; (d) matching employment opportunities with demand for work at the Block level; (e) monitoring and supervising implementation; (f) disposing of complaints; (g) ensuring that Gram Sabha conducts social audits; and (h) payment of unemployment allowance.
District Panchayat (a) finalizing district plans and labour budget; and (b) monitoring and supervising at district level.
District Programme Coordinator (DPC) (a) ensuring that the scheme is implemented according to the Act at the district level; (b) information dissemination; (c) training; (d) consolidating block plans into a district plan; (e) ensuring that administrative and technical approval for projects are obtained on time; (f) release and utilisation of funds; (g) ensuring monitoring of works; (h) muster roll verifications; and (i) submitting monthly progress reports.
State Employment Guarantee Council (SEGC) (a) advising the state government on implementation; (b) evaluate and monitor implementation; (c) determining the "preferred works" to be taken up; (d) recommending the proposal of works to be submitted to the state government; and (e) prepare an annual report to the state legislature.
State Government (a) wide communication of the scheme; (b) setting up the SEGC; (c) setting up a State Employment Guarantee Fund; (d) ensuring that dedicated personnel are in place for implementation, including Gram Rozgar Sahayak, Programme Officer, and technical staff; (e) ensuring state share of the scheme budget is released on time; (f) delegation of financial and administrative powers to the DPC and Programme Officer if necessary; (g) training; (h) establishing a network of professional agencies for technical support and quality control; (i) regular review, monitoring, and evaluation of processes and outcomes; and (j) ensuring accountability and transparency.
Central Employment Guarantee Council (a) advising the central government on MNREGA matters; (b) monitoring and evaluating implementation of the Act; and (c) preparing annual reports on implementation and submitting them to Parliament.
Ministry of Rural Development (a) ensuring resource support to states and the CEGC; (b) regular review, monitoring, and evaluation of processes and outcomes;  (c) maintaining and operating the MIS to capture and track data on critical aspects of implementation; (d) assessing the utilization of resources through a set of performance indicators; (e) supporting innovations that help in improving processes towards the achievement of the objectives of the Act; (f) support the use of Information Technology (IT) to increase the efficiency and transparency of the processes as well as improve interface with the public;  and (g) ensuring that the implementation of NREGA at all levels is sought to be made transparent and accountable to the public..
Source: Operational Guidelines, National Rural Employment Guarantee Scheme, Ministry of Rural Development.

Authored by Anil Nair and CV Madhukar PRS just concluded a workshop for MLAs from 50+ from more than a dozen states.  What an AMAZING experience this was, even though this is the sixth such workshop we have held in this past year! This three day workshop on 'Mastering the Budget' was designed to help MLAs understand how to work with budget documents and numbers, find trends, understand the most critical macro numbers to track, etc. The second day of the workshop was tailored to reflect on the big thematic issues that have an impact on state finances. The Fiscal Responsibility and Budget Management Act, the Goods and Services Tax, the pattern of quantum of funds flow from the Centre to the state and local governments, the 13th Finance Commission, etc. The final day was devoted to doing an inter-state comparison of states on important budget parameters, and gleaning lessons from them. The idea for this budget workshop germinated at a previous workshop held at IIM Bangalore. The participating MLAs requested PRS to organise a special session on 'Mastering the Budget'. So this workshop was being organised as a result of their feedback. The choice of location was easy -- this was held at the National Institute for Public Finance and Policy in Delhi, which is amongst India's foremost institutions working on state budgets and public finance issues. Invitations were sent out to MLAs in several states. Responses started coming in within a few days, with about 70 confirmations. But there is always an uncertainty on the participation until the very last minute because elected politicians have immense demands on their time, at least some of which are unpredictable. So it was heartening to see that more than 50 MLAs came to the workshop representing 15 states -- Bihar, Rajasthan, Odisha, Uttar Pradesh, Assam, Kerala, West Bengal, Andhra Pradesh, Meghalaya, Tamil Nadu, Madhya Pradesh, Himachal Pradesh, Gujarat, Haryana, Manipur. The participants ranged from first time MLAs (about 50%), to a sitting Minister, a sitting Speaker, former Ministers, and senior leaders of political parties from some states. But the best part about the interaction in this workshop was that even on seemingly complex issues being discussed in the classroom, the MLAs were not mere recipients of 'gyan' that was being dished out. They had important questions to raise, and well articulated points of disagreement with the faculty, and brought in practical perspectives that might not have otherwise come up in the discussions. They went beyond the scope of the workshop to engage the economists on discussions on subjects like FDI in retail, state of India’s economy… Based on our experience of several workshops with MLAs, we want to share some observations about the participating MLAs: -         There are MLAs in every state who want to understand substantive policy issues, and are willing to invest time and energy to do so. -         When the MLAs participate in these workshops, they choose to do so on their own, and are not compelled by anyone to do so. -         The sessions almost always begin and end on time, even in the freezing cold mornings in the Delhi winter. -         The MLAs are very engaged in the discussions, ask questions, and bring in their experiences into the classroom discussions. -         They keep partylines completely out of the substantive classroom discussions, and in the rare event that some new participant mentions anything partisan, other participants quickly ask him to avoid making any such mentions. In 2011, we have engaged with over 250 MLAs through these workshops and more. These workshops are just a starting point of what we hope will develop into a sustained, longer term engagement with MLAs on policy issues coming up in their states. In an important partnership with the Indian School of Business, Hyderabad, PRS has already conducted two workshops  at the world class facilities at the ISB campus, and is planning to hold more in 2012. Just as PRS engages with about 300 MPs in Parliament, the hope is that more MLAs will be able to derive value from the work of PRS in the years to come, thereby making their decisions better informed. Some feedback from MLAs from our earlier workshops can be seen here: http://www.youtube.com/watch?v=9XlgKCp2bvs or http://www.youtube.com/watch?v=01kLLTVtJOU&feature=related or http://www.youtube.com/watch?v=WA4NZqCj2xk&feature=related