The Land Acquisition Bill is slated to be taken up for consideration and passing in the Lok Sabha today. The government had circulated an amendment list in the last session of Parliament. In a column in the Financial Express, MR Madhavan discusses the major features of the Land Acquisition Bill and the associated issues that Parliament may need to consider while deliberating on the Bill. Economic growth and job creation require efficient usage of land resources. It is important that a fair and transparent process for purchase and for acquisition of land is followed. For the purchase of land, a key concern is the authenticity of land titles, and the government has drafted a Land Titling Bill for this purpose. In the case of land acquisition, the following questions need to be addressed. What are the end-uses for which public interests will trump private property rights, and justify acquisition of land from a person who is not willing to part with it? What should be the process followed? Since there is no market mechanism of discovery of prices in these cases, how should compensation be computed? Is there a need to address non-land owners who may be displaced by the acquisition process? Does the acquisition process get completed in a reasonable amount of time, and is there finality to the acquisition? In sum, do both sides—the acquirer and the land owner—perceive the process to be fair? The current Bill addresses these questions in the following manner. It defines public purpose to include infrastructure projects (as defined by the finance ministry, with some exclusions); projects related to agriculture, agro-processing and cold storage; industrial corridors, mining activities, national investment and manufacturing zones; government administered or aided educational and research institutions; sports, healthcare, transport and space programmes. It also enables the government to include other infrastructural facilities to this list after tabling a notification in Parliament. The significant difference from the current Land Acquisition Act, 1894, is that land cannot be acquired for use by companies unless they satisfy any of the above end-uses. The Bill includes a requirement for consent of the land owners in some cases. If the land is acquired for use by a private company, 80% of land owners need to give consent. If it is for use by a public private partnership (PPP), 70% of the land owners have to agree to the acquisition. The rationale of having differential consent requirements based on ownership—including the lack of any such requirement if the land is for the use of the government or a public sector undertaking—is not clear. Why should a land owner, who is losing his land care, whether the intended project is to be executed by the government or a private company? The Bill specifies that the compensation will be computed in the following manner. Three factors are taken into account: the circle rate according to the Stamp Act; the average of the top 50% of sale deeds registered in the vicinity in the previous three years; the amount agreed upon, if any, in case of purchase by a private company or PPP. The higher of these three amounts is multiplied by a factor, which varies from 1 in urban areas to a number between 1 and 2 in rural areas, depending upon the distance from the urban centre. To this amount, the value of any fixed assets such as buildings, trees, irrigation channels etc is added. Finally, this figure is doubled (as solatium, i.e. compensation for the fact that the transaction was made with an unwilling seller). The justification given for the multiplier ranging from 1 to 2 is that many transactions are registered at a price significantly lower than the actual value in order to evade taxes—the moot question is whether such under-reporting is uniform across the country? The Bill states that all persons who are affected by the project should be rehabilitated and resettled (R&R). The R&R entitlements for each family includes a house, a one-time allowance, and choice of (a) employment for one person in the project, (b) one-time payment of R5 lakh, or (c) inflation adjusted annuity of R2,000 per month for 20 years. In addition, the resettlement areas should have infrastructure such as a school, post office, roads, drainage, drinking water, etc. The process has several steps. Every acquisition, regardless of size, needs a social impact assessment, which will be reviewed by an expert committee, and evaluated by the state government. Then a preliminary notification will be issued, land records will be updated, objections will be heard, rehabilitation and resettlement survey carried out, and a final declaration of acquisition issued. The owners can then claim compensation, the final award will be announced, and the possession of the land taken. The total time for this process can last up to 50 months. The big question is whether this time frame would hinder economic development and the viability of projects? The Bill provides for an Authority to adjudicate disputes related to measurement of land, compensation payable, R&R etc, with appeals to be heard by the High Court. There are several restrictions on the land acquired. The purpose for which land is acquired cannot be changed. If land is not used for five years, it would be transferred to a land bank or the original owners. Transfer of ownership needs prior permission, and in case of transfer in the first five years, 40% of capital gains have to be shared with the original owners. Recent cases of land acquisition have been followed by public protests, and the stalling of the acquisition. Whereas some of these may be driven by political agendas, the old Act was perceived to be unfair to land owners in several ways. The challenge for Parliament is to examine the new Bill and craft the law in such a way that it is fair (and perceived as such) to land owners, while making acquisition feasible and practical for projects that are required for economic development and other areas of public interest.

Recently, the government issued letters de-allocating coal blocks of various companies, based on the recommendations of the  Inter Ministerial Group (IMG).  This post discusses the history behind the de-allocations, the parameters the IMG used while examining the progress of various coal blocks and the action that has been taken by the government. The Comptroller and Auditor General (CAG) released a performance audit report on 'Allocation of Coal Blocks and Augmentation of Coal Production' on August 17, 2012.  Some of the key findings of the Report were:

  • The government failed to conduct competitive bids for the allocation of coal blocks.  This resulted in a benefit of  Rs 1.86 lakh crore (approx.) to private allottees.  The government could have tapped some of this financial benefit by expediting the decision on competitive bidding for allocation of coal blocks.
  • The implementation schedule of a number of coal blocks has been delayed by one to ten years.  This schedule relates to the time frame within which the Mining Plan for the block has to be approved, various clearances have to be submitted, land acquired, etc.
  • From 2005, the Ministry of Coal (MoC) required the allottees to provide bank guarantees which would be encashed if they failed to meet the above mentioned milestones.  The CAG observed that there was a delay in introducing the bank guarantee and linking it with milestones.

The IMG on Coal was constituted for the periodic review of the development of coal blocks and end use plants.  The IMG had requested a status paper from the Coal Controller, MoC.  This has been submitted to the IMG but is not available.  The IMG will decide if private allottees have made substantial progress based on certain parameters.  The parameters used by IMG are:  approval of Mining Plan, status of environment and forest clearance, grant of mining lease and progress made in land acquisition. They are also examining the physical status of End Use Plant (EUP), investment made and the expected date of opening of the mine and commissioning of EUP. The IMG has made the following recommendations:

  • The coal blocks of companies that have not made substantial progress should be de-allocated.  Additionally, they have recommended the deduction of bank guarantee in the cases where the private companies have not reached the milestones as per the time line decided upon.  As of November 22, 2012, the IMG has recommended the de-allocation of the coal blocks listed in Table 1 and the deduction of bank guarantees for the coal blocks in Table 2.
  • Since, the system of bank guarantee was only introduced in March 2005, not all coal blocks had submitted a bank guarantee.  Where a bank guarantee has not been provided but there is substantial progress in meeting the milestones, the IMG may require the allottee to submit a bank guarantee.

[table id=1 /]

 

[table id=5 /]

 

Of the coal blocks that the IMG has recommended for de-allocation, until now the government has accepted the de-allocation of the following: Bramhadih block, Gourangdih, New Patrapara, Chinora block, Warora (Southern Part) block, Lalgarh (North) block, Bhaskarpara block, Dahegaon/Makardhokra-IV block, Gondkhari block and Ramanwara North block.  The government has accepted the deduction of bank guarantees for blocks such as Moitra, Jitpur, Bhaskarpara, Durgapur II/Sariya, Dahegaon/Makardhokra-IV, Marki Mangli II, III and IV, Gondhkari, Lohari, Radhikapur East, Bijahan and Nerad Malegaon. The letters issued by the government de-allocating coal blocks and deducting bank guarantees are available here.

For a detailed summary of the CAG Report, click here.