The Land Acquisition Bill is slated to be taken up for consideration and passing in the Lok Sabha today. The government had circulated an amendment list in the last session of Parliament. In a column in the Financial Express, MR Madhavan discusses the major features of the Land Acquisition Bill and the associated issues that Parliament may need to consider while deliberating on the Bill. Economic growth and job creation require efficient usage of land resources. It is important that a fair and transparent process for purchase and for acquisition of land is followed. For the purchase of land, a key concern is the authenticity of land titles, and the government has drafted a Land Titling Bill for this purpose. In the case of land acquisition, the following questions need to be addressed. What are the end-uses for which public interests will trump private property rights, and justify acquisition of land from a person who is not willing to part with it? What should be the process followed? Since there is no market mechanism of discovery of prices in these cases, how should compensation be computed? Is there a need to address non-land owners who may be displaced by the acquisition process? Does the acquisition process get completed in a reasonable amount of time, and is there finality to the acquisition? In sum, do both sides—the acquirer and the land owner—perceive the process to be fair? The current Bill addresses these questions in the following manner. It defines public purpose to include infrastructure projects (as defined by the finance ministry, with some exclusions); projects related to agriculture, agro-processing and cold storage; industrial corridors, mining activities, national investment and manufacturing zones; government administered or aided educational and research institutions; sports, healthcare, transport and space programmes. It also enables the government to include other infrastructural facilities to this list after tabling a notification in Parliament. The significant difference from the current Land Acquisition Act, 1894, is that land cannot be acquired for use by companies unless they satisfy any of the above end-uses. The Bill includes a requirement for consent of the land owners in some cases. If the land is acquired for use by a private company, 80% of land owners need to give consent. If it is for use by a public private partnership (PPP), 70% of the land owners have to agree to the acquisition. The rationale of having differential consent requirements based on ownership—including the lack of any such requirement if the land is for the use of the government or a public sector undertaking—is not clear. Why should a land owner, who is losing his land care, whether the intended project is to be executed by the government or a private company? The Bill specifies that the compensation will be computed in the following manner. Three factors are taken into account: the circle rate according to the Stamp Act; the average of the top 50% of sale deeds registered in the vicinity in the previous three years; the amount agreed upon, if any, in case of purchase by a private company or PPP. The higher of these three amounts is multiplied by a factor, which varies from 1 in urban areas to a number between 1 and 2 in rural areas, depending upon the distance from the urban centre. To this amount, the value of any fixed assets such as buildings, trees, irrigation channels etc is added. Finally, this figure is doubled (as solatium, i.e. compensation for the fact that the transaction was made with an unwilling seller). The justification given for the multiplier ranging from 1 to 2 is that many transactions are registered at a price significantly lower than the actual value in order to evade taxes—the moot question is whether such under-reporting is uniform across the country? The Bill states that all persons who are affected by the project should be rehabilitated and resettled (R&R). The R&R entitlements for each family includes a house, a one-time allowance, and choice of (a) employment for one person in the project, (b) one-time payment of R5 lakh, or (c) inflation adjusted annuity of R2,000 per month for 20 years. In addition, the resettlement areas should have infrastructure such as a school, post office, roads, drainage, drinking water, etc. The process has several steps. Every acquisition, regardless of size, needs a social impact assessment, which will be reviewed by an expert committee, and evaluated by the state government. Then a preliminary notification will be issued, land records will be updated, objections will be heard, rehabilitation and resettlement survey carried out, and a final declaration of acquisition issued. The owners can then claim compensation, the final award will be announced, and the possession of the land taken. The total time for this process can last up to 50 months. The big question is whether this time frame would hinder economic development and the viability of projects? The Bill provides for an Authority to adjudicate disputes related to measurement of land, compensation payable, R&R etc, with appeals to be heard by the High Court. There are several restrictions on the land acquired. The purpose for which land is acquired cannot be changed. If land is not used for five years, it would be transferred to a land bank or the original owners. Transfer of ownership needs prior permission, and in case of transfer in the first five years, 40% of capital gains have to be shared with the original owners. Recent cases of land acquisition have been followed by public protests, and the stalling of the acquisition. Whereas some of these may be driven by political agendas, the old Act was perceived to be unfair to land owners in several ways. The challenge for Parliament is to examine the new Bill and craft the law in such a way that it is fair (and perceived as such) to land owners, while making acquisition feasible and practical for projects that are required for economic development and other areas of public interest.

On October 16, the Group of Experts on Privacy, Chaired by Mr. A. P. Shah, submitted its Report to the Planning Commission.  The Expert Group was appointed to set out the principles that Indian privacy law should abide by.   Even though privacy has been held to be a fundamental right as long back as in 1962, India does not have a law that specifies safeguards to privacy.  Moreover, recent government initiatives, such as the UID, involve collection of personal information and storage in electronic form.  The absence of a law on privacy increases the risk to infringement of the fundamental right. In this blog we list the recommendations made by the expert group, discuss the status of the right to privacy in India, and why there is a need for an enactment. Recommendations of the Expert Group on Privacy

  • The Expert Group recommended that the new legislation on privacy should ensure that safeguards are technology neutral.  This means that the enactment should provide protections that are applicable to information, regardless of the manner in which it is stored: digital or physical form.
  • The new legislation should protect all types of privacy, such as bodily privacy (DNA and physical privacy); privacy against surveillance (unauthorised interception, audio and video surveillance); and data protection.
  • The safeguards under the Bill should apply to both government and private sector entities.
  • There should be an office of a ‘Privacy Commissioner’ at both the central and regional level.
  • There should be Self-Regulating Organisations set up by the industry.  These organisations would develop a baseline legal framework that protects and enforces an individual’s right to privacy.  The standards developed by the organisations would have to be approved by the Commissioner.
  • The legislation should ensure that entities that collect and process data would be accountable for these processes and the use to which the data is put.  This, according to the Group, would ensure that the privacy of the data subject is guaranteed.

Present status of the Right to Privacy While the Supreme Court has held privacy to be a fundamental right, it is restricted to certain aspects of a person’s life.  These aspects include the privacy of one’s home, family, marriage, motherhood, procreation and child-rearing.  Therefore, to claim privacy in any other aspect, individuals have to substantiate these are ‘private’ and should not be subjected to state or private interference.  For instance, in 1996 petitioners had to argue before the Court that the right to speak privately over the telephone was a fundamental right. Risks to privacy Government departments collect data under various legislations.  For instance, under the Passport Act, 1967 and the Motor Vehicles Act, 1988 persons have to give details of their address, date of birth etc.  These enactments do not provide safeguards against access and use of the information by third parties.  Similarly, information regarding ownership of property and taxes paid are publicly available on the MCD website. Furthermore, recent government initiatives may increase the risk to infringement of privacy as personal information, previously only available in physical form, will now be available electronically.  Initiatives such as the National e-Governance Plan, introduced in 2006 and Aadhaar would require maintenance of information in electronic form.  The Aadhaar initiative aims at setting up a system for identifying beneficiaries of government sponsored schemes.  Under the initiative, biometric details of the beneficiaries, such as retina scan and fingerprints, are collected and stored by the government.  The government has also introduced a Bill in Parliament creating a right to electronic service delivery.  As per news reports, a draft DNA Profiling Bill is also in the pipeline.