The Land Acquisition Bill is slated to be taken up for consideration and passing in the Lok Sabha today. The government had circulated an amendment list in the last session of Parliament. In a column in the Financial Express, MR Madhavan discusses the major features of the Land Acquisition Bill and the associated issues that Parliament may need to consider while deliberating on the Bill. Economic growth and job creation require efficient usage of land resources. It is important that a fair and transparent process for purchase and for acquisition of land is followed. For the purchase of land, a key concern is the authenticity of land titles, and the government has drafted a Land Titling Bill for this purpose. In the case of land acquisition, the following questions need to be addressed. What are the end-uses for which public interests will trump private property rights, and justify acquisition of land from a person who is not willing to part with it? What should be the process followed? Since there is no market mechanism of discovery of prices in these cases, how should compensation be computed? Is there a need to address non-land owners who may be displaced by the acquisition process? Does the acquisition process get completed in a reasonable amount of time, and is there finality to the acquisition? In sum, do both sides—the acquirer and the land owner—perceive the process to be fair? The current Bill addresses these questions in the following manner. It defines public purpose to include infrastructure projects (as defined by the finance ministry, with some exclusions); projects related to agriculture, agro-processing and cold storage; industrial corridors, mining activities, national investment and manufacturing zones; government administered or aided educational and research institutions; sports, healthcare, transport and space programmes. It also enables the government to include other infrastructural facilities to this list after tabling a notification in Parliament. The significant difference from the current Land Acquisition Act, 1894, is that land cannot be acquired for use by companies unless they satisfy any of the above end-uses. The Bill includes a requirement for consent of the land owners in some cases. If the land is acquired for use by a private company, 80% of land owners need to give consent. If it is for use by a public private partnership (PPP), 70% of the land owners have to agree to the acquisition. The rationale of having differential consent requirements based on ownership—including the lack of any such requirement if the land is for the use of the government or a public sector undertaking—is not clear. Why should a land owner, who is losing his land care, whether the intended project is to be executed by the government or a private company? The Bill specifies that the compensation will be computed in the following manner. Three factors are taken into account: the circle rate according to the Stamp Act; the average of the top 50% of sale deeds registered in the vicinity in the previous three years; the amount agreed upon, if any, in case of purchase by a private company or PPP. The higher of these three amounts is multiplied by a factor, which varies from 1 in urban areas to a number between 1 and 2 in rural areas, depending upon the distance from the urban centre. To this amount, the value of any fixed assets such as buildings, trees, irrigation channels etc is added. Finally, this figure is doubled (as solatium, i.e. compensation for the fact that the transaction was made with an unwilling seller). The justification given for the multiplier ranging from 1 to 2 is that many transactions are registered at a price significantly lower than the actual value in order to evade taxes—the moot question is whether such under-reporting is uniform across the country? The Bill states that all persons who are affected by the project should be rehabilitated and resettled (R&R). The R&R entitlements for each family includes a house, a one-time allowance, and choice of (a) employment for one person in the project, (b) one-time payment of R5 lakh, or (c) inflation adjusted annuity of R2,000 per month for 20 years. In addition, the resettlement areas should have infrastructure such as a school, post office, roads, drainage, drinking water, etc. The process has several steps. Every acquisition, regardless of size, needs a social impact assessment, which will be reviewed by an expert committee, and evaluated by the state government. Then a preliminary notification will be issued, land records will be updated, objections will be heard, rehabilitation and resettlement survey carried out, and a final declaration of acquisition issued. The owners can then claim compensation, the final award will be announced, and the possession of the land taken. The total time for this process can last up to 50 months. The big question is whether this time frame would hinder economic development and the viability of projects? The Bill provides for an Authority to adjudicate disputes related to measurement of land, compensation payable, R&R etc, with appeals to be heard by the High Court. There are several restrictions on the land acquired. The purpose for which land is acquired cannot be changed. If land is not used for five years, it would be transferred to a land bank or the original owners. Transfer of ownership needs prior permission, and in case of transfer in the first five years, 40% of capital gains have to be shared with the original owners. Recent cases of land acquisition have been followed by public protests, and the stalling of the acquisition. Whereas some of these may be driven by political agendas, the old Act was perceived to be unfair to land owners in several ways. The challenge for Parliament is to examine the new Bill and craft the law in such a way that it is fair (and perceived as such) to land owners, while making acquisition feasible and practical for projects that are required for economic development and other areas of public interest.

In law, the addition or deletion a single punctuation or a single word can have a major impact on the effect of that law.  One such example can be seen from the recommended changes in the Civil Liability for Nuclear Damage Bill, 2010 by Parliament’s Standing Committee. The Civil Liability for Nuclear Damage Bill, 2010 was introduced in the Lok Sabha on May 7, 2010.  The Bill was referred to the Parliamentary Committee on Science and Technology, Environment and Forests, which submitted its report on the Bill yesterday (August 18, 2010).  The Committee has made a number of recommendations regarding certain clauses in the Bill (See summary here).  One of these may have the effect of diluting the provision currently in the Bill.  The main recommendations pertain to:

  • Preventing the entry of private operators.
  • Allowing the government to increase the total liability for a nuclear incident by notification, but not decrease it.
  • Increasing the liability of the operator to Rs 1,500 crore from Rs 500 crore.
  • Increasing the time limit for claiming compensation to 20 years from 10 years.
  • Changing the provision giving operators a right of recourse against persons actually responsible for causing damage.

Clause 17 of the Bill which gives operators a right of recourse against those actually causing damage had been opposed as it was felt that it was not strong enough to hold suppliers liable in case the damage was caused by them.  Clause 17 gave a right of recourse under three conditions.  The exact clause is reproduced below: The operator of a nuclear installation shall have a right of recourse where — (a) such right is expressly provided for in a contract in writing; (b) the nuclear incident has resulted from the wilful act or gross negligence on the part of the supplier of the material, equipment or services, or of his employee; (c) the nuclear incident has resulted from the act of commission or omission of a person done with the intent to cause nuclear damage. Under this clause, a right of recourse exists when (a) there is a contract giving such a right, or (b) the supplier acts deliberately or in a grossly negligent manner to cause nuclear damage, or (c) a person causes nuclear damage with the intent to do so.  If any of the three cases can be proved by the operator, he has a right of recourse. The Committee has stated that “Clause 17(b) gives escape route to the suppliers of nuclear materials, equipments, services of his employees as their willful act or gross negligence would be difficult to establish in a civil nuclear compensation case.” It recommended that Clause 17(b) should be modified to cover consequences “of latent or patent defect, supply of sub-standard material, defective equipment or services or from the gross negligence on the part of the supplier of the material, equipment or service.” The Committee also recommended another change in Clause 17.  It recommended that clause 17(a) may end with “and”. This provision may dilute the right of recourse available to operators.  The modified clause 17 would read as: The operator of a nuclear installation shall have a right of recourse where — (a) such right is expressly provided for in a contract in writing; and, (b) the nuclear incident has resulted as a consequence of latent or patent defect, supply of sub-standard material, defective equipment or services or from the gross negligence on the part of the supplier of the material, equipment or services.; (c) the nuclear incident has resulted from the act of commission or omission of a person done with the intent to cause nuclear damage. This implies that for Clauses 17(b) or (c) to be applicable, the condition specified in clause 17(a) has to be compulsorily satisfied.  Two examples highlight the consequence of the recommended change in Clause 17(a) of the Bill:

  1. A person X deliberately commits sabotage in a nuclear plant and causes damage.  Under the Bill, the operator has recourse under Clause 17(c).  If the recommendation regarding clause 17 is accepted, the operator may also have to also prove the existence of a pre-existing contract with X in addition to clause 17(c).
  2. If a supplier supplies defective equipment, but does not have a contract in writing stating that he will be liable for damage caused by defective equipment, the operator may not have a right of recourse against the supplier under 17(b).

The effect of the changes recommended by the committee may thus dilute the provision as it exists in the Bill.  The table below compares the position in the Bill and the position as per the Standing Committee’s recommendations:

Right of recourse - The Bill gives operators a right to recourse under three conditions:  (a) if there is a clear contract; (b) if the damage is caused by someone with intent to cause damage; (c) against suppliers if damage is caused by their wilful act or negligence. In the Bill the three conditions are separated by a semi-colon.  The Committee recommended that the semi-colon in clause 17(a) should be replaced by “and”. This might imply that all three conditions mentioned need to exist for an operator to have recourse.
Right to recourse against suppliers exists in cases of “willful act or gross negligence on the part of the supplier”. (Clause 17) The Committee felt that the right of recourse against suppliers is vague.  It recommended that recourse against the supplier should be strengthened.  The supplier is liable if an incident has occurred due to (i) defects, or (ii) sub-standard material, or (iii) gross negligence of the supplier of the material, equipment or services. The variance with the Convention continues to exist.