The Land Acquisition Bill is slated to be taken up for consideration and passing in the Lok Sabha today. The government had circulated an amendment list in the last session of Parliament. In a column in the Financial Express, MR Madhavan discusses the major features of the Land Acquisition Bill and the associated issues that Parliament may need to consider while deliberating on the Bill. Economic growth and job creation require efficient usage of land resources. It is important that a fair and transparent process for purchase and for acquisition of land is followed. For the purchase of land, a key concern is the authenticity of land titles, and the government has drafted a Land Titling Bill for this purpose. In the case of land acquisition, the following questions need to be addressed. What are the end-uses for which public interests will trump private property rights, and justify acquisition of land from a person who is not willing to part with it? What should be the process followed? Since there is no market mechanism of discovery of prices in these cases, how should compensation be computed? Is there a need to address non-land owners who may be displaced by the acquisition process? Does the acquisition process get completed in a reasonable amount of time, and is there finality to the acquisition? In sum, do both sides—the acquirer and the land owner—perceive the process to be fair? The current Bill addresses these questions in the following manner. It defines public purpose to include infrastructure projects (as defined by the finance ministry, with some exclusions); projects related to agriculture, agro-processing and cold storage; industrial corridors, mining activities, national investment and manufacturing zones; government administered or aided educational and research institutions; sports, healthcare, transport and space programmes. It also enables the government to include other infrastructural facilities to this list after tabling a notification in Parliament. The significant difference from the current Land Acquisition Act, 1894, is that land cannot be acquired for use by companies unless they satisfy any of the above end-uses. The Bill includes a requirement for consent of the land owners in some cases. If the land is acquired for use by a private company, 80% of land owners need to give consent. If it is for use by a public private partnership (PPP), 70% of the land owners have to agree to the acquisition. The rationale of having differential consent requirements based on ownership—including the lack of any such requirement if the land is for the use of the government or a public sector undertaking—is not clear. Why should a land owner, who is losing his land care, whether the intended project is to be executed by the government or a private company? The Bill specifies that the compensation will be computed in the following manner. Three factors are taken into account: the circle rate according to the Stamp Act; the average of the top 50% of sale deeds registered in the vicinity in the previous three years; the amount agreed upon, if any, in case of purchase by a private company or PPP. The higher of these three amounts is multiplied by a factor, which varies from 1 in urban areas to a number between 1 and 2 in rural areas, depending upon the distance from the urban centre. To this amount, the value of any fixed assets such as buildings, trees, irrigation channels etc is added. Finally, this figure is doubled (as solatium, i.e. compensation for the fact that the transaction was made with an unwilling seller). The justification given for the multiplier ranging from 1 to 2 is that many transactions are registered at a price significantly lower than the actual value in order to evade taxes—the moot question is whether such under-reporting is uniform across the country? The Bill states that all persons who are affected by the project should be rehabilitated and resettled (R&R). The R&R entitlements for each family includes a house, a one-time allowance, and choice of (a) employment for one person in the project, (b) one-time payment of R5 lakh, or (c) inflation adjusted annuity of R2,000 per month for 20 years. In addition, the resettlement areas should have infrastructure such as a school, post office, roads, drainage, drinking water, etc. The process has several steps. Every acquisition, regardless of size, needs a social impact assessment, which will be reviewed by an expert committee, and evaluated by the state government. Then a preliminary notification will be issued, land records will be updated, objections will be heard, rehabilitation and resettlement survey carried out, and a final declaration of acquisition issued. The owners can then claim compensation, the final award will be announced, and the possession of the land taken. The total time for this process can last up to 50 months. The big question is whether this time frame would hinder economic development and the viability of projects? The Bill provides for an Authority to adjudicate disputes related to measurement of land, compensation payable, R&R etc, with appeals to be heard by the High Court. There are several restrictions on the land acquired. The purpose for which land is acquired cannot be changed. If land is not used for five years, it would be transferred to a land bank or the original owners. Transfer of ownership needs prior permission, and in case of transfer in the first five years, 40% of capital gains have to be shared with the original owners. Recent cases of land acquisition have been followed by public protests, and the stalling of the acquisition. Whereas some of these may be driven by political agendas, the old Act was perceived to be unfair to land owners in several ways. The challenge for Parliament is to examine the new Bill and craft the law in such a way that it is fair (and perceived as such) to land owners, while making acquisition feasible and practical for projects that are required for economic development and other areas of public interest.

The Civil Liability for Nuclear Damage Bill, 2010 was introduced in the Lok Sabha on may 7, 2010.  The following is PRS’s summary of the Bill (The Bill summary and the Bill along with related media articles can also be accessed on the PRS Website):

The main features of the Bill are:

a. It defines nuclear incidents and nuclear damage, nuclear fuel, material and nuclear installations, and also operators of nuclear installations.

b. It lays down who will be liable for nuclear damage, and the financial limit of the liability for a nuclear incident.

c. It creates authorities who will assess claims and distribute compensation in cases of nuclear damage. It also specifies who can claim compensation for nuclear damage, and how compensation can be claimed and distributed.

d. It specifies penalties for not complying with the provisions of the Bill, or any directions issued under it.

Nuclear damage means (a) loss of life or injury to a person, or loss of, or damage to property caused by a nuclear incident (b) economic loss arising out of such damage to person or property, (c) costs of measures to repair the damage caused to the environment, and (d) costs of preventive measures.

The Atomic Energy Regulatory Board has to notify a nuclear incident within 15 days from the date of a nuclear incident occurring.

The operator of a nuclear installation will be liable for nuclear damage caused by a nuclear incident in that installation or if he is in charge of nuclear material. If more than one operator is liable for nuclear damage, all operators shall be jointly, and also individually liable to pay compensation for the damage. The Bill also provides certain exceptions to an operator’s liability.

The operator has a right of recourse against the supplier and other individuals responsible for the damage under certain conditions.

The Bill states that the total liability for a nuclear incident shall not exceed 300 million Special Drawing Rights (Approximately Rs 2100 crore at current exchange rates).

Within this amount, the liability of the operator shall be Rs 500 crore. If the liability exceeds Rs 500 crore, the central government shall be liable for the amount exceeding Rs 500 crore (up to SDR 300 million). If damage is caused in a nuclear installation owned by the central government, the government will be solely liable.

The Bill allows the central government to create two authorities by notification:

a. Claims Commissioner: The Claims Commissioner will have certain powers of a civil court. Once a nuclear incident is notified, the Commissioner will invite applications for claiming compensation.

b. Nuclear Damage Claims Commission: If the central government thinks that with regard to a nuclear incident (a) the amount of compensation may exceed Rs 500 crore, or (b) it is necessary that claims will be heard by the Commission and not the Claims Commissioner, or (c) that it is in public interest, it can establish a Nuclear Damage Claims Commission. The Commission shall have the same powers as that of a Claims Commissioner.

An application for claiming compensation can be made by (a) person sustaining the injury, (b) owner of the damaged property, (c) legal representative of a deceased person, or (d) an authorised agent. An application can be made within three years from the date of the person having knowledge of nuclear damage. This right to make an application is however exhausted after a period of ten years from the date of the notification of the nuclear incident.

he Civil Liability for Nuclear Damage Bill, 2010 was introduced in the Lok Sabha on May 7, 2010. The main features of the Bill are:

a. It defines nuclear incidents and nuclear damage, nuclear fuel, material and nuclear installations, and also operators of nuclear installations.

b. It lays down who will be liable for nuclear damage, and the financial limit of the liability for a nuclear incident.

c. It creates authorities who will assess claims and distribute compensation in cases of nuclear damage. It also specifies who can claim compensation for nuclear damage, and how compensation can be claimed and distributed.

d. It specifies penalties for not complying with the provisions of the Bill, or any directions issued under it.

§ Nuclear damage means (a) loss of life or injury to a person, or loss of, or damage to property caused by a nuclear incident (b) economic loss arising out of such damage to person or property, (c) costs of measures to repair the damage caused to the environment, and (d) costs of preventive measures.

§ The Atomic Energy Regulatory Board has to notify a nuclear incident within 15 days from the date of a nuclear incident occurring.

§ The operator of a nuclear installation will be liable for nuclear damage caused by a nuclear incident in that installation or if he is in charge of nuclear material. If more than one operator is liable for nuclear damage, all operators shall be jointly, and also individually liable to pay compensation for the damage. The Bill also provides certain exceptions to an operator’s liability.

§ The operator has a right of recourse against the supplier and other individuals responsible for the damage under certain conditions.

§ The Bill states that the total liability for a nuclear incident shall not exceed 300 million Special Drawing Rights (Approximately Rs 2100 crore at current exchange rates).

§ Within this amount, the liability of the operator shall be Rs 500 crore. If the liability exceeds Rs 500 crore, the central government shall be liable for the amount exceeding Rs 500 crore (up to SDR 300 million). If damage is caused in a nuclear installation owned by the central government, the government will be solely liable.

§ The Bill allows the central government to create two authorities by notification:

a. Claims Commissioner: The Claims Commissioner will have certain powers of a civil court. Once a nuclear incident is notified, the Commissioner will invite applications for claiming compensation.

b. Nuclear Damage Claims Commission: If the central government thinks that with regard to a nuclear incident (a) the amount of compensation may exceed Rs 500 crore, or (b) it is necessary that claims will be heard by the Commission and not the Claims Commissioner, or (c) that it is in public interest, it can establish a Nuclear Damage Claims Commission. The Commission shall have the same powers as that of a Claims Commissioner.

An application for claiming compensation can be made by (a) person sustaining the injury, (b) owner of the damaged property, (c) legal representative of a deceased person, or (d) an authorised agent. An application can be made within three years from the date of the person having knowledge of nuclear damage. This right to make an application is however exhausted after a period of ten years from the date of the notification of the nuclear incident.