In a recent judgement (Judgement on Feb 23 - Baldev Singh and Ors. V. State of Punjab), the Supreme Court reduced the sentence of three persons convicted of rape from 10 years to 3 and a half years, and also asked the three convicts to pay a fine of Rs 50,000 each to the victim.   In reducing the sentence, the court drew from the provision in S. 376 (punishment for rape) of the Indian Penal Code which allows the court to reduce the sentence for "adequate and special reasons". There have been a number of past cases where the Supreme Court has reversed High Court decisions reducing sentences under this provision for not giving suitable reasons.  In 2007, the Supreme Court struck down a decision of the Karnataka High Court which had reduced the sentence of a convicted rapist to 3 and a half years.  The High Court had stated that the sentence should be reduced since the accused was "a young boy of 18 years belonging to Vaddara Community and Illiterate".  The Supreme Court stated that there is a legislative mandate to impose a sentence for not less than 10 years.  Only in exceptional cases, for "adequate and special reasons" can a sentence less than 10 years be imposed.  It overturned the Karnataka High Court decision saying that there was an "absence of any reason which could have been treated as "special and adequate reason"". In Baldev Singh's case, the Supreme Court said: 1.  The fact that the incident is an old one (the incident took place in 1997) is a circumstance which fits into "adequate and special reasons" for reducing a sentence. 2. The parties have entered into a compromise among themselves. The issue is whether this judgement has gone beyond the legislative mandate, and whether it has adhered to the principles laid down by earlier decisions of the Supreme Court.  In 2007, the Supreme Court itself stated that for a crime like rape, strong reasons have to be given to reduce the sentence envisaged by the legislature.  Moreover, the provision does not envisage the settlement of a crime by payment of compensation to the victim of a crime.  A criminal act is seen in law as a crime against the whole of society (which is why the state's prosecution agency, and not the victim, goes to court against alleged criminals).  Therefore, criminal actions such as rape (or murder, robbery, kidnapping etc.) cannot be "settled" by the payment of compensation under the Indian Penal Code.  In this light, it should be interesting to see whether the State files an appeal against this judgement.

There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,