The Civil Damage for Nuclear Liability Bill, 2010 has been criticised on many grounds (Also click here), including (a) capping liability for the operator, (b) fixing a low cap on the amount of liability of the operator, and (c) making the operator solely liable.  We summarise the main principles of civil nuclear liability mentioned in IAEA's Handbook on Nuclear Law: Strict Liability of the Operator: The operator is held liable regardless of fault.  Those claiming compensation do not need to prove negligence or any other type of fault on the part of the operator.  The operator is liable merely by virtue of the fact that damage has been caused. Legal channeling of liability on the operator: "The operator of a nuclear installation is exclusively liable for nuclear damage. No other person may be held liable, and the operator cannot be held liable under other legal provisions (e.g. tort law)...This concept is a feature of nuclear liability law unmatched in other fields of law."  The reason for this has been quoted in the Handbook as:

"...Firstly, it is desirable to avoid difficult and lengthy questions of complicated legal cross-actions to establish in individual cases who is legally liable. Secondly, such channelling obviates the necessity for all those who might be associated with construction or operation of a nuclear installation other than the operator himself to take out insurance also, and thus allows a concentration of the insurance capacity available.”

Limiting the amount of liability: "Limitation of liability in amount is clearly an advantage for the operator.  Legislators feel that unlimited liability, or very high liability amounts, would discourage people from engaging in nuclear related activities. Operators should not be exposed to financial burdens that could entail immediate bankruptcy....Whatever figure is established by the legislator will seem to be arbitrary, but, in the event of a nuclear catastrophe, the State will inevitably step in and pay additional compensation. Civil law is not designed to cope with catastrophes; these require special measures." Limitation of liability in time: "In all legal systems there is a time limit for the submission of claims. In many States the normal time limit in general tort law is 30 years. Claims for compensation for nuclear damage must be submitted within 30 years in the event of personal injury and within 10 years in the event of other damage. The 30 year period in the event of personal injury is due to the fact that radiation damage may be latent for a long time; other damage should be evident within the 10 year period." Insurance coverage: "The nuclear liability conventions require that the operator maintain insurance or provide other financial security covering its liability for nuclear damage in such amount, of such type and in such terms as the Installation State specifies....This ensures that the liability amount of the operator is always covered by an equal amount of money. The congruence principle is to the advantage both of the victims of a nuclear incident and of the operator. The victims have the assurance that their claims are financially covered, and the operator has funds available for compensation and does not need to convert assets into cash.

There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the  implementation of such  projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:

  • Screening: To determine whether the project requires further study for preparing the Environmental Impact Assessment (EIA).
  • Scoping: Setting clear guidelines that state the environmental concerns identified in the project.
  • Public Consultation: To ascertain the concerns of the local persons affected by the environmental impacts of the project.
  • Appraisal: The EAC studies the application, final EIA report, and outcome of the public consultations and makes its recommendations to the MoEF.

The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded

Sector No.  of  projects accorded EC
Industry (Steel & Cement)

88

Thermal Power

29

River Valley and Hydro-electric

6

Coal Mining

29

Non-Coal Mining

25

National Highways

32

Total

209

Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.


[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,