The Civil Damage for Nuclear Liability Bill, 2010 has been criticised on many grounds (Also click here), including (a) capping liability for the operator, (b) fixing a low cap on the amount of liability of the operator, and (c) making the operator solely liable.  We summarise the main principles of civil nuclear liability mentioned in IAEA's Handbook on Nuclear Law: Strict Liability of the Operator: The operator is held liable regardless of fault.  Those claiming compensation do not need to prove negligence or any other type of fault on the part of the operator.  The operator is liable merely by virtue of the fact that damage has been caused. Legal channeling of liability on the operator: "The operator of a nuclear installation is exclusively liable for nuclear damage. No other person may be held liable, and the operator cannot be held liable under other legal provisions (e.g. tort law)...This concept is a feature of nuclear liability law unmatched in other fields of law."  The reason for this has been quoted in the Handbook as:

"...Firstly, it is desirable to avoid difficult and lengthy questions of complicated legal cross-actions to establish in individual cases who is legally liable. Secondly, such channelling obviates the necessity for all those who might be associated with construction or operation of a nuclear installation other than the operator himself to take out insurance also, and thus allows a concentration of the insurance capacity available.”

Limiting the amount of liability: "Limitation of liability in amount is clearly an advantage for the operator.  Legislators feel that unlimited liability, or very high liability amounts, would discourage people from engaging in nuclear related activities. Operators should not be exposed to financial burdens that could entail immediate bankruptcy....Whatever figure is established by the legislator will seem to be arbitrary, but, in the event of a nuclear catastrophe, the State will inevitably step in and pay additional compensation. Civil law is not designed to cope with catastrophes; these require special measures." Limitation of liability in time: "In all legal systems there is a time limit for the submission of claims. In many States the normal time limit in general tort law is 30 years. Claims for compensation for nuclear damage must be submitted within 30 years in the event of personal injury and within 10 years in the event of other damage. The 30 year period in the event of personal injury is due to the fact that radiation damage may be latent for a long time; other damage should be evident within the 10 year period." Insurance coverage: "The nuclear liability conventions require that the operator maintain insurance or provide other financial security covering its liability for nuclear damage in such amount, of such type and in such terms as the Installation State specifies....This ensures that the liability amount of the operator is always covered by an equal amount of money. The congruence principle is to the advantage both of the victims of a nuclear incident and of the operator. The victims have the assurance that their claims are financially covered, and the operator has funds available for compensation and does not need to convert assets into cash.

One of the most politically contentious issues in recent times has been the government’s right to acquire land for ‘public purpose’.  Increasingly, farmers are refusing to part with their land without adequate compensation, the most recent example being the agitation in Uttar Pradesh over the acquisition of land for the Yamuna Express Highway. Presently, land acquisition in India is governed by the Land Acquisition Act, an archaic law passed more than a century ago in 1894.  According to the Act, the government has the right to acquire private land without the consent of the land owners if the land is acquired for a “public purpose” project (such as development of towns and village sites, building of schools, hospitals and housing and state run corporations).  The land owners get only the current price value of the land as compensation.  The key provision that has triggered most of the discontent is the one that allows the government to acquire land for private companies if it is for a “public purpose” project.  This has led to conflict over issues of compensation, rehabilitation of displaced people and the type of land that is being acquired. The UPA government introduced the Land Acquisition (Amendment) Bill in conjunction with the Rehabilitation and Resettlement Bill on December 6, 2007 in the Lok Sabha and referred them to the Standing Committee on Rural Development for scrutiny.  The Committee submitted its report on October 21, 2008 but the Bills lapsed at the end of the 14th Lok Sabha.  The government is planning to introduce revised versions of the Bills.  The following paragraphs discuss the lapsed Bills to give some idea of the government’s perspective on the issue while analysing the lacunae in the Bills. The Land Acquisition (Amendment) Bill, 2007 redefined “public purpose” to allow land acquisition only for defence purposes, infrastructure projects, or any project useful to the general public where 70% of the land had already been purchased from willing sellers through the free market.  It prohibited land acquisition for companies unless they had already purchased 70% of the required land.  The Bill also made it mandatory for the government to conduct a social impact assessment if land acquisition resulted in displacement of 400 families in the plains or 200 families in the hills or tribal areas.  The compensation was to be extended to tribals and individuals with tenancy rights under state laws.  The compensation was based on many factors such as market rates, the intended use of the land, and the value of standing crop.  A Land Acquisition Compensation Disputes Settlement Authority was to be established to adjudicate disputes. The Rehabilitation and Resettlement Bill, 2007 sought to provide for benefits and compensation to people displaced by land acquisition or any other involuntary displacements.  The Bill created project-specific authorities to formulate, implement and monitor the rehabilitation process.  It also outlined minimum benefits for displaced families such as land, house, monetary compensation, skill training and preference for jobs.  A grievance redressal system was also provided for. Although the Bills were a step in the right direction, many issues still remained unresolved.  Since the Land Acquisition Bill barred the civil courts from entertaining any disputes related to land acquisition, it was unclear whether there was a mechanism by which a person could challenge the qualification of a project as “public purpose”.  Unlike the Special Economic Zone Act, 2005, the Bill did not specify the type of land that could be acquired (such as waste and barren lands).  The Bill made special provision for land taken in the case of ‘urgency’.  However, it did not define the term urgency, which could lead to confusion and misuse of the term. The biggest loop-hole in the Rehabilitation and Resettlement Bill was the use of non-binding language.  Take for example Clause 25, which stated that “The Government may, by notification, declare any area…as a resettlement area.” Furthermore, Clause 36(1) stated that land for land “shall be allotted…if Government land is available.”  The government could effectively get away with not providing many of the benefits listed in the Bill.  Also, most of the safeguards and benefits were limited to families affected by large-scale displacements (400 or more families in the plains and 200 or more families in the hills and tribal areas).  The benefits for affected families in case of smaller scale displacements were not clearly spelt out.  Lastly, the Bill stated that compensation to displaced families should be borne by the requiring body (body which needs the land for its projects).  Who would bear the expenditure of rehabilitation in case of natural disasters remained ambiguous. If India is to attain economic prosperity, the government needs to strike a balance between the need for development and protecting the rights of people whose land is being acquired. Kaushiki Sanyal The article was published in Sahara Time (Issue dated September 4, 2010, page 36)