The 2010 Commonwealth Games may have ended on October 14th, but the controversy surrounding the organising of the games is far from over. In Parliament, the Opposition has called for a Joint-Parliamentary Committee (JPC) to be formed to investigate suspected financial irregularities in the organising of the Games[1]. In a statement in Parliament on Tuesday, Minister for Youth Affairs & Sports M.S. Gill commented that “All irregularities will be examined and the guilty will not be spared”[2]. In July 2010, the Central Vigilance Commission (CVC) found irregularities in 14 Games related construction projects[3]. It has been reported that officials from the CVC now believe total misappropriation of Games Funds could be between Rs 5000 crore and Rs 8000 crore [4]. So what is being done about it? Currently, six different government organisations are conducting independent inquiries into financial irregularities, corruption, and mismanagement of the Games: the High Level (Shunglu) Commission, CVC, CAG, CBI, Income Tax Department, and Enforcement Directorate (ED).  With so many government organisations involved, it can be difficult to decipher the big picture. Here is a breakdown of what each organisation is doing: High Level Commission (Shunglu Commission): The Commission was appointed by the Prime Minister on October 15th[5]. It is chaired by V.K. Shunglu, former Comptroller and Auditor General of India, who has been given the status equivalent to a Supreme Court Judge[6]. The Commission has a broad mandate to investigate all matters regarding the Games, specifically:[7]

  • Roles and responsibilities of signatories to Host City Contract
  • Planning and execution of development projects and contracts
  • Effectiveness of organisational structure and governance for agencies involved
  • Managerial weaknesses
  • All financial aspects of the event, including wrongdoing
  • Coordination issues amongst agencies
  • Role of advisors and consultants to Organising Committee
  • Overall impact of the games
  • Lessons learnt for the future

A report from the Commission detailing its findings is expected by mid January. Central Vigilance Commission (CVC): The CVC first found financial irregularities in 14 Games projects in July 2010.  Subsequently, it asked the CBI to register a corruption case against MCD officials in connection with a tender issued for a Games project[8]. In total, the CVC has found irregularities in 38 games related projects, under the following departments and agencies:[9]

  • Ministry of Youth Affairs & Sports: 6
  • Delhi Development Authority: 6
  • Public Works Department: 6
  • Municipal Corporation of Delhi: 5
  • Central Public Works Department: 4
  • Organising Committee: 3
  • New Delhi Municipal Council: 3
  • Government of Delhi: 2
  • Department of Commerce: 1
  • Indian Meteorological Department: 1
  • RITES: 1

The CVC has directed the above agencies to respond to queries regarding the irregularities and has directed the CBI to begin a Preliminary Inquiry into them [10]. The CVC will report its findings to the Shunglu Commission. Income Tax Department: The I-T Department is investigating tenders and awards of contracts for Games related works, as well as tax evasion [11]. It has conducted raids in offices of over 30 business firms and individuals [12]. Enforcement Directorate (ED): The ED is proceeding against Organising Committee officials for violations of the Foreign Exchange Management Act (FEMA) for projects involving venue development and overlays contracts awarded by the Organising Committee. Central Bureau of Investigation (CBI): It has been reported that the CBI had received over 300 complaints of corruption in Games projects by August 2010[13]. It is verifying these claims and investigating matters highlighted by the CVC. Comptroller and Auditor General (CAG): In August 2009, the CAG published a report entitled Preparedness for the XIX Commonwealth Games highlighting the lack of preparedness for the Games and its escalating cost.  The CAG is conducting a detailed audit of the Games that is expected to be published in March 2011[14]. Given that CAG reports are tabled in Parliament, the March 2011 report will be critical to the Parliamentary debate on the Games. Two members of the Organising Committee, the Joint Director and the Deputy Director General, were arrested by the CBI this past Monday.  However, Given that the report of the Shunglu Commssion is due in January 2011, the CAG audit will follow two months later, and the current Opposition demand for a JPC remains unresolved, it may be some time before significant details are made public.


[1] http://economictimes.indiatimes.com/news/politics/nation/BJP-to-press-for-JPC-probe-into-spectrum-Adarsh-CWG-scams/articleshow/6934697.cms [2] http://www.thehindu.com/news/article890174.ece [3] ttp://economictimes.indiatimes.com/news/news-by-industry/et-cetera/CVC-finds-irregularities-in-several-CWG-projects/articleshow/6229429.cms [4] http://www.deccanherald.com/content/105830/cwg-fraud-may-touch-rs.html [5] http://www.business-standard.com/india/news/games-over-pm-orders-probe-into-pre-event-mess/411739/ [6] http://economictimes.indiatimes.com/news/politics/nation/CWG-probe-Shunglu-given-status-of-SC-judge/articleshow/6818404.cms [7] http://pib.nic.in/newsite/PrintRelease.aspx?relid=66561 [8] http://timesofindia.indiatimes.com/city/delhi/CWG-construction-CVC-asks-CBI-to-register-corruption-case/articleshow/6237714.cms [9] http://www.hindustantimes.com/specials/sports/cwg-2010/22-more-CWG-works-under-CVC-scanner/CWG2010-TopStories/SP-Article10-614446.aspx [10] http://www.indianexpress.com/news/Claiming-fraud---favour-in-Games-rentals--CVC-to-CBI--begin-probe/700998/ [11]http://www.indianexpress.com/news/it-dept-collects-cwg-works-related-documents/698683/ [12] http://www.thehindu.com/news/national/article837892.ece [13] http://www.indianexpress.com/news/cbi-has-over-300-complaints-regarding-games-works/655692/ [14] http://economictimes.indiatimes.com/news/politics/nation/CAG-starts-Commonwealth-Games-audit-report-by-March-2011/articleshow/6252852.cms

The Airports Economic Regulatory Authority of India (Amendment) Bill, 2021 was passed by Parliament on August 4, 2021.  It amends the Airports Economic Regulatory Authority of India Act, 2008.  This Bill was introduced in Lok Sabha during the budget session this year in March 2021.  Subsequently, it was referred to the Standing Committee on Transport, Tourism, and Culture, which submitted its report on July 22, 2021.

Typically, cities have one civilian airport which provides all aeronautical services in that area.  These services include air traffic management, landing and parking of aircraft, and ground handling services.  This makes airports natural monopolies in the area.  To ensure that private airport operators do not misuse their monopoly, the need for an independent tariff regulator in the airport sector was felt.  Hence, the Airport Economic Regulatory Authority (AERA) was established as an independent body under the 2008 Act to regulate tariffs and other charges (development fee and passenger service fee) for aeronautical services at major airports.  

For the remaining airports, these tariffs are determined by the Airports Authority of India (AAI), which is a body under the Ministry of Civil Aviation.  In addition, AAI leases out airports under the public-private partnership (PPP) model for operation, management, and development.  Before AERA was set up, AAI determined and fixed the aeronautical charges for all airports.  It also prescribed performance standards for all airports and monitored them.  Various committees had noted that AAI performed the role of airport operator as well as the regulator, which resulted in a conflict of interest.

The 2008 Act designates an airport as a major airport if it has an annual passenger traffic of at least 35 lakh.  The central government may also designate any airport as a major airport through a notification.  The Bill adds that the central government may group airports and notify the group as a major airport.  Thus, when a small airport will be clubbed in a group and the group is notified as a major airport, its tariff will be determined by AERA instead of AAI.  Note that AERA will not determine the tariff if such tariff or tariff structures or the amount of development fees has been incorporated in the bidding document, which is the basis for the award of operatorship of that airport.

The amendments under the Bill raise some concerns regarding the grouping of airports and the capacity of the regulator.

  • Grouping of airports: The Statement of Objects and Reasons of the Bill states that government will club together profit-making and loss-making airports and offer them as a package in PPP mode to the prospective bidders.  This may be a policy decision to revive loss-making airports.  With the passage of the Bill, AERA will treat a group of airports as one entity.  One of the ways in which tariffs may be structured for the grouped entity would be through cross-subsidies.  This would involve compensating loss-making airports with the revenue generated from the profit-making airports.  If such a model is used, it may increase the cost of services to the end-consumers of profit-making airports or could reduce the profitability of such airports.  The experiences from other sectors such as electricity show that cross-subsidisation may lead to pricing problems in long term. 
     
  • Capacity of the regulator: AERA was created to provide a level playing field in the aviation sector and resolve the conflict of interest that arises with AAI both operating and regulating tariffs at airports.  During the examination of the AERA Bill, 2007 by the Standing Committee, the Ministry of Civil Aviation informed the Committee that AERA should regulate tariff and monitor performance standards only at major airports.  Depending upon future developments in the sector, and as the regulator built its capacity, other functions could be subsequently assigned to the regulator.

As of 2020, there are 125 operational airports in India (includes international airports, customs airports, and civil enclaves).  The number of airports under the purview of AERA increased from 11 in 2007 to 24 in 2019.  For the remaining airports, tariffs are still determined by AAI.  In the last five years (2014 to 2019), air passenger traffic increased from 11.3 crore to 34.9 crore (which is an annual growth rate of 10%).  Till 2030-31, air traffic in the country is expected to continue growing at an average annual rate of 10-11%

Before 2019, an airport with annual passenger traffic of at least 15 lakh was considered a major airport.  In 2019, the AERA Act was amended to increase this threshold to 35 lakh.  The Statement of Objects and Reasons of the 2019 Bill stated that the exponential growth of the aviation sector has put tremendous pressure on AERA, while its resources are limited.  Therefore, if too many airports come under the purview of AERA, it will not be able to perform its functions efficiently.  Consequently, in 2019, the number of airports under the purview of AERA was reduced.  Now, with the passage of the 2021 Bill, AERA will have to again regulate tariffs at more airports as and when notified by the central government.  Thus, the capacity of AERA may be needed to be enhanced for extending its scope to other airports.

Table 1: List of major airports in India (as of June 2019)

Ahmedabad

Delhi  

Mumbai  

Amritsar  

Goa  

Patna  

Bengaluru  

Guwahati  

Pune  

Bhubaneswar     

Hyderabad  

Raipur  

Calicut  

Jaipur  

Thiruvananthapuram     

Chandigarh  

Kolkata  

Tiruchirappalli     

Chennai  

Lucknow  

Varanasi  

Cochin  

Mangalore  

Kannur 

Source: AERA website as accessed on August 2, 2021; PRS.