Applications for LAMP Fellowship 2025-26 are now open. Apply here. The last date for submitting applications is December 21, 2024

Recently, the government issued letters de-allocating coal blocks of various companies, based on the recommendations of the  Inter Ministerial Group (IMG).  This post discusses the history behind the de-allocations, the parameters the IMG used while examining the progress of various coal blocks and the action that has been taken by the government. The Comptroller and Auditor General (CAG) released a performance audit report on 'Allocation of Coal Blocks and Augmentation of Coal Production' on August 17, 2012.  Some of the key findings of the Report were:

  • The government failed to conduct competitive bids for the allocation of coal blocks.  This resulted in a benefit of  Rs 1.86 lakh crore (approx.) to private allottees.  The government could have tapped some of this financial benefit by expediting the decision on competitive bidding for allocation of coal blocks.
  • The implementation schedule of a number of coal blocks has been delayed by one to ten years.  This schedule relates to the time frame within which the Mining Plan for the block has to be approved, various clearances have to be submitted, land acquired, etc.
  • From 2005, the Ministry of Coal (MoC) required the allottees to provide bank guarantees which would be encashed if they failed to meet the above mentioned milestones.  The CAG observed that there was a delay in introducing the bank guarantee and linking it with milestones.

The IMG on Coal was constituted for the periodic review of the development of coal blocks and end use plants.  The IMG had requested a status paper from the Coal Controller, MoC.  This has been submitted to the IMG but is not available.  The IMG will decide if private allottees have made substantial progress based on certain parameters.  The parameters used by IMG are:  approval of Mining Plan, status of environment and forest clearance, grant of mining lease and progress made in land acquisition. They are also examining the physical status of End Use Plant (EUP), investment made and the expected date of opening of the mine and commissioning of EUP. The IMG has made the following recommendations:

  • The coal blocks of companies that have not made substantial progress should be de-allocated.  Additionally, they have recommended the deduction of bank guarantee in the cases where the private companies have not reached the milestones as per the time line decided upon.  As of November 22, 2012, the IMG has recommended the de-allocation of the coal blocks listed in Table 1 and the deduction of bank guarantees for the coal blocks in Table 2.
  • Since, the system of bank guarantee was only introduced in March 2005, not all coal blocks had submitted a bank guarantee.  Where a bank guarantee has not been provided but there is substantial progress in meeting the milestones, the IMG may require the allottee to submit a bank guarantee.

[table id=1 /]

 

[table id=5 /]

 

Of the coal blocks that the IMG has recommended for de-allocation, until now the government has accepted the de-allocation of the following: Bramhadih block, Gourangdih, New Patrapara, Chinora block, Warora (Southern Part) block, Lalgarh (North) block, Bhaskarpara block, Dahegaon/Makardhokra-IV block, Gondkhari block and Ramanwara North block.  The government has accepted the deduction of bank guarantees for blocks such as Moitra, Jitpur, Bhaskarpara, Durgapur II/Sariya, Dahegaon/Makardhokra-IV, Marki Mangli II, III and IV, Gondhkari, Lohari, Radhikapur East, Bijahan and Nerad Malegaon. The letters issued by the government de-allocating coal blocks and deducting bank guarantees are available here.

For a detailed summary of the CAG Report, click here.

On March 14, 2022 Rajya Sabha discussed the working of the Ministry of Development of North Eastern Region (DoNER).  During the discussion, several issues around budgetary allocation, implementation of schemes and connectivity with the North Eastern Region were discussed.  The Ministry of DoNER is responsible for matters relating to the planning, execution and monitoring of development schemes and projects in the North Eastern Region.  In this blog post, we analyse the 2022-23 budgetary allocations for the Ministry and discuss related issues.  

A new scheme named PM-DevINE announced to boost infrastructure and social development

In 2022-23, the Ministry has seen a 5% increase in allocation from the revised estimates of 2021-22.  The Ministry has been allocated Rs 2,800 crore which will be used for various development schemes, such as the North East Special Infrastructure Development Scheme and North East Road Sector Development Scheme.  A scheme-wise break-up of the budget allocation for the Ministry is given below in Table 1.  

One of the key highlights of the Finance Minister’s Budget Speech was the announcement of a new scheme named the Prime Minister’s Development Initiative for North East (PM-DevINE).  It will be implemented through the North East Council (nodal agency for the economic and social development of the North Eastern Region).  PM-DevINE will fund infrastructure and social development projects in areas such as road connectivity, health, and agriculture.  The scheme will not replace or subsume existing central sector or centrally sponsored schemes.  The Scheme will be given an initial allocation of Rs 1,500 crore.

Table 1: Break-up of allocation to the Ministry of DoNER (in Rs crore)

Major Heads

2020-21 Actuals

2021-22 BE

2021-22 RE

2022-23 BE

% change from 2021-22 RE to 2022-23 BE

North East Special Infrastructure Development Scheme

446

675

674

1,419

111%

Schemes of North East Council

567

585

585

702

20%

North East Road Sector Development Scheme

416

696

674

496

-26%

Central pool of resources for North East and Sikkim

342

581

581

-

-

Others

270

322

344

241

-30%

Total

1,854

2,658

2,658

2,800

5%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Note: BE – Budget Estimate; RE – Revised Estimate; Schemes for North East Council includes Special Development Projects.

Sources: Demand No. 23 of Union Budget Documents 2022-23; PRS. 

Allocation towards capital outlay less than demand

The Standing Committee on Home Affairs (2022) noted that the amount allocated at the budget stage in 2022-23 (Rs 660 crore) was 17% less than the demand by the Ministry (Rs 794 crore).  Capital expenditure includes capital outlay which leads to the creation of assets such as schools, hospitals, and roads and bridges.  The Committee observed that this may severely affect the implementation of several projects and schemes that require capital outlay.  It recommended the Ministry to take up this matter with the Finance Ministry and demand additional assistance at the revised stage of the 2022-23 financial year.

Underutilisation of funds over the years

Since 2011-12 (barring 2016-17), the Ministry has not been able to utilise the funds allocated to it at the budgeted stage (See Figure 1).  For instance, in 2020-21, fund utilisation in case of the North East Road Sector Development Scheme was 52%, whereas only 34% of funds were utilised under the North East Special Infrastructure Development Scheme (for infrastructure projects relating to water supply, power, connectivity, social infrastructure).  Key reasons for underspending highlighted by the Ministry include late receipt of project proposals and non-receipt of utilisation certificates from state governments.

Figure 1: Underutilisation of funds by the Ministry since 2011-12

image
 Note: Revised Estimate has been used as the Actual Expenditure for 2021-22.
 Sources: Union Budget Documents (2011-12 to 2022-23); PRS
.

Delay in project completion

The Ministry implements several schemes for infrastructural projects such as roads and bridges.  The progress of the certain schemes has been inadequate.   The Standing Committee (2022) observed that the physical progress of many road sector projects under the North East Road Sector Development Scheme is either at zero or in single digit percent in spite of release of the amount for the project.  Similarly, projects under the Karbi Anglong Autonomous Territorial Council (autonomous district council in Assam) and Social and Infrastructure Development Fund (construction of roads, bridges, and construction of schools and water supply projects in the North Eastern Region) have seen inadequate progress.

Need to address declining forest cover

The Standing Committee (2021) has also recommended the Ministry of DoNER to work towards preserving forest cover.  The Committee took note of the declining forest cover in the North East India.  As per the India State of Forest Report (2021), states showing major loss of forest cover from 2019 to 2021 are: (i) Arunachal Pradesh (loss of 257 sq km of forest cover), (ii) Manipur (249 sq km), (iii) Nagaland (235 sq km), (iv) Mizoram (186 sq km), and (v) Meghalaya (73 sq km).  The loss of forest cover may be attributed to shifting cultivation, cutting down of trees, natural calamities, anthropogenic (environmental pollution) pressure, and developmental activities.  The Committee recommended that various measures to protect the forest and environment must be given priority and should implemented within the stipulated timeline.  It also suggested the Ministry to: (i) carry out regular plantation drives to increase forest cover/density, and (ii) accord priority towards the ultimate goal of preserving and protecting the forests under various centrally sponsored initiatives.

Key issues raised by Members during discussion in Rajya Sabha

The discussion on the working of the Ministry of DoNER took place in Rajya Sabha on March 14, 2022.  One of the issues highlighted by members was about the Ministry not having its own line Department.  This leads to the Ministry being dependent on the administrative strength of the states for implementation of projects.  Another issue highlighted by several members was the lack of connectivity of the region through railways and road networks which hampers the economic growth of region.  The DoNER Minister in his response to the House assured the members that the central government is making continuous efforts towards improving connectivity to the North East region through roads, railways, waterways, and telecommunication.         

Allocation by Union Ministries to the North East 

Union Ministries allocate 10% of their budget allocation for the North East (See Figure 2 for fund allocation and utilisation).  The Ministry of DoNER is the nodal Ministry that monitors and keeps track of the allocation done by various Ministries.  In 2022-23, Rs 76,040 crore has been allocated by all the Ministries for the North Eastern region.  The allocation has increased by 11% from the revised estimate of 2021-22 (Rs 68,440 crore).   In 2019-20 and 2021-21 the actual expenditure towards North Eastern areas was lower than budget estimates by 18% and 19% respectively.  

Figure 2: Budgetary allocation by all Union Ministries for the North East (amount in Rs crore)

image   

Source: Report No. 239: Demand for Grants (2022-23) of Ministry of Development of North Eastern Region, Standing Committee on Home Affairs; PRS.