Recently, the government issued letters de-allocating coal blocks of various companies, based on the recommendations of the  Inter Ministerial Group (IMG).  This post discusses the history behind the de-allocations, the parameters the IMG used while examining the progress of various coal blocks and the action that has been taken by the government. The Comptroller and Auditor General (CAG) released a performance audit report on 'Allocation of Coal Blocks and Augmentation of Coal Production' on August 17, 2012.  Some of the key findings of the Report were:

  • The government failed to conduct competitive bids for the allocation of coal blocks.  This resulted in a benefit of  Rs 1.86 lakh crore (approx.) to private allottees.  The government could have tapped some of this financial benefit by expediting the decision on competitive bidding for allocation of coal blocks.
  • The implementation schedule of a number of coal blocks has been delayed by one to ten years.  This schedule relates to the time frame within which the Mining Plan for the block has to be approved, various clearances have to be submitted, land acquired, etc.
  • From 2005, the Ministry of Coal (MoC) required the allottees to provide bank guarantees which would be encashed if they failed to meet the above mentioned milestones.  The CAG observed that there was a delay in introducing the bank guarantee and linking it with milestones.

The IMG on Coal was constituted for the periodic review of the development of coal blocks and end use plants.  The IMG had requested a status paper from the Coal Controller, MoC.  This has been submitted to the IMG but is not available.  The IMG will decide if private allottees have made substantial progress based on certain parameters.  The parameters used by IMG are:  approval of Mining Plan, status of environment and forest clearance, grant of mining lease and progress made in land acquisition. They are also examining the physical status of End Use Plant (EUP), investment made and the expected date of opening of the mine and commissioning of EUP. The IMG has made the following recommendations:

  • The coal blocks of companies that have not made substantial progress should be de-allocated.  Additionally, they have recommended the deduction of bank guarantee in the cases where the private companies have not reached the milestones as per the time line decided upon.  As of November 22, 2012, the IMG has recommended the de-allocation of the coal blocks listed in Table 1 and the deduction of bank guarantees for the coal blocks in Table 2.
  • Since, the system of bank guarantee was only introduced in March 2005, not all coal blocks had submitted a bank guarantee.  Where a bank guarantee has not been provided but there is substantial progress in meeting the milestones, the IMG may require the allottee to submit a bank guarantee.

[table id=1 /]

 

[table id=5 /]

 

Of the coal blocks that the IMG has recommended for de-allocation, until now the government has accepted the de-allocation of the following: Bramhadih block, Gourangdih, New Patrapara, Chinora block, Warora (Southern Part) block, Lalgarh (North) block, Bhaskarpara block, Dahegaon/Makardhokra-IV block, Gondkhari block and Ramanwara North block.  The government has accepted the deduction of bank guarantees for blocks such as Moitra, Jitpur, Bhaskarpara, Durgapur II/Sariya, Dahegaon/Makardhokra-IV, Marki Mangli II, III and IV, Gondhkari, Lohari, Radhikapur East, Bijahan and Nerad Malegaon. The letters issued by the government de-allocating coal blocks and deducting bank guarantees are available here.

For a detailed summary of the CAG Report, click here.

In law, the addition or deletion a single punctuation or a single word can have a major impact on the effect of that law.  One such example can be seen from the recommended changes in the Civil Liability for Nuclear Damage Bill, 2010 by Parliament’s Standing Committee. The Civil Liability for Nuclear Damage Bill, 2010 was introduced in the Lok Sabha on May 7, 2010.  The Bill was referred to the Parliamentary Committee on Science and Technology, Environment and Forests, which submitted its report on the Bill yesterday (August 18, 2010).  The Committee has made a number of recommendations regarding certain clauses in the Bill (See summary here).  One of these may have the effect of diluting the provision currently in the Bill.  The main recommendations pertain to:

  • Preventing the entry of private operators.
  • Allowing the government to increase the total liability for a nuclear incident by notification, but not decrease it.
  • Increasing the liability of the operator to Rs 1,500 crore from Rs 500 crore.
  • Increasing the time limit for claiming compensation to 20 years from 10 years.
  • Changing the provision giving operators a right of recourse against persons actually responsible for causing damage.

Clause 17 of the Bill which gives operators a right of recourse against those actually causing damage had been opposed as it was felt that it was not strong enough to hold suppliers liable in case the damage was caused by them.  Clause 17 gave a right of recourse under three conditions.  The exact clause is reproduced below: The operator of a nuclear installation shall have a right of recourse where — (a) such right is expressly provided for in a contract in writing; (b) the nuclear incident has resulted from the wilful act or gross negligence on the part of the supplier of the material, equipment or services, or of his employee; (c) the nuclear incident has resulted from the act of commission or omission of a person done with the intent to cause nuclear damage. Under this clause, a right of recourse exists when (a) there is a contract giving such a right, or (b) the supplier acts deliberately or in a grossly negligent manner to cause nuclear damage, or (c) a person causes nuclear damage with the intent to do so.  If any of the three cases can be proved by the operator, he has a right of recourse. The Committee has stated that “Clause 17(b) gives escape route to the suppliers of nuclear materials, equipments, services of his employees as their willful act or gross negligence would be difficult to establish in a civil nuclear compensation case.” It recommended that Clause 17(b) should be modified to cover consequences “of latent or patent defect, supply of sub-standard material, defective equipment or services or from the gross negligence on the part of the supplier of the material, equipment or service.” The Committee also recommended another change in Clause 17.  It recommended that clause 17(a) may end with “and”. This provision may dilute the right of recourse available to operators.  The modified clause 17 would read as: The operator of a nuclear installation shall have a right of recourse where — (a) such right is expressly provided for in a contract in writing; and, (b) the nuclear incident has resulted as a consequence of latent or patent defect, supply of sub-standard material, defective equipment or services or from the gross negligence on the part of the supplier of the material, equipment or services.; (c) the nuclear incident has resulted from the act of commission or omission of a person done with the intent to cause nuclear damage. This implies that for Clauses 17(b) or (c) to be applicable, the condition specified in clause 17(a) has to be compulsorily satisfied.  Two examples highlight the consequence of the recommended change in Clause 17(a) of the Bill:

  1. A person X deliberately commits sabotage in a nuclear plant and causes damage.  Under the Bill, the operator has recourse under Clause 17(c).  If the recommendation regarding clause 17 is accepted, the operator may also have to also prove the existence of a pre-existing contract with X in addition to clause 17(c).
  2. If a supplier supplies defective equipment, but does not have a contract in writing stating that he will be liable for damage caused by defective equipment, the operator may not have a right of recourse against the supplier under 17(b).

The effect of the changes recommended by the committee may thus dilute the provision as it exists in the Bill.  The table below compares the position in the Bill and the position as per the Standing Committee’s recommendations:

Right of recourse - The Bill gives operators a right to recourse under three conditions:  (a) if there is a clear contract; (b) if the damage is caused by someone with intent to cause damage; (c) against suppliers if damage is caused by their wilful act or negligence. In the Bill the three conditions are separated by a semi-colon.  The Committee recommended that the semi-colon in clause 17(a) should be replaced by “and”. This might imply that all three conditions mentioned need to exist for an operator to have recourse.
Right to recourse against suppliers exists in cases of “willful act or gross negligence on the part of the supplier”. (Clause 17) The Committee felt that the right of recourse against suppliers is vague.  It recommended that recourse against the supplier should be strengthened.  The supplier is liable if an incident has occurred due to (i) defects, or (ii) sub-standard material, or (iii) gross negligence of the supplier of the material, equipment or services. The variance with the Convention continues to exist.