Applications for the LAMP Fellowship 2025-26 will open soon. Sign up here to be notified when the dates are announced.

The recent order of the ministry of environment and forests (MoE&F) rejecting the application for grant of forest clearance to the Orissa Mining Company (the Vedanta project) has raised a number of important questions. The order cited the company’s non-compliance with a number of laws. But the Vedanta case is just one example. There are several projects in the country where similar issues are relevant. The question really is, are the multiple laws that are applicable in such cases in harmony with each other or are they working at cross purposes? In a sector such as mining, doing business is inherently complicated. There are at least four broad aspects that need to be addressed—obtaining mining licences, securing environmental clearances, acquiring land, and rehabilitation of people affected by such projects. We take a look at each of the four broad areas, to understand how the applicable laws interact with one another. Obtaining mining licences Doing business in the mining sector first entails obtaining a licence for activities such as prospecting and mining. The Mines and Minerals (Development and Regulation) Act, 1957, lays down the framework for any prospecting, leasing or mining activity to be carried out for specified minerals, and the licences that need to be obtained. The Act allows the central government to frame the rules and conditions applicable both for grant of licences and for the actual activity carried out by enterprises. The licensing authority for mining activities is the state government. Securing environment clearances Environmental clearances for industrial activities are governed by a number of laws. Most activities require clearances under the Environment (Protection) Act, 1986. Additionally, for activities in forest areas, clearance is also required under the Forest (Conservation) Act, 1980. Acts pertaining to wildlife protection, bio-diversity and the quality of air and water may also be applicable. The Environment (Protection) Act, 1986, enables the central government to take measures for “protecting and improving the quality of the environment and preventing, controlling and abating environmental pollution”. These measures may include (among others) (a) laying down standards for the quality of the environment, (b) areas in which industries or operations may not be carried out, or carried out subject to certain safeguards. The rules framed under the Act make it compulsory for all new projects to take prior environmental clearance. For a specified category of activities clearance has to be obtained from the MoE&F, while for others, clearance has to be obtained from State Environment Impact Assessment Authorities (SEIAAs). The Forest (Conservation) Act, 1980, prohibits state governments and other authorities from any unauthorised change in the status of areas declared to be reserved forests, and any diversion of forests for non-forest purposes. It prohibits felling of trees within forest areas. Any such action has to be undertaken with the prior permission of the central government. To divert any forest area for non-forest purposes, state governments have to submit formal proposals to the Centre. State governments also have to show proposals for compensatory afforestation. Acquiring land for the project Acquiring land for projects has become increasingly contentious in recent years. The Land Acquisition Act of 1894 appears to have outlived its utility, which led the UPA-1 to introduce a Bill in the Parliament to bring a new legal framework to facilitate land acquisition. The Bill tried to address several critical aspects of land acquisition. It tried to redefine ‘public purpose’ somewhat more strictly than in the existing Act. ‘Public purpose’ was redefined to include defence purposes, infrastructure projects or for any project useful to the general public where 70% of the land has already been purchased. For acquisitions by companies, the Bill mandated that 70% of the land will have to be acquired directly from the land owners at market prices and that the government would step in under the Act to acquire the remaining 30% for the project. The Bill also aimed to provide for cases resulting in large-scale displacement. It stated that in such cases a social impact assessment study must be conducted. Tribals, forest dwellers and those with tenancy rights were also made eligible for compensation. It also mandated that the intended use of the land being acquired and the current market value of the land would have to be considered for determining compensation. The Bill lapsed when the Lok Sabha was dissolved in 2009. It is not known when the government proposes to reintroduce a Bill in the Parliament to address this issue of land acquisition. Rights of project-affected people When large projects are planned and land is acquired for those, people are often displaced from the project areas and need to be rehabilitated appropriately. The UPA-1 had introduced a Bill in the Parliament to create a legal framework for rehabilitation of project-affected people. However, the proposed Rehabilitation and Resettlement Bill, 2007, lapsed when the Lok Sabha was dissolved before the last general elections. But the UPA-1 government managed to pass a highly contested Bill that recognised the rights of scheduled tribes and other traditional forest dwellers. The Scheduled Tribes and Other Traditional Forest Dwellers (Recognition of Forest Rights) Act passed in 2006 focuses on the rights of forest-dwelling Scheduled Tribes and traditional forest dwellers. The Act seeks to recognise and vest forest rights in forest dwelling Scheduled Tribes with respect to forest land and their habitat. The Act mentions 13 separate rights given to forest dwellers. These include (a) living in the forest for habitation or for self-cultivation for livelihood, (b) right to own, use or dispose of minor forest produce, (c) right to protect and conserve any community resource that they have been traditionally protecting and (d) individual and community rights of habitat for primitive tribal groups. These rights have to be formally recorded/recognised by state governments. The Act also prevents any modification of forest rights or the resettlement of forest dwellers unless the Gram Sabha of the village consents to the proposal in writing. There are additional requirements to be met if developmental activities are to be undertaken in tribal dominated areas (defined as Scheduled Areas in the Constitution). The Panchayat (Extension into Scheduled Areas) Act, 1996, extends the part of the Constitution providing for Panchayati Raj in rural areas to Scheduled Areas. The Act requires that government authorities consult the Panchayat or the Gram Sabha before acquiring land for development projects and for rehabilitating persons affected by such projects. At a conceptual level, there is no apparent contradiction in the applicable laws and each of the laws mentioned above appear to be necessary to ensure that there is fairness for all stakeholders involved. However, a distinction has to be made between the legal principles these laws seek to enforce, and procedural formalities that need to be complied with to be on the right side of the law. Also, a closer look at these individual laws and their implementation will reveal a number of loopholes that need to be plugged to ensure that the spirit and basic principles enshrined in each law are enforced efficiently. From the point of view of the company that intends to do business in India, all this adds up to a lot of time-consuming process. This is perhaps why the Doing Business index published annually by the World Bank group ranks India at 133 out of 183 counties in terms of ease of doing business. The challenge, going forward, is for us to strengthen processes that are fair to all stakeholders, but at the same time are not unduly burdensome on the company that seeks to make investments in the mining sector. By CV Madhukar and Anirudh Burman This was published as an article in Financial Express on September 2, 2010

Recently, the central government launched the Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya).[i],[ii]  The scheme seeks to ensure universal household electrification (in both rural and urban areas) by providing last mile connectivity.  The scheme is expected to cover three crore households.  Note that currently about four crore households are un-electrified.  A rural electrification scheme has also been under implementation since 2005.  In light of this, we discuss the current situation of, and key issues related to rural electrification in the country.

Regulatory and policy framework

Under the Electricity Act, 2003, the central and state governments have the joint responsibility of providing electricity to rural areas.  The 2003 Act also mandates that the central government should, in consultation with the state governments, provide for a national policy on (i) stand-alone power systems for rural areas (systems that are not connected to the electricity grid), and (ii) electrification and local distribution in rural areas.  Consequently, the Rural Electrification Policy was notified in August 2006.[iii]

The Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), launched in 2005, was the first scheme on rural electrification.  In December 2014, Ministry of Power launched the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), which subsumed the RGGVY.[iv]  Components of DDUGJY include: (i) separation of agricultural and non-agricultural electricity feeders to improve supply for consumers in rural areas, (ii) improving sub-transmission and distribution infrastructure in rural areas, and (iii) rural electrification by carrying forward targets specified under the RGGVY.

The total financial outlay for DDUGJY over the implementation period (until 2021-22) is Rs 82,300 crore which includes budgetary support of Rs 68,900 crore.  The central government provides 60% of the project cost as grant, the state power distribution companies (discoms) raise 10% of the funds, and 30% is borrowed from financial institutions and banks.

Status of rural electrification

As of August 2017, about 1% of the villages in India remain un-electrified (3,146 villages).  However, with regard to households, around 23% (4.1 crore households) are yet to be electrified.  Table 1 at the end of this post shows the status of rural electrification across all states.

Issues with rural electrification

Definition of an electrified village

An electrified village is defined as one that has the following: (i) provision of basic infrastructure such as distribution transformers and lines in the inhabited locality, (ii) provision of electricity in public places like schools, panchayat office, health centers, dispensaries, and community centers, and (iii) at least 10% of the total number of households in the village are electrified.[iv]

Therefore, a village is considered to be electrified if 10% of the total number of households in the village have been electrified.  This is apart from the basic infrastructure and electrification of certain public centers in the village.  The Standing Committee on Energy (2013) had observed that according to this definition, a village would be called electrified even if up to 90% of households in it do not have an electricity connection.[v]  It also noted that the infrastructure being provided under the scheme is highly inadequate, unreliable and unsustainable.  The Committee recommended that the actual electrification requirement of villages must be assessed, and it should be ensured that the state discoms provide electricity to the remaining households in the village.

Supply of electricity

The Standing Committee had also noted that while the rural electrification scheme looks at creating infrastructure, the actual supply of electricity to households rests with the state discoms.[v]  These discoms are already facing huge financial losses and hence are unable to supply electricity to the villages.  Discoms continue to supply subsidised power to agricultural and residential consumers, resulting in revenue losses.  Further, the average technical and commercial losses (theft and pilferage of electricity) (AT&C losses) are at around 25%.  While the Ujjwal Discom Assurance Yojana (UDAY) has eased off some of the financial losses of the discoms, it remains to be seen whether discoms are able to reduce the cost-tariff gap and AT&C losses in the future.

It has been recommended that generation capacity should be augmented so that states can meet the additional demand under the rural electrification schemes. Further, the assistance to financially weaker states should be increased so that they can better implement the scheme.[v]

Electricity to below poverty line (BPL) households

Under the rural electrification scheme, the cost for providing free electricity connection per BPL household is Rs 3,000.  It has been observed that this cost per household may be inadequate.[v]  Due to the low cost, the quantity and the quality of work has been getting compromised leading to poor implementation of the scheme.  It has been recommended that the Ministry should revisit the cost provided under the scheme.[v]

The new electrification scheme: Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya)

The new scheme, Saubhagya, seeks to ensure universal household electrification, that is, in both rural and urban areas.  Under Saubhagya, beneficiaries will be identified using the Socio Economic and Caste Census (SECC) 2011 data.  The identified poor households will get free electricity connections.  Other households not covered under the SECC, will be provided electricity connections at a cost of Rs 500.  This amount will be collected by the electricity distribution companies in 10 instalments.

The total outlay of the scheme will be Rs 16,320 crore, of which the central government will provide Rs 12,320 crore.  The outlay for the rural households will be Rs 14,025 crore, of which the centre will provide Rs 10,588 crore.  For urban households the outlay will be Rs 2,295 crore of which the centre will provide Rs. 1,733 crore.

The state discoms will execute the electrification works through contractors or other suitable agencies.  Information technology (mobile apps, web portals) will be used to organise camps in villages to identify beneficiaries.  In order to accelerate the process, applications for electricity connections will be completed on the spot.

So far the focus of electrification schemes has been on rural areas, where typically last mile connectivity has been difficult to provide.  Saubhagya extends the ambit of electrification projects to urban areas as well.  While DDUGJY has focused on the village as the principal unit to measure electrification, the new scheme shifts the targets to household electrification.  While the target for ensuring electricity connection in each household will be a significant step towards ensuring 24×7 power, the question of continuous and quality supply to these households will still rest on the ability of the discoms to provide electricity.  Further, while the scheme provides for free connections, the ability of these households to pay for the electricity they consume may be a concern.

Table 1: Status of rural electrification across states (as of August 2017)

Fig 1 edit

* all villages in Telangana were declared electrified before the bifurcation of the state.
Sources:  Ministry of Power; PRS.

 

[i] “PM launches Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 25, 2017.

[ii] “FAQs on Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 27, 2017.

[iii].  Rural Electrification Policy, Ministry of Power, August 23, 2006, http://powermin.nic.in/sites/default/files/uploads/RE%20Policy_1.pdf.

[iv].  “Office memorandum: Deendayal Upadhyaya Gram Jyoti Yojana”, Ministry of Power, December 3, 2014, http://powermin.nic.in/rural_electrification/pdf/Deendayal_Upadhyaya_Gram_Jyoti_Yojana.pdf.

[v].  “41st Report: Implementation of Rajiv Gandhi Grameen Vidyutikaran Yojana”, Standing Committee on Energy, December 13, 2013, http://164.100.47.134/lsscommittee/Energy/15_Energy_41.pdf.