The recent order of the ministry of environment and forests (MoE&F) rejecting the application for grant of forest clearance to the Orissa Mining Company (the Vedanta project) has raised a number of important questions. The order cited the company’s non-compliance with a number of laws. But the Vedanta case is just one example. There are several projects in the country where similar issues are relevant. The question really is, are the multiple laws that are applicable in such cases in harmony with each other or are they working at cross purposes? In a sector such as mining, doing business is inherently complicated. There are at least four broad aspects that need to be addressed—obtaining mining licences, securing environmental clearances, acquiring land, and rehabilitation of people affected by such projects. We take a look at each of the four broad areas, to understand how the applicable laws interact with one another. Obtaining mining licences Doing business in the mining sector first entails obtaining a licence for activities such as prospecting and mining. The Mines and Minerals (Development and Regulation) Act, 1957, lays down the framework for any prospecting, leasing or mining activity to be carried out for specified minerals, and the licences that need to be obtained. The Act allows the central government to frame the rules and conditions applicable both for grant of licences and for the actual activity carried out by enterprises. The licensing authority for mining activities is the state government. Securing environment clearances Environmental clearances for industrial activities are governed by a number of laws. Most activities require clearances under the Environment (Protection) Act, 1986. Additionally, for activities in forest areas, clearance is also required under the Forest (Conservation) Act, 1980. Acts pertaining to wildlife protection, bio-diversity and the quality of air and water may also be applicable. The Environment (Protection) Act, 1986, enables the central government to take measures for “protecting and improving the quality of the environment and preventing, controlling and abating environmental pollution”. These measures may include (among others) (a) laying down standards for the quality of the environment, (b) areas in which industries or operations may not be carried out, or carried out subject to certain safeguards. The rules framed under the Act make it compulsory for all new projects to take prior environmental clearance. For a specified category of activities clearance has to be obtained from the MoE&F, while for others, clearance has to be obtained from State Environment Impact Assessment Authorities (SEIAAs). The Forest (Conservation) Act, 1980, prohibits state governments and other authorities from any unauthorised change in the status of areas declared to be reserved forests, and any diversion of forests for non-forest purposes. It prohibits felling of trees within forest areas. Any such action has to be undertaken with the prior permission of the central government. To divert any forest area for non-forest purposes, state governments have to submit formal proposals to the Centre. State governments also have to show proposals for compensatory afforestation. Acquiring land for the project Acquiring land for projects has become increasingly contentious in recent years. The Land Acquisition Act of 1894 appears to have outlived its utility, which led the UPA-1 to introduce a Bill in the Parliament to bring a new legal framework to facilitate land acquisition. The Bill tried to address several critical aspects of land acquisition. It tried to redefine ‘public purpose’ somewhat more strictly than in the existing Act. ‘Public purpose’ was redefined to include defence purposes, infrastructure projects or for any project useful to the general public where 70% of the land has already been purchased. For acquisitions by companies, the Bill mandated that 70% of the land will have to be acquired directly from the land owners at market prices and that the government would step in under the Act to acquire the remaining 30% for the project. The Bill also aimed to provide for cases resulting in large-scale displacement. It stated that in such cases a social impact assessment study must be conducted. Tribals, forest dwellers and those with tenancy rights were also made eligible for compensation. It also mandated that the intended use of the land being acquired and the current market value of the land would have to be considered for determining compensation. The Bill lapsed when the Lok Sabha was dissolved in 2009. It is not known when the government proposes to reintroduce a Bill in the Parliament to address this issue of land acquisition. Rights of project-affected people When large projects are planned and land is acquired for those, people are often displaced from the project areas and need to be rehabilitated appropriately. The UPA-1 had introduced a Bill in the Parliament to create a legal framework for rehabilitation of project-affected people. However, the proposed Rehabilitation and Resettlement Bill, 2007, lapsed when the Lok Sabha was dissolved before the last general elections. But the UPA-1 government managed to pass a highly contested Bill that recognised the rights of scheduled tribes and other traditional forest dwellers. The Scheduled Tribes and Other Traditional Forest Dwellers (Recognition of Forest Rights) Act passed in 2006 focuses on the rights of forest-dwelling Scheduled Tribes and traditional forest dwellers. The Act seeks to recognise and vest forest rights in forest dwelling Scheduled Tribes with respect to forest land and their habitat. The Act mentions 13 separate rights given to forest dwellers. These include (a) living in the forest for habitation or for self-cultivation for livelihood, (b) right to own, use or dispose of minor forest produce, (c) right to protect and conserve any community resource that they have been traditionally protecting and (d) individual and community rights of habitat for primitive tribal groups. These rights have to be formally recorded/recognised by state governments. The Act also prevents any modification of forest rights or the resettlement of forest dwellers unless the Gram Sabha of the village consents to the proposal in writing. There are additional requirements to be met if developmental activities are to be undertaken in tribal dominated areas (defined as Scheduled Areas in the Constitution). The Panchayat (Extension into Scheduled Areas) Act, 1996, extends the part of the Constitution providing for Panchayati Raj in rural areas to Scheduled Areas. The Act requires that government authorities consult the Panchayat or the Gram Sabha before acquiring land for development projects and for rehabilitating persons affected by such projects. At a conceptual level, there is no apparent contradiction in the applicable laws and each of the laws mentioned above appear to be necessary to ensure that there is fairness for all stakeholders involved. However, a distinction has to be made between the legal principles these laws seek to enforce, and procedural formalities that need to be complied with to be on the right side of the law. Also, a closer look at these individual laws and their implementation will reveal a number of loopholes that need to be plugged to ensure that the spirit and basic principles enshrined in each law are enforced efficiently. From the point of view of the company that intends to do business in India, all this adds up to a lot of time-consuming process. This is perhaps why the Doing Business index published annually by the World Bank group ranks India at 133 out of 183 counties in terms of ease of doing business. The challenge, going forward, is for us to strengthen processes that are fair to all stakeholders, but at the same time are not unduly burdensome on the company that seeks to make investments in the mining sector. By CV Madhukar and Anirudh Burman This was published as an article in Financial Express on September 2, 2010

Recently, Delhi witnessed large scale protests by various groups demanding stricter punishment and speedier trial in cases of sexual assault against women.  In light of the protests, the central government has constituted a Commission (headed by Justice Verma) to suggest possible amendments in the criminal law to ensure speedier disposal of cases relating to sexual assault.  Though the Supreme Court, in 1986, had recognised speedy trial to be a fundamental right, India continues to have a high number of pending cases. In 2012, the net pendency in High Courts and subordinate courts decreased by over 6 lakh cases. However, there is still a substantial backlog of cases across various courts in the country.  As per the latest information given by the Ministry of Law and Justice, there are 43.2 lakh cases pending in the High Courts and 2.69 crore cases pending in the district courts.[1]

After the recent gang-rape of a 23 year old girl, the Delhi High Court directed the state government to establish five Fast Track Courts (FTCs) for the expeditious adjudication of cases relating to sexual assault.   According to a news report, other states such as Maharashtra and Tamil Nadu have also begun the process of establishing FTCs for rape cases.  In this blog, we look at the status of pending cases in various courts in the country, the number of vacancies of judges and the status of FTCs in the country. Vacancies in the High Courts and the Subordinate Courts One of the reasons for the long delay in the disposal of cases is the high number of vacancies in position for judges in the High Courts and the District Courts of the country.  As of December 1, 2012, the working strength of the High Court judges was 613 as against the sanctioned strength of 895 judges.  This reflects a 32% vacancy of judges across various High Courts in the country.  The highest number of vacancies is in the Allahabad High Court with a working strength of 86 judges against the sanctioned strength of 160 judges (i.e. vacancy of 74 judges).   The situation is not much better at the subordinate level.  As on September 30, 2011, the sanctioned strength of judges at the subordinate level was 18,123 judges as against a working strength of 14,287 judges (i.e. 21% vacancy).  The highest vacancy is in Gujarat with 794 vacancies of judges, followed by Bihar with 690 vacancies. Fast Track Courts The 11th Finance Commission had recommended a scheme for the establishment of 1734 FTCs for the expeditious disposal of cases pending in the lower courts.  In this regard, the Commission had allocated Rs 500 crore.   FTCs were to be established by the state governments in consultation with the respective High Courts.  An average of five FTCs were to be established in each district of the country.  The judges for these FTCs were appointed on an adhoc basis.  The judges were selected by the High Courts of the respective states.  There are primarily three sources of recruitment.  First, by promoting members from amongst the eligible judicial officers; second, by appointing retired High Court judges and third, from amongst members of the Bar of the respective state. FTCs were initially established for a period of five years (2000-2005).  However, in 2005, the Supreme Court[2] directed the central government to continue with the FTC scheme, which was extended until 2010-2011.  The government discontinued the FTC scheme in March 2011.  Though the central government stopped giving financial assistance to the states for establishing FTCs, the state governments could establish FTCs from their own funds.  The decision of the central government not to finance the FTCs beyond 2011 was challenged in the Supreme Court.  In 2012, the Court upheld the decision of the central government.[3]  It held that the state governments have the liberty to decide whether they want to continue with the scheme or not.  However, if they decide to continue then the FTCs have to be made a permanent feature. As of September 3, 2012, some states such as Arunachal Pradesh, Assam, Maharashtra, Tamil Nadu and Kerala decided to continue with the FTC scheme.  However, some states such as Haryana and Chhattisgarh decided to discontinue it. Other states such as Delhi and Karnataka have decided to continue the FTC scheme only till 2013.[4]

Table 1: Number of Fast Track Courts and the pending cases in FTCs                     (As on March 31, 2011)

State No of FTC No of cases transferred until March 31, 2011 Pending cases
Arunachal Pradesh 3 4,162 2,502
Bihar` 179 2,39,278 80,173
Assam 20 72,191 16,380
West Bengal 109 1,46,083 32,180
Goa 5 5,096 1,079
Punjab 15 58,570 12,223
Jharkhand 38 1,10,027 22,238
Gujarat 61 5,37.636 1,03,340
Chattisgarh 25 9,4670 18,095
Meghalaya 3 1,031 188
Rajasthan 83 1,49,447 26,423
Himachal Pradesh 9 40,126 6,699
Karnataka 87 2,18,402 34,335
Andhra Pradesh 108 2,36,928 36,975
Nagaland 2 845 129
Kerala 38 1,09,160 13,793
Mizoram 3 18,68 233
Haryana 6 38,359 4,769
Madhya Pradesh 84 3,60,602 43,239
UP 153 4,64,775 53,117
Maharashtra 51 4,23,518 41,899
Tamil Nadu 49 4,11,957 40,621
Uttarakhand 20 98,797 9006
Orissa 35 66,199 5,758
Manipur 2 3,059 198
Tripura 3 5,812 221
Total 1192 3898598 6,05,813

Sources:  Lok Sabha Unstarred Question No.498, March 3, 2012; PRS

 


[1].  Rajya Sabha Starred Question no 231 dated December 10, 2012.

[2].  Brij Mohan Lal v Union of India (2005) 3 SCR 103.

[3].  Brij Mohan Lal v Union of India (2012) 6 SCC 502. [4].  Rajya Sabha Unstarred Question no 2388 dated September 3, 2012.