Bihar became the first state to scrap the MLA Local Area Development Fund scheme (MLALAD).  According to news reports, Nitish Kumar, Bihar’s Chief Minister, is planning to replace it with the CM Area Development Programme, which would be implemented at the District level.  The schemes would be selected by a district selection committee headed by the minister-in-charge and MLAs and MLCs of that district as members.  The implementation shall rest with a body of engineers, headed by Engineer-in-chief.  The district magistrates would only monitor implementation and contractors would be chosen through open tendering in which a representative of the Comptroller and Auditor General of India (CAG) would be present.  The state government would allocate funds as per requirement. The MPLAD and MLALAD scheme was introduced in December 1993 by former Prime Minister, P.V. Narasimha Rao to enable legislators to execute small works of a local nature to meet the urgent needs of their constituents.  Under the scheme, each legislator may identify projects and sanction upto Rs 2 crore per year for public works in their constituencies.  The scheme was mooted after MPs demanded that they should be able to recommend certain development projects in their constituencies.  The projects include assets building such as drinking water facilities, primary education, public health sanitation and roads.  The initial amount allocated was Rs 5 lakh per year to each MP. It has however not been smooth sailing for the scheme.  Besides the many implementation lapses (as pointed out by the Standing Committee on Finance in 1998-1199, the CAG and the Planning Commission), the constitutionality of the scheme has been questioned by various scholars and experts. In 2002, the National Commission to Review the Working of the Constitution recommended immediate discontinuation of the MPLAD scheme on the ground that it was inconsistent with the spirit of federalism and distribution of powers between the centre and the state.  Former MP, Era Sezhiyan in a booklet titled ‘MPLADS – Concept, Confusion and Contradictions’ also opposed the scheme and recommended that it be scrapped since it ran contrary to the Constitutional provisions which envisaged separate roles for the Executive and Legislature.  However, the Committee on MPLADS in its 13th Report and its 15th Report stated that there was nothing wrong with the scheme per se except some procedural infirmities and recommended among other things a change of nomenclature to the Scheme for Local Area Development.  The debate continued with the 2nd Administrative Reforms Commission’s report on “Ethics in Governance” taking a firm stand against the scheme arguing that it seriously erodes the notion of separation of powers, as the legislator directly becomes the executive.  However, in response to a Writ Petition that challenged the constitutionality of the MPLAD scheme as ultra vires of the Constitution of India, in May 2010, a five-judge bench of the Supreme Court ruled that there was no violation of the concept of separation of powers because the role of an MP in this case is recommendatory and the actual work is carried out by the Panchayats and Municipalities which belong to the executive organ.  There are checks and balances in place through the guidelines which have to be adhered to and the fact that each MP is ultimately responsible to the Parliament. Meanwhile, some MPs are pushing for hiking the amount allocated under the scheme to Rs 5 crore.  However, no decision has been reached yet.  The Ministry of Statistics and Programme Implementation has suggested that a single parliamentary committee be formed comprising of members of both Houses of Parliament to monitor MPLAD schemes. While the question of constitutionality of the MPLAD scheme may have been put to rest by the Supreme Court ruling, other issues related to implementation of the scheme still remain.  Unless problems such as poor utilisation of funds, irregular sanction of works, delay in completion of works are tackled in an efficient manner, the efficacy of the scheme will remain in doubt.

The Minister of Railways, Dinesh Trivedi, presented the Railways Budget 2012 to Parliament on 14th March.  While commenting on the financial position of Railways, the Minister said that 'the Indian Railways are passing through a difficult phase'. The Operating Ratio for the closing year is now estimated to equal 95%. This is significantly higher than the 91.1% figure budgeted last year. Operating Ratio is a metric that compares operating expenses to revenues. A higher ratio indicates lower ability to generate surplus. Surplus is used for capital investments such as laying of new lines, deploying more coaches etc. Therefore, a smaller surplus affects the Railway’s capability to make such investments. Budget v/s Revised estimates 2011-12 Budget 2011-12 had estimated the performance of Railways for the financial year. Revised estimates have now been submitted. Taken together, these two figures help in comparing actual performance against targets. Some observations are enumerated below:

  • Total receipts decreased by Rs 2,746 crore.
  • Total expenditure increased by Rs 2,102 crore.
  • Operating Ratio increased from 91.1% to 95%. This implies a decrease in surplus.
  • Appropriations to the ‘Development Fund’ and the ‘Capital Fund’ decreased from Rs 5,258 crore to Rs 1,492 crore (a decrease of 72%). The ‘Development Fund’ finances expenditure such as passenger amenities; the ‘Capital Fund’ is used for capital augmentation such as laying of new lines.

Budget estimates 2012-13 In 2012-13, Railways plan to improve Operating Ratio to 84.9% and to increase surplus to Rs 15,557 crore. This is more than 10 times the surplus generated in 2011-12 (Revised Estimates). The effective increase in freight rates is estimated to average 23%. During this time, passenger fares are also estimated to increase by an effective average rate of 19%. [1] Infrastructure Performance during the 11th Plan Under the 11th Five Year Plan, the total plan expenditure for Railways had been approved at Rs 2,33,289 crore. The Outcome Budget shows that the actual expenditure is only likely to be Rs 1,92,291 crore. Thus, expenditure will fall short by Rs 40,998 crore. This gaps exists despite a significant increase in the Gross Budgetary Support approved by Parliament. Plan expenditure during 2007-12 (In Rs Crore)

 

Approved Expenditure

Actual Expenditure

Gross Budgetary Support

63,635

75,979

Internal Resources

90,000

67,763

Extra Budgetary Support

79,654

48,549

Total

2,33,289

1,92,291

The Standing Committee on Railways, in its 11th report presented in August 2011, had sought an explanation from the Ministry. According to the Ministry, lower mobilization of internal resources and lack of extra budgetary support are the main reasons for the shortfall.  Internal resource mobilization has been low because of (i) impact of the 6th Pay Commission; and (ii) slow growth in freight earnings due to the economic slowdown. Extra budgetary resources have been low due to non-materialization of funds through the Public-Private Partnership route. Proposals for the 12th Plan Two recent committees – Kakodkar Committee on Railway Safety and the Pitroda Committee on Railway Modernization – have called for large investments in the next five years. The Kakodkar Committee has recommended an investment of Rs 1,00,000 crore in the next five years to improve safety; the Pitroda Committee has recommended an expenditure of Rs 3,96,000 crore in the next five years on modernization. The Railway sub-group of the 12th Five Year Plan has also estimated a requirement of Rs 4,42,744 crore for various other investments proposed to be undertaken during the Plan period. [2] All three groups have called for significant investments in infrastructure augmentation in the next five years. Budget proposals 2012-13 According to the Minister’s speech, the Annual Plan outlay for the year 2012-13 has been set at Rs 60,100 crore. The plan would be financed through:

  • Gross Budgetary Support of Rs 24,000 crore
  • Railway Safety Fund of Rs 2,000 crore
  • Internal Resources of Rs 18,050 crore
  • Extra Budgetary Resources of Rs 16,050 crore. Of this, Rs 15,000 crore would be borrowed from the market through IRFC (Indian Railway Finance Corporation).

What happens now? The Budget is likely to be discussed in the two Houses within the next few days.  Post the discussion, the Ministry's proposals will be put to vote.  Once passed, the Ministry can put its proposals into action. For more details on the Railway Budget, including the projects proposed this year and the status of proposals made last year, please see our analysis here. To understand some of the challenges faced by the Indian Railways, see our blog post from last year. Notes: [1] The ‘effective average fare’ has been calculated by dividing the total income from the segment (freight/ passenger) by the total traffic (in NTKM/ PKM).  This would vary with changes in fares as well as the usage by different categories of users (including the proportion of tickets booked through Tatkal). [2] Source: Report of the Expert Group on Railway Modernization (Chairman: Sam Pitroda)