Recently, the central government launched the Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya).[i],[ii]  The scheme seeks to ensure universal household electrification (in both rural and urban areas) by providing last mile connectivity.  The scheme is expected to cover three crore households.  Note that currently about four crore households are un-electrified.  A rural electrification scheme has also been under implementation since 2005.  In light of this, we discuss the current situation of, and key issues related to rural electrification in the country.

Regulatory and policy framework

Under the Electricity Act, 2003, the central and state governments have the joint responsibility of providing electricity to rural areas.  The 2003 Act also mandates that the central government should, in consultation with the state governments, provide for a national policy on (i) stand-alone power systems for rural areas (systems that are not connected to the electricity grid), and (ii) electrification and local distribution in rural areas.  Consequently, the Rural Electrification Policy was notified in August 2006.[iii]

The Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), launched in 2005, was the first scheme on rural electrification.  In December 2014, Ministry of Power launched the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), which subsumed the RGGVY.[iv]  Components of DDUGJY include: (i) separation of agricultural and non-agricultural electricity feeders to improve supply for consumers in rural areas, (ii) improving sub-transmission and distribution infrastructure in rural areas, and (iii) rural electrification by carrying forward targets specified under the RGGVY.

The total financial outlay for DDUGJY over the implementation period (until 2021-22) is Rs 82,300 crore which includes budgetary support of Rs 68,900 crore.  The central government provides 60% of the project cost as grant, the state power distribution companies (discoms) raise 10% of the funds, and 30% is borrowed from financial institutions and banks.

Status of rural electrification

As of August 2017, about 1% of the villages in India remain un-electrified (3,146 villages).  However, with regard to households, around 23% (4.1 crore households) are yet to be electrified.  Table 1 at the end of this post shows the status of rural electrification across all states.

Issues with rural electrification

Definition of an electrified village

An electrified village is defined as one that has the following: (i) provision of basic infrastructure such as distribution transformers and lines in the inhabited locality, (ii) provision of electricity in public places like schools, panchayat office, health centers, dispensaries, and community centers, and (iii) at least 10% of the total number of households in the village are electrified.[iv]

Therefore, a village is considered to be electrified if 10% of the total number of households in the village have been electrified.  This is apart from the basic infrastructure and electrification of certain public centers in the village.  The Standing Committee on Energy (2013) had observed that according to this definition, a village would be called electrified even if up to 90% of households in it do not have an electricity connection.[v]  It also noted that the infrastructure being provided under the scheme is highly inadequate, unreliable and unsustainable.  The Committee recommended that the actual electrification requirement of villages must be assessed, and it should be ensured that the state discoms provide electricity to the remaining households in the village.

Supply of electricity

The Standing Committee had also noted that while the rural electrification scheme looks at creating infrastructure, the actual supply of electricity to households rests with the state discoms.[v]  These discoms are already facing huge financial losses and hence are unable to supply electricity to the villages.  Discoms continue to supply subsidised power to agricultural and residential consumers, resulting in revenue losses.  Further, the average technical and commercial losses (theft and pilferage of electricity) (AT&C losses) are at around 25%.  While the Ujjwal Discom Assurance Yojana (UDAY) has eased off some of the financial losses of the discoms, it remains to be seen whether discoms are able to reduce the cost-tariff gap and AT&C losses in the future.

It has been recommended that generation capacity should be augmented so that states can meet the additional demand under the rural electrification schemes. Further, the assistance to financially weaker states should be increased so that they can better implement the scheme.[v]

Electricity to below poverty line (BPL) households

Under the rural electrification scheme, the cost for providing free electricity connection per BPL household is Rs 3,000.  It has been observed that this cost per household may be inadequate.[v]  Due to the low cost, the quantity and the quality of work has been getting compromised leading to poor implementation of the scheme.  It has been recommended that the Ministry should revisit the cost provided under the scheme.[v]

The new electrification scheme: Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya)

The new scheme, Saubhagya, seeks to ensure universal household electrification, that is, in both rural and urban areas.  Under Saubhagya, beneficiaries will be identified using the Socio Economic and Caste Census (SECC) 2011 data.  The identified poor households will get free electricity connections.  Other households not covered under the SECC, will be provided electricity connections at a cost of Rs 500.  This amount will be collected by the electricity distribution companies in 10 instalments.

The total outlay of the scheme will be Rs 16,320 crore, of which the central government will provide Rs 12,320 crore.  The outlay for the rural households will be Rs 14,025 crore, of which the centre will provide Rs 10,588 crore.  For urban households the outlay will be Rs 2,295 crore of which the centre will provide Rs. 1,733 crore.

The state discoms will execute the electrification works through contractors or other suitable agencies.  Information technology (mobile apps, web portals) will be used to organise camps in villages to identify beneficiaries.  In order to accelerate the process, applications for electricity connections will be completed on the spot.

So far the focus of electrification schemes has been on rural areas, where typically last mile connectivity has been difficult to provide.  Saubhagya extends the ambit of electrification projects to urban areas as well.  While DDUGJY has focused on the village as the principal unit to measure electrification, the new scheme shifts the targets to household electrification.  While the target for ensuring electricity connection in each household will be a significant step towards ensuring 24×7 power, the question of continuous and quality supply to these households will still rest on the ability of the discoms to provide electricity.  Further, while the scheme provides for free connections, the ability of these households to pay for the electricity they consume may be a concern.

Table 1: Status of rural electrification across states (as of August 2017)

Fig 1 edit

* all villages in Telangana were declared electrified before the bifurcation of the state.
Sources:  Ministry of Power; PRS.

 

[i] “PM launches Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 25, 2017.

[ii] “FAQs on Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 27, 2017.

[iii].  Rural Electrification Policy, Ministry of Power, August 23, 2006, http://powermin.nic.in/sites/default/files/uploads/RE%20Policy_1.pdf.

[iv].  “Office memorandum: Deendayal Upadhyaya Gram Jyoti Yojana”, Ministry of Power, December 3, 2014, http://powermin.nic.in/rural_electrification/pdf/Deendayal_Upadhyaya_Gram_Jyoti_Yojana.pdf.

[v].  “41st Report: Implementation of Rajiv Gandhi Grameen Vidyutikaran Yojana”, Standing Committee on Energy, December 13, 2013, http://164.100.47.134/lsscommittee/Energy/15_Energy_41.pdf.

Yesterday, the Governor of Karnataka promulgated the Karnataka Protection of Right to Freedom of Religion Ordinance, 2022.  The Ordinance prohibits forced religious conversions.  A Bill with the same provisions as the Ordinance was passed by the Karnataka Legislative Assembly in December 2021.   The Bill was pending introduction in the Legislative Council. 

In the recent past, Haryana (2022), Madhya Pradesh (2021), and Uttar Pradesh (2021) have passed laws regulating religious conversions.  In this blog post, we discuss the key provisions of the Karnataka Ordinance and compare it with existing laws in other states (Table 2). 

What religious conversions does the Karnataka Ordinance prohibit?

The Ordinance prohibits forced religious conversions through misrepresentation, coercion, allurement, fraud, or the promise of marriage.  Any person who converts another person unlawfully will be penalised, and all offences will be cognizable and non-bailable.  Penalties for attempting to forcibly convert someone are highlighted in Table 1.  If an institution (such as an orphanage, old age home, or NGO) violates the provisions of the Ordinance, the persons in charge of the institution will be punished as per the provisions in Table 1.   

Table 1: Penalties for forced conversion 

Conversion of

Imprisonment

Fine (in Rs)

Any person through specified means

3-5 years

25,000

Minor, woman, SC/ST, or a person of unsound mind

3-10 years 

50,000

Two or more persons (Mass conversion)

3-10 years 

1,00,000

Sources: Karnataka Protection of Right to Freedom of Religion Ordinance, 2022; PRS.

Re-converting to one’s immediate previous religion will not be considered a conversion under the Ordinance.   Further, any marriage done for the sole purpose of an unlawful conversion will be prohibited, unless the procedure for religious conversion is followed.  

How may one convert their religion?

As per the Ordinance, a person intending to convert their religion is required to send a declaration to the District Magistrate (DM), before and after a conversion ceremony takes place.  The pre-conversion declaration must be submitted by both parties (the person converting their religion, and the religious converter), at least 30 days in advance.  The Ordinance prescribes penalties for both parties for failing to follow procedure.

After receiving the pre-conversion declarations, the DM will notify the proposed religious conversion in public, and invite objections to the proposed conversion for a period of 30 days.  Once a public objection is recorded, the DM will order an enquiry to prove the cause, purpose, and genuine intent of the conversion.  If the enquiry finds that an offence has been committed, the DM may initiate criminal action against the convertor.  A similar procedure is specified for a post-conversion declaration (by the converted person).  

Note that among other states, only Uttar Pradesh requires a post-conversion declaration and a pre-conversion declaration.

After the religious conversion has taken place, the converted person must submit a post-conversion declaration to the DM, within 30 days of the conversion.  Further, the converted person must also appear before the DM to confirm their identity and the contents of the declaration.   If no complaints are received during this time, the DM will notify the conversion, and inform concerned authorities (employer, officials of various government departments, local government bodies, and heads of educational institutions).  

Who may file a complaint?

Similar to laws in other states, any person who has been unlawfully converted, or a person associated to them by blood, marriage, or adoption may file a complaint against an unlawful conversion.   Laws in Haryana and Madhya Pradesh allow certain people (those related by blood, adoption, custodianship, or marriage) to file complaints, after seeking permission from the Court.  Note that the Karnataka Ordinance allows colleagues (or any associated person) to file a complaint against an unlawful conversion.

  image

*In Chirag Singhvi v. State of Rajasthan, the Rajasthan High Court framed guidelines to regulate religious conversions in the state.