Recently, the central government launched the Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya).[i],[ii]  The scheme seeks to ensure universal household electrification (in both rural and urban areas) by providing last mile connectivity.  The scheme is expected to cover three crore households.  Note that currently about four crore households are un-electrified.  A rural electrification scheme has also been under implementation since 2005.  In light of this, we discuss the current situation of, and key issues related to rural electrification in the country.

Regulatory and policy framework

Under the Electricity Act, 2003, the central and state governments have the joint responsibility of providing electricity to rural areas.  The 2003 Act also mandates that the central government should, in consultation with the state governments, provide for a national policy on (i) stand-alone power systems for rural areas (systems that are not connected to the electricity grid), and (ii) electrification and local distribution in rural areas.  Consequently, the Rural Electrification Policy was notified in August 2006.[iii]

The Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), launched in 2005, was the first scheme on rural electrification.  In December 2014, Ministry of Power launched the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), which subsumed the RGGVY.[iv]  Components of DDUGJY include: (i) separation of agricultural and non-agricultural electricity feeders to improve supply for consumers in rural areas, (ii) improving sub-transmission and distribution infrastructure in rural areas, and (iii) rural electrification by carrying forward targets specified under the RGGVY.

The total financial outlay for DDUGJY over the implementation period (until 2021-22) is Rs 82,300 crore which includes budgetary support of Rs 68,900 crore.  The central government provides 60% of the project cost as grant, the state power distribution companies (discoms) raise 10% of the funds, and 30% is borrowed from financial institutions and banks.

Status of rural electrification

As of August 2017, about 1% of the villages in India remain un-electrified (3,146 villages).  However, with regard to households, around 23% (4.1 crore households) are yet to be electrified.  Table 1 at the end of this post shows the status of rural electrification across all states.

Issues with rural electrification

Definition of an electrified village

An electrified village is defined as one that has the following: (i) provision of basic infrastructure such as distribution transformers and lines in the inhabited locality, (ii) provision of electricity in public places like schools, panchayat office, health centers, dispensaries, and community centers, and (iii) at least 10% of the total number of households in the village are electrified.[iv]

Therefore, a village is considered to be electrified if 10% of the total number of households in the village have been electrified.  This is apart from the basic infrastructure and electrification of certain public centers in the village.  The Standing Committee on Energy (2013) had observed that according to this definition, a village would be called electrified even if up to 90% of households in it do not have an electricity connection.[v]  It also noted that the infrastructure being provided under the scheme is highly inadequate, unreliable and unsustainable.  The Committee recommended that the actual electrification requirement of villages must be assessed, and it should be ensured that the state discoms provide electricity to the remaining households in the village.

Supply of electricity

The Standing Committee had also noted that while the rural electrification scheme looks at creating infrastructure, the actual supply of electricity to households rests with the state discoms.[v]  These discoms are already facing huge financial losses and hence are unable to supply electricity to the villages.  Discoms continue to supply subsidised power to agricultural and residential consumers, resulting in revenue losses.  Further, the average technical and commercial losses (theft and pilferage of electricity) (AT&C losses) are at around 25%.  While the Ujjwal Discom Assurance Yojana (UDAY) has eased off some of the financial losses of the discoms, it remains to be seen whether discoms are able to reduce the cost-tariff gap and AT&C losses in the future.

It has been recommended that generation capacity should be augmented so that states can meet the additional demand under the rural electrification schemes. Further, the assistance to financially weaker states should be increased so that they can better implement the scheme.[v]

Electricity to below poverty line (BPL) households

Under the rural electrification scheme, the cost for providing free electricity connection per BPL household is Rs 3,000.  It has been observed that this cost per household may be inadequate.[v]  Due to the low cost, the quantity and the quality of work has been getting compromised leading to poor implementation of the scheme.  It has been recommended that the Ministry should revisit the cost provided under the scheme.[v]

The new electrification scheme: Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya)

The new scheme, Saubhagya, seeks to ensure universal household electrification, that is, in both rural and urban areas.  Under Saubhagya, beneficiaries will be identified using the Socio Economic and Caste Census (SECC) 2011 data.  The identified poor households will get free electricity connections.  Other households not covered under the SECC, will be provided electricity connections at a cost of Rs 500.  This amount will be collected by the electricity distribution companies in 10 instalments.

The total outlay of the scheme will be Rs 16,320 crore, of which the central government will provide Rs 12,320 crore.  The outlay for the rural households will be Rs 14,025 crore, of which the centre will provide Rs 10,588 crore.  For urban households the outlay will be Rs 2,295 crore of which the centre will provide Rs. 1,733 crore.

The state discoms will execute the electrification works through contractors or other suitable agencies.  Information technology (mobile apps, web portals) will be used to organise camps in villages to identify beneficiaries.  In order to accelerate the process, applications for electricity connections will be completed on the spot.

So far the focus of electrification schemes has been on rural areas, where typically last mile connectivity has been difficult to provide.  Saubhagya extends the ambit of electrification projects to urban areas as well.  While DDUGJY has focused on the village as the principal unit to measure electrification, the new scheme shifts the targets to household electrification.  While the target for ensuring electricity connection in each household will be a significant step towards ensuring 24×7 power, the question of continuous and quality supply to these households will still rest on the ability of the discoms to provide electricity.  Further, while the scheme provides for free connections, the ability of these households to pay for the electricity they consume may be a concern.

Table 1: Status of rural electrification across states (as of August 2017)

Fig 1 edit

* all villages in Telangana were declared electrified before the bifurcation of the state.
Sources:  Ministry of Power; PRS.

 

[i] “PM launches Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 25, 2017.

[ii] “FAQs on Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 27, 2017.

[iii].  Rural Electrification Policy, Ministry of Power, August 23, 2006, http://powermin.nic.in/sites/default/files/uploads/RE%20Policy_1.pdf.

[iv].  “Office memorandum: Deendayal Upadhyaya Gram Jyoti Yojana”, Ministry of Power, December 3, 2014, http://powermin.nic.in/rural_electrification/pdf/Deendayal_Upadhyaya_Gram_Jyoti_Yojana.pdf.

[v].  “41st Report: Implementation of Rajiv Gandhi Grameen Vidyutikaran Yojana”, Standing Committee on Energy, December 13, 2013, http://164.100.47.134/lsscommittee/Energy/15_Energy_41.pdf.

Listed below are some key Bills pending in Parliament that are expected to address various aspects of corruption in India. These Bills need to be scrutinized carefully by both lawmakers and citizens alike, so as the strengthen them. Citizen groups can engage in a variety of ways to get their views heard, which have been described in the primer on Engaging with Policy Makers. Some of these anti-corruption Bills are listed in the current Winter Session for consideration and passing. These are marked in red below. (The full list of all Bills being considered in the Winter Session can be accessed here.) Each Bill below has been hyperlinked to a page which has the text of the Bill, the report of the Standing Committee, PRS analysis, and other relevant documents, all in one place. Spreading this message to a number of interested people will be a very useful contribution by all those interested in building greater engagement of people with what happens in Parliament.  

Bill

Date of introduction

Status

Brief description

The Lokpal and Lokayuktas Bill, 2011 (Listed for passing) December 22, 2011 Passed by Lok Sabha on 27 Dec 2011. Report of Rajya Sabha Select Committee submitted on November 23, 2012. It seeks to establish the office of the Lok Pal at the centre and Lokayuktas in states for inquiring into complaints against certain public servants.The Bill once passed shall be applicable to states if they give their consent to its application.
The Whistle Blowers Protection Bill, 2011 (Listed for passing) August 26, 2010 Passed by Lok Sabha on December 27, 2011. Pending in Rajya Sabha It seeks to protect whistleblowers (person making a disclosure related to acts of corruption, misuse of power or criminal offence).Under the Bill any person including a public servant may make such a disclosure to the Central or State Vigilance Commission.The identity of the complainant shall not be disclosed.
The Benami Transactions (Prohibition) Bill, 2011 August 18, 2011 Standing Committee submitted its Report on June 26, 2012 The Bill prohibits all persons from entering into benami transactions (property transactions in the name of another person).Any benami property shall be confiscated by the central government.It seeks to replace the existing Benami Transactions (Prohibition) Act, 1988.
The Prevention of Bribery of Foreign Public Officials and Officials of Public International Organisations Bill, 2011 (Listed for passing) March 25, 2011 Standing Committee  submitted its Report on March 29, 2012 Indiais a signatory to the UN Convention against corruption. The Bill is necessary for India to ratify the Convention.The Bill makes it an offence to accept or offer a bribe to foreign public officials and officials of public international organizations in order to obtain or retain international business
The Right of Citizens for Time Bound Delivery of Goods and Services and Redressal of their Grievances Bill, 2011 December 20, 2011 Standing Committee submitted its Report on August 28, 2012 It requires every public authority to publish a citizen charter within six months of commencement of the Act.The charter should detail the goods and services to be provided and the timeline for their delivery.
The Electronic Delivery of Services Bill, 2011 December 27, 2011 Standing Committee submitted its Report on August 30, 2012 The Bill requires all public authorities to deliver all public services electronically within a maximum period of eight years.There are two exceptions to this requirement: (a) service which cannot be delivered electronically; and (b) services that the public authorities in consultation with the respective Central and State EDS Commissions decide not to deliver electronically.
The Prevention of Money-Laundering (Amendment) Bill, 2011 (Listed for passing) December 27, 2011 Standing Committee submitted its Report on May 9, 2012 The Bill Amends the Prevention of Money Laundering Act, 2002.This Bill widens the definition of offences under money laundering to include activities like concealment, acquisition, possession and use of proceeds of crime.It provides for the provisional attachment and confiscation of property (for a maximum period of 180 days).
The National Identification Authority of India Bill, 2010 December 3, 2010 Standing Committee  submitted its Report on December 13,  2011 The Bill seeks to establish the National Identification Authority of India to issue unique identification numbers (called ‘Aadhaar’) to residents ofIndia.Every person residing inIndia(regardless of citizenship) is entitled to obtain an Aadhaar number after furnishing the required information.The number shall serve as an identity proof.  But not as a citizenship proof.
The Judicial Standards and Accountability Bill, 2010 December 1, 2010 Passed by Lok Sabha on March 29, 2012; Pending in Rajya Sabha It replaces the Judges (Inquiry) Act, 1968.  It provides for enforceable standards for the conduct of High Court and Supreme Court judges.The Bill requires judges and their spouses and children to declare their assets and liabilities.  It also establishes a process for the removal of judges of Supreme Court and High Court
The Public Procurement Bill, 2012 May 14, 2012 Standing Committee Report pending The Bill seeks to regulate and ensure transparency in the procurement process.  It applies to procurement processes above Rs 50 lakh.The procuring entity shall adhere to certain standards such as (a) ensuring efficiency and economy; and (b) provide fair and equitable treatment to bidders.

Sources: Respective Bills, PRS Legislative Research