Recently, the central government launched the Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya).[i],[ii]  The scheme seeks to ensure universal household electrification (in both rural and urban areas) by providing last mile connectivity.  The scheme is expected to cover three crore households.  Note that currently about four crore households are un-electrified.  A rural electrification scheme has also been under implementation since 2005.  In light of this, we discuss the current situation of, and key issues related to rural electrification in the country.

Regulatory and policy framework

Under the Electricity Act, 2003, the central and state governments have the joint responsibility of providing electricity to rural areas.  The 2003 Act also mandates that the central government should, in consultation with the state governments, provide for a national policy on (i) stand-alone power systems for rural areas (systems that are not connected to the electricity grid), and (ii) electrification and local distribution in rural areas.  Consequently, the Rural Electrification Policy was notified in August 2006.[iii]

The Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), launched in 2005, was the first scheme on rural electrification.  In December 2014, Ministry of Power launched the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), which subsumed the RGGVY.[iv]  Components of DDUGJY include: (i) separation of agricultural and non-agricultural electricity feeders to improve supply for consumers in rural areas, (ii) improving sub-transmission and distribution infrastructure in rural areas, and (iii) rural electrification by carrying forward targets specified under the RGGVY.

The total financial outlay for DDUGJY over the implementation period (until 2021-22) is Rs 82,300 crore which includes budgetary support of Rs 68,900 crore.  The central government provides 60% of the project cost as grant, the state power distribution companies (discoms) raise 10% of the funds, and 30% is borrowed from financial institutions and banks.

Status of rural electrification

As of August 2017, about 1% of the villages in India remain un-electrified (3,146 villages).  However, with regard to households, around 23% (4.1 crore households) are yet to be electrified.  Table 1 at the end of this post shows the status of rural electrification across all states.

Issues with rural electrification

Definition of an electrified village

An electrified village is defined as one that has the following: (i) provision of basic infrastructure such as distribution transformers and lines in the inhabited locality, (ii) provision of electricity in public places like schools, panchayat office, health centers, dispensaries, and community centers, and (iii) at least 10% of the total number of households in the village are electrified.[iv]

Therefore, a village is considered to be electrified if 10% of the total number of households in the village have been electrified.  This is apart from the basic infrastructure and electrification of certain public centers in the village.  The Standing Committee on Energy (2013) had observed that according to this definition, a village would be called electrified even if up to 90% of households in it do not have an electricity connection.[v]  It also noted that the infrastructure being provided under the scheme is highly inadequate, unreliable and unsustainable.  The Committee recommended that the actual electrification requirement of villages must be assessed, and it should be ensured that the state discoms provide electricity to the remaining households in the village.

Supply of electricity

The Standing Committee had also noted that while the rural electrification scheme looks at creating infrastructure, the actual supply of electricity to households rests with the state discoms.[v]  These discoms are already facing huge financial losses and hence are unable to supply electricity to the villages.  Discoms continue to supply subsidised power to agricultural and residential consumers, resulting in revenue losses.  Further, the average technical and commercial losses (theft and pilferage of electricity) (AT&C losses) are at around 25%.  While the Ujjwal Discom Assurance Yojana (UDAY) has eased off some of the financial losses of the discoms, it remains to be seen whether discoms are able to reduce the cost-tariff gap and AT&C losses in the future.

It has been recommended that generation capacity should be augmented so that states can meet the additional demand under the rural electrification schemes. Further, the assistance to financially weaker states should be increased so that they can better implement the scheme.[v]

Electricity to below poverty line (BPL) households

Under the rural electrification scheme, the cost for providing free electricity connection per BPL household is Rs 3,000.  It has been observed that this cost per household may be inadequate.[v]  Due to the low cost, the quantity and the quality of work has been getting compromised leading to poor implementation of the scheme.  It has been recommended that the Ministry should revisit the cost provided under the scheme.[v]

The new electrification scheme: Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya)

The new scheme, Saubhagya, seeks to ensure universal household electrification, that is, in both rural and urban areas.  Under Saubhagya, beneficiaries will be identified using the Socio Economic and Caste Census (SECC) 2011 data.  The identified poor households will get free electricity connections.  Other households not covered under the SECC, will be provided electricity connections at a cost of Rs 500.  This amount will be collected by the electricity distribution companies in 10 instalments.

The total outlay of the scheme will be Rs 16,320 crore, of which the central government will provide Rs 12,320 crore.  The outlay for the rural households will be Rs 14,025 crore, of which the centre will provide Rs 10,588 crore.  For urban households the outlay will be Rs 2,295 crore of which the centre will provide Rs. 1,733 crore.

The state discoms will execute the electrification works through contractors or other suitable agencies.  Information technology (mobile apps, web portals) will be used to organise camps in villages to identify beneficiaries.  In order to accelerate the process, applications for electricity connections will be completed on the spot.

So far the focus of electrification schemes has been on rural areas, where typically last mile connectivity has been difficult to provide.  Saubhagya extends the ambit of electrification projects to urban areas as well.  While DDUGJY has focused on the village as the principal unit to measure electrification, the new scheme shifts the targets to household electrification.  While the target for ensuring electricity connection in each household will be a significant step towards ensuring 24×7 power, the question of continuous and quality supply to these households will still rest on the ability of the discoms to provide electricity.  Further, while the scheme provides for free connections, the ability of these households to pay for the electricity they consume may be a concern.

Table 1: Status of rural electrification across states (as of August 2017)

Fig 1 edit

* all villages in Telangana were declared electrified before the bifurcation of the state.
Sources:  Ministry of Power; PRS.

 

[i] “PM launches Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 25, 2017.

[ii] “FAQs on Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 27, 2017.

[iii].  Rural Electrification Policy, Ministry of Power, August 23, 2006, http://powermin.nic.in/sites/default/files/uploads/RE%20Policy_1.pdf.

[iv].  “Office memorandum: Deendayal Upadhyaya Gram Jyoti Yojana”, Ministry of Power, December 3, 2014, http://powermin.nic.in/rural_electrification/pdf/Deendayal_Upadhyaya_Gram_Jyoti_Yojana.pdf.

[v].  “41st Report: Implementation of Rajiv Gandhi Grameen Vidyutikaran Yojana”, Standing Committee on Energy, December 13, 2013, http://164.100.47.134/lsscommittee/Energy/15_Energy_41.pdf.

According to a recent press release, the Cabinet has approved a proposal to introduce a Bill in Parliament to amend the Indian Penal Code, 1860 (IPC).  While the draft Bill is currently not available, its highlights are specified in the press release.  As per the press release, the Bill aims to make rape laws gender neutral.  The key features specified are:

  • Substituting the word “rape” with “sexual assault”;
  • Increasing the age of consent 16 to 18 years;
  • Excluding sexual intercourse between a married couple from the definition of rape, where the wife's consent has not been obtained and the wife is at least 16 years of age.

Present Law According to section 375 of the IPC, an allegation of rape has to satisfy the following criteria:

  • sexual intercourse between a man with a woman in the following circumstances: (a) against the will of the woman; (b) without her consent; (c) under duress; (d) consent obtained by fraud; (e) consent obtained by reason of unsoundness of mind or intoxication.
  • If the woman is below the age of 16 years, sexual intercourse is deemed to amount to rape.  Even if the woman has consented, it would be considered rape under the law.
  • There is however, an exception to this definition of rape.  Un-consented sexual intercourse between a man and his wife would not amount to rape if the wife is 16 years or older.

This definition of rape does not include use of other body parts or foreign objects by the offender upon the victim’s body.  Such offences are classified as “use of criminal force to outrage the modesty of a woman” (see here) and are punishable with two years imprisonment or fine or both.  Rape, on the other hand, is punishable with imprisonment for seven years to a life term. Proposals to amend the law on rape Through an order in 1999, the Supreme Court had directed the Law Commission to review the law on rape (Sakshi vs. Union of India).  The Law Commission had in its 172nd Report, dated March 25, 2000 made recommendations to amend the law to widen the definition of rape.  In its report, the Commission had recommended that rape be substituted by sexual assault as an offence.  Such assault included the use of any object for penetration.  It further recognised that there was an increase in the incidence of sexual assaults against boys.  The Report recommended the widening of the definition of rape to include circumstances where both men and women could be perpetrators and victims of sexual assault.[1]   Amendments to the law on the basis of these recommendations are still awaited. The High Court of Delhi has recognised the need to amend the laws on rape.  It observed that the law did not adequately safeguard victims against sexual assaults which were included by the Law Commission within the scope of rape.  It was observed that the definition should be widened to include instances of sexual assault which may not satisfy the penile-vaginal penetration required under the existing law. The 2010 draft Criminal Laws Amendment Bill, released by the Ministry of Home Affairs, attempted to redefine rape.  The draft provisions substitute the offence of rape with “sexual assault”.  Sexual assault is defined as penetration of the vagina, the anus or urethra or mouth of any woman, by a man, with (i) any part of his body; or (ii) any object manipulated by such man under the following circumstances: (a) against the will of the woman; (b) without her consent; (c) under duress; (d) consent obtained by fraud; (e) consent obtained by reason of unsoundness of mind or intoxication; and (f) when the woman is below the age of 18. Variation between proposals The existing legal provisions, the Law Commission Report, the 2010 Bill and the recent press release are similar in that they provide an exception to marital rape.  Under the law, un-consented sexual intercourse is not an offence if the wife is above a certain age.  (Under the existing law the wife has to be over 16 years’ of age and as per press release she has to be more than 18 years old.)  This is at variance with the proposal of the National Commission of Women (NCW).   An amendment to the IPC recommended by the NCW deleted the exemption granted to un-consented sex between a man and his wife if she was more than 16 years old.  It therefore criminalised marital rape. As per the press release, this exemption has been retained in the proposed Bill.  Furthermore, as per the release, while the age of consent for sexual intercourse will be increased to 18 years, for the purpose of marital sex, the age of consent would be 16 years.


[1] Review of Rape Laws, Law Commission of India, 172nd Report, paragraph 3.1.2,  "375.  Sexual Assault:  Sexual assault means - (a) penetrating  the  vagina (which term shall include the labia majora), the  anus  or  urethra  of  any person with - i)      any part of the body of another person or ii)   an object manipulated by another person except  where  such penetration is carried out for proper hygienic or medical purposes; (b) manipulating any  part  of  the  body  of  another person  so  as  to cause penetration of the vagina (which term shall include the labia  majora),  the anus or the urethra of the offender by any part of  the other person's body; (c) introducing any part of the penis of a person into the mouth of another person; (d)    engaging in cunnilingus or fellatio; or (e) continuing  sexual  assault  as defined in clauses (a) to (d) above in circumstances falling  under  any  of  the  six following descriptions: ... Exception:  Sexual intercourse by a man with his own wife, the wife not being under sixteen  years  of  age,  is  not sexual assault."