Recently, the central government launched the Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya).[i],[ii] The scheme seeks to ensure universal household electrification (in both rural and urban areas) by providing last mile connectivity. The scheme is expected to cover three crore households. Note that currently about four crore households are un-electrified. A rural electrification scheme has also been under implementation since 2005. In light of this, we discuss the current situation of, and key issues related to rural electrification in the country.
Regulatory and policy framework
Under the Electricity Act, 2003, the central and state governments have the joint responsibility of providing electricity to rural areas. The 2003 Act also mandates that the central government should, in consultation with the state governments, provide for a national policy on (i) stand-alone power systems for rural areas (systems that are not connected to the electricity grid), and (ii) electrification and local distribution in rural areas. Consequently, the Rural Electrification Policy was notified in August 2006.[iii]
The Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), launched in 2005, was the first scheme on rural electrification. In December 2014, Ministry of Power launched the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), which subsumed the RGGVY.[iv] Components of DDUGJY include: (i) separation of agricultural and non-agricultural electricity feeders to improve supply for consumers in rural areas, (ii) improving sub-transmission and distribution infrastructure in rural areas, and (iii) rural electrification by carrying forward targets specified under the RGGVY.
The total financial outlay for DDUGJY over the implementation period (until 2021-22) is Rs 82,300 crore which includes budgetary support of Rs 68,900 crore. The central government provides 60% of the project cost as grant, the state power distribution companies (discoms) raise 10% of the funds, and 30% is borrowed from financial institutions and banks.
Status of rural electrification
As of August 2017, about 1% of the villages in India remain un-electrified (3,146 villages). However, with regard to households, around 23% (4.1 crore households) are yet to be electrified. Table 1 at the end of this post shows the status of rural electrification across all states.
Issues with rural electrification
Definition of an electrified village
An electrified village is defined as one that has the following: (i) provision of basic infrastructure such as distribution transformers and lines in the inhabited locality, (ii) provision of electricity in public places like schools, panchayat office, health centers, dispensaries, and community centers, and (iii) at least 10% of the total number of households in the village are electrified.[iv]
Therefore, a village is considered to be electrified if 10% of the total number of households in the village have been electrified. This is apart from the basic infrastructure and electrification of certain public centers in the village. The Standing Committee on Energy (2013) had observed that according to this definition, a village would be called electrified even if up to 90% of households in it do not have an electricity connection.[v] It also noted that the infrastructure being provided under the scheme is highly inadequate, unreliable and unsustainable. The Committee recommended that the actual electrification requirement of villages must be assessed, and it should be ensured that the state discoms provide electricity to the remaining households in the village.
Supply of electricity
The Standing Committee had also noted that while the rural electrification scheme looks at creating infrastructure, the actual supply of electricity to households rests with the state discoms.[v] These discoms are already facing huge financial losses and hence are unable to supply electricity to the villages. Discoms continue to supply subsidised power to agricultural and residential consumers, resulting in revenue losses. Further, the average technical and commercial losses (theft and pilferage of electricity) (AT&C losses) are at around 25%. While the Ujjwal Discom Assurance Yojana (UDAY) has eased off some of the financial losses of the discoms, it remains to be seen whether discoms are able to reduce the cost-tariff gap and AT&C losses in the future.
It has been recommended that generation capacity should be augmented so that states can meet the additional demand under the rural electrification schemes. Further, the assistance to financially weaker states should be increased so that they can better implement the scheme.[v]
Electricity to below poverty line (BPL) households
Under the rural electrification scheme, the cost for providing free electricity connection per BPL household is Rs 3,000. It has been observed that this cost per household may be inadequate.[v] Due to the low cost, the quantity and the quality of work has been getting compromised leading to poor implementation of the scheme. It has been recommended that the Ministry should revisit the cost provided under the scheme.[v]
The new electrification scheme: Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya)
The new scheme, Saubhagya, seeks to ensure universal household electrification, that is, in both rural and urban areas. Under Saubhagya, beneficiaries will be identified using the Socio Economic and Caste Census (SECC) 2011 data. The identified poor households will get free electricity connections. Other households not covered under the SECC, will be provided electricity connections at a cost of Rs 500. This amount will be collected by the electricity distribution companies in 10 instalments.
The total outlay of the scheme will be Rs 16,320 crore, of which the central government will provide Rs 12,320 crore. The outlay for the rural households will be Rs 14,025 crore, of which the centre will provide Rs 10,588 crore. For urban households the outlay will be Rs 2,295 crore of which the centre will provide Rs. 1,733 crore.
The state discoms will execute the electrification works through contractors or other suitable agencies. Information technology (mobile apps, web portals) will be used to organise camps in villages to identify beneficiaries. In order to accelerate the process, applications for electricity connections will be completed on the spot.
So far the focus of electrification schemes has been on rural areas, where typically last mile connectivity has been difficult to provide. Saubhagya extends the ambit of electrification projects to urban areas as well. While DDUGJY has focused on the village as the principal unit to measure electrification, the new scheme shifts the targets to household electrification. While the target for ensuring electricity connection in each household will be a significant step towards ensuring 24×7 power, the question of continuous and quality supply to these households will still rest on the ability of the discoms to provide electricity. Further, while the scheme provides for free connections, the ability of these households to pay for the electricity they consume may be a concern.
Table 1: Status of rural electrification across states (as of August 2017)
[i] “PM launches Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 25, 2017.
[ii] “FAQs on Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 27, 2017.
[iii]. Rural Electrification Policy, Ministry of Power, August 23, 2006, http://powermin.nic.in/sites/default/files/uploads/RE%20Policy_1.pdf.
[iv]. “Office memorandum: Deendayal Upadhyaya Gram Jyoti Yojana”, Ministry of Power, December 3, 2014, http://powermin.nic.in/rural_electrification/pdf/Deendayal_Upadhyaya_Gram_Jyoti_Yojana.pdf.
[v]. “41st Report: Implementation of Rajiv Gandhi Grameen Vidyutikaran Yojana”, Standing Committee on Energy, December 13, 2013, http://164.100.47.134/lsscommittee/Energy/15_Energy_41.pdf.
As of May 22, 2020, there are 1,18,447 confirmed cases of COVID-19 in India, which is 76% higher than the cases on May 11, 2020 (67,152). Out of total confirmed cases, there are 66,330 active cases, 48,354 patients have been cured/discharged and 3,583 have died (Figure 1). As the spread of COVID-19 has increased across India, the central government has continued to announce several policy decisions to contain the spread, and support citizens and businesses who are being affected by the pandemic. In this blog post, we summarise some of the key measures taken by the central government in this regard between May 11 and May 22, 2020.
Figure 1: Number of day wise COVID 19 cases as on May 22, 2020
Aatma Nirbhar Bharat Abhiyaan
On May 12, the Prime Minister, Mr. Narendra Modi, announced a special economic package of Rs 20 lakh crore (equivalent to 10% of India’s GDP) aimed towards making the country ready for the tough competition in the global supply chain and empowering the poor, labourers, migrants who have been adversely affected by COVID-19. Following this announcement, the Finance Minister, Ms. Nirmala Sitharaman, in five press conferences, announced the detailed measures under the economic package. The economic package includes earlier measures taken by the government to support the citizens and businesses of India. A break-up of the package is presented in Table 1.
Table 1: Break-up of stimulus from Aatma Nirbhar Bharat Abhiyaan package
Item |
Key Topics covered |
Amount (in Rs crore) |
Stimulus from earlier measures |
Pradhan Mantri Garib Kalyan Yojana, Tax Concessions, and the Prime Minister's announcement for health sector |
1,92,800 |
Part 1 |
Business including Micro, Small and Medium Enterprises (MSMEs) |
5,94,550 |
Part 2 |
Poor people including migrants and farmers. |
3,10,000 |
Part 3 |
Agriculture and allied sectors. |
1,50,000 |
Part 4 and Part 5 |
Part 4: Coal and mineral sectors, defence sector, civil Aviation, airports and aircraft Maintenance, Repair and Overhaul (MRO), power sector, social infrastructures, space, atomic energy. Part 5: Government reforms and other provisions including public health and education, additional allocation to MGNREGS |
48,100 |
Sub Total |
|
1,295,400 |
RBI Measures (Actual) |
Reduction in Cash Reserve Ratio (CRR), Special Liquidity Facility (SLF) for mutual funds, Special refinance facilities for NABARD, SIDBI and NHB at policy repo rate |
8,01,603 |
Grand Total |
|
20,97,053 |
Note: Part 1, 2, 3, 4, 5 in the table above represents the five press conferences conducted by the Finance Minister to announce the details of the economic package.
Source: Presentation made by Union Finance & Corporate Affairs Minister Smt. Nirmala Sitharaman under Aatmanirbhar Bharat Abhiyaan to support Indian economy in fight against COVID-19, Ministry of Finance, May 13, 2020, PRS.
For more information on the details of the announcements made under Aatma Nirbhar Bharat Abhiyaan, please see here.
Finance
Following the Prime Minister’s and Finance Minister’s announcements, further announcements were also made.
Lockdown 4.0
The Ministry of Home Affairs (MHA) passed an order extending the lockdown till May 31, 2020. This lockdown will have more relaxations compared to earlier lockdowns.
Zoning of areas
The new guidelines have authorised states/union territories (UTs) to define the red, green and orange zones based on the parameters prescribed by the Health Ministry. The states/UTs can define a district, or a municipal corporation/ municipality or even smaller administrative units such as sub-divisions, etc. as a red or green or orange zone.
The prohibition of certain activities or restrictions in various zones within a state will be at the discretion of the state/union territory as deemed necessary.
Prohibited Activities
Some activities will continue to remain prohibited throughout the country. These include:
Online/ distance learning is encouraged and permitted; and, restaurants will be allowed to operate kitchens for home delivery of food items.
National Directives for COVID Management
The Ministry of Home Affairs issued the National Directives for COVID Management, which apply to public places and work places. As per these guidelines:
Guidelines for workplaces include:
Aarogya Setu
The District authorities will ensure installation of the Aarogya Setu application on compatible mobile phones of all individuals and will have to regularly update their health status on the app.
Aarogya Setu Data access and knowledge sharing protocol, 2020
The Ministry of Electronics and Information Technology, Government of India issued a notification on the data access and knowledge sharing protocol, 2020 in reference to the Aarogya Setu mobile application. The protocol will: (i) ensure secure collection of data by the mobile application, (ii) protect the personal data of individuals, and (iii) ensure efficient use and sharing of personal or non-personal data of the application users. The protocol provides principles for: (i) collection and processing of response data, (ii) sharing of response data, (iii) obligations of entities with whom the data will be shared, and (iv) sharing of data for research purpose. A sunset clause is applicable to the protocol subjecting it to a review after 6 months unless there is any extension of sunset clause in wake of the pandemic.
Travel and Movement
Health
The Ministry of Health and Family Welfare issued: (i) updated containment plan on COVID-19, and (ii) updated containment plan for large outbreaks of COVID 19. These plans provide information on various scenarios of COVID-19 and strategies to control the spread of the disease including definitions, action plans and specific details on (i) identification of containment zones and buffer zones; (ii) perimeter control; (iii) support from various stakeholders such as testing laboratories and hospitals; (iv) pharamaceutical and non-pharmaceutical interventions; and (v) risk communication.
For more information on the spread of COVID-19 and the central and state government response to the pandemic, please see here.