Recently, the central government launched the Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya).[i],[ii]  The scheme seeks to ensure universal household electrification (in both rural and urban areas) by providing last mile connectivity.  The scheme is expected to cover three crore households.  Note that currently about four crore households are un-electrified.  A rural electrification scheme has also been under implementation since 2005.  In light of this, we discuss the current situation of, and key issues related to rural electrification in the country.

Regulatory and policy framework

Under the Electricity Act, 2003, the central and state governments have the joint responsibility of providing electricity to rural areas.  The 2003 Act also mandates that the central government should, in consultation with the state governments, provide for a national policy on (i) stand-alone power systems for rural areas (systems that are not connected to the electricity grid), and (ii) electrification and local distribution in rural areas.  Consequently, the Rural Electrification Policy was notified in August 2006.[iii]

The Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), launched in 2005, was the first scheme on rural electrification.  In December 2014, Ministry of Power launched the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), which subsumed the RGGVY.[iv]  Components of DDUGJY include: (i) separation of agricultural and non-agricultural electricity feeders to improve supply for consumers in rural areas, (ii) improving sub-transmission and distribution infrastructure in rural areas, and (iii) rural electrification by carrying forward targets specified under the RGGVY.

The total financial outlay for DDUGJY over the implementation period (until 2021-22) is Rs 82,300 crore which includes budgetary support of Rs 68,900 crore.  The central government provides 60% of the project cost as grant, the state power distribution companies (discoms) raise 10% of the funds, and 30% is borrowed from financial institutions and banks.

Status of rural electrification

As of August 2017, about 1% of the villages in India remain un-electrified (3,146 villages).  However, with regard to households, around 23% (4.1 crore households) are yet to be electrified.  Table 1 at the end of this post shows the status of rural electrification across all states.

Issues with rural electrification

Definition of an electrified village

An electrified village is defined as one that has the following: (i) provision of basic infrastructure such as distribution transformers and lines in the inhabited locality, (ii) provision of electricity in public places like schools, panchayat office, health centers, dispensaries, and community centers, and (iii) at least 10% of the total number of households in the village are electrified.[iv]

Therefore, a village is considered to be electrified if 10% of the total number of households in the village have been electrified.  This is apart from the basic infrastructure and electrification of certain public centers in the village.  The Standing Committee on Energy (2013) had observed that according to this definition, a village would be called electrified even if up to 90% of households in it do not have an electricity connection.[v]  It also noted that the infrastructure being provided under the scheme is highly inadequate, unreliable and unsustainable.  The Committee recommended that the actual electrification requirement of villages must be assessed, and it should be ensured that the state discoms provide electricity to the remaining households in the village.

Supply of electricity

The Standing Committee had also noted that while the rural electrification scheme looks at creating infrastructure, the actual supply of electricity to households rests with the state discoms.[v]  These discoms are already facing huge financial losses and hence are unable to supply electricity to the villages.  Discoms continue to supply subsidised power to agricultural and residential consumers, resulting in revenue losses.  Further, the average technical and commercial losses (theft and pilferage of electricity) (AT&C losses) are at around 25%.  While the Ujjwal Discom Assurance Yojana (UDAY) has eased off some of the financial losses of the discoms, it remains to be seen whether discoms are able to reduce the cost-tariff gap and AT&C losses in the future.

It has been recommended that generation capacity should be augmented so that states can meet the additional demand under the rural electrification schemes. Further, the assistance to financially weaker states should be increased so that they can better implement the scheme.[v]

Electricity to below poverty line (BPL) households

Under the rural electrification scheme, the cost for providing free electricity connection per BPL household is Rs 3,000.  It has been observed that this cost per household may be inadequate.[v]  Due to the low cost, the quantity and the quality of work has been getting compromised leading to poor implementation of the scheme.  It has been recommended that the Ministry should revisit the cost provided under the scheme.[v]

The new electrification scheme: Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya)

The new scheme, Saubhagya, seeks to ensure universal household electrification, that is, in both rural and urban areas.  Under Saubhagya, beneficiaries will be identified using the Socio Economic and Caste Census (SECC) 2011 data.  The identified poor households will get free electricity connections.  Other households not covered under the SECC, will be provided electricity connections at a cost of Rs 500.  This amount will be collected by the electricity distribution companies in 10 instalments.

The total outlay of the scheme will be Rs 16,320 crore, of which the central government will provide Rs 12,320 crore.  The outlay for the rural households will be Rs 14,025 crore, of which the centre will provide Rs 10,588 crore.  For urban households the outlay will be Rs 2,295 crore of which the centre will provide Rs. 1,733 crore.

The state discoms will execute the electrification works through contractors or other suitable agencies.  Information technology (mobile apps, web portals) will be used to organise camps in villages to identify beneficiaries.  In order to accelerate the process, applications for electricity connections will be completed on the spot.

So far the focus of electrification schemes has been on rural areas, where typically last mile connectivity has been difficult to provide.  Saubhagya extends the ambit of electrification projects to urban areas as well.  While DDUGJY has focused on the village as the principal unit to measure electrification, the new scheme shifts the targets to household electrification.  While the target for ensuring electricity connection in each household will be a significant step towards ensuring 24×7 power, the question of continuous and quality supply to these households will still rest on the ability of the discoms to provide electricity.  Further, while the scheme provides for free connections, the ability of these households to pay for the electricity they consume may be a concern.

Table 1: Status of rural electrification across states (as of August 2017)

Fig 1 edit

* all villages in Telangana were declared electrified before the bifurcation of the state.
Sources:  Ministry of Power; PRS.

 

[i] “PM launches Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 25, 2017.

[ii] “FAQs on Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 27, 2017.

[iii].  Rural Electrification Policy, Ministry of Power, August 23, 2006, http://powermin.nic.in/sites/default/files/uploads/RE%20Policy_1.pdf.

[iv].  “Office memorandum: Deendayal Upadhyaya Gram Jyoti Yojana”, Ministry of Power, December 3, 2014, http://powermin.nic.in/rural_electrification/pdf/Deendayal_Upadhyaya_Gram_Jyoti_Yojana.pdf.

[v].  “41st Report: Implementation of Rajiv Gandhi Grameen Vidyutikaran Yojana”, Standing Committee on Energy, December 13, 2013, http://164.100.47.134/lsscommittee/Energy/15_Energy_41.pdf.

On October 18, it was reportein the news that the central government has been given more time for framing rules under the Citizenship (Amendment) Act, 2019.  The President had given assent to this Act in December 2019 and the Act came into force in January 2020.   Similarly, about two years have passed since the new labour codes were passed by Parliament, and the final Rules are yet to be published.  This raises the question how long the government can take to frame Rules and what is the procedure guiding this.  In this blog, we discuss the same.

Under the Constitution, the Legislature has the power to make laws and the Executive is responsible for implementing them.  Often, the Legislature enacts a law covering the general principles and policies, and delegates the power to the Executive for specifying certain details for the implementation of a law.  For example, the Citizenship Amendment Act provides who will be eligible for citizenship.  The certificate of registration or naturalization to a person will be issued, subject to conditions, restrictions, and manner as may be prescribed by the central government through Rules.  Delay in framing Rules results in delay in implementing the law, since the necessary details are not available.  For example, new labour codes provide a social security scheme for gig economy workers such as Swiggy and Zomato delivery persons and Uber and Ola drivers.  These benefits as per these Codes are yet to be rolled out as the Rules are yet to be notified.

Timelines and checks and balances for adherence

Each House of Parliament has a Committee of Members to examine Rules, Regulations, and government orders in detail called the Committee on Subordinate Legislation.  Over the years, the recommendations of these Committees have shaped the evolution of the procedure and timelines for framing subordinate legislation.  These are reflected in the Manual of Parliamentary Procedures issued by the Ministry of Parliamentary Affairs, which provides detailed guidelines.

Ordinarily, Rules, Regulations, and bye-laws are to be framed within six months from the date on which the concerned Act came into force.   Post that, the concerned Ministry is required to seek an extension from the Parliamentary Committees on Subordinate Legislation.  The reason for the extension needs to be stated.   Such extensions may be granted for a maximum period of three months at a time.  For example, in case of Rules under the Citizenship Amendment Act, 2019, at an earlier instance, an extension was granted on account of the onset of the COVID-19 pandemic.

Activity

Timeline

  • Publication of Rules, Regulations, and Bye-Laws, where public consultation is required under the Act
  • A minimum of 30 days for public feedback
  • Consequently, for publication,
  • Three months, if the number of suggestions is small
  • Six months, if the number of suggestions is large
  • Publication of Rules, Regulations, and Bye-Laws, not requiring public consultation
  • Six months from the date on which the concerned Act came into force
  • Any extension for publication
  • A maximum of three months at a time

To ensure monitoring, every Ministry is required to prepare a quarterly report on the status of subordinate legislation not framed and share it with the Ministry of Law and Justice.  These reports are not available in the public domain.

Recommendations to address delays

Over the years, the Subordinate Legislation Committees in both Houses have observed multiple instances of non-adherence to the above timelines by various Ministries.  To address this, they have made the following key recommendations:

  • Statement on reasons for the delay: In 2011, Rajya Sabha Committee recommended that while laying Rules/Regulations before Parliament, the Ministry should also lay a statement explaining the reasons for the delay, if any.
  • Scrutiny of delays by the Cabinet Secretary:  In 2016, the Rajya Sabha Committee recommended that the Cabinet Secretary should continue the practice of calling the Secretaries of concerned Ministries/Departments, to explain the reasons for the delay in framing the subordinate legislation.  Each Ministry should send a quarterly status report to the Cabinet Secretariat.
  • Revisiting guidelines: In 2011, Lok Sabha Committee recommended that the 1986 guidelines should be revisited and all major recommendations of the Committee should be incorporated.  However, as per the Action Taken Report, the government observed that the ministries consider the extant guidelines adequate and these guidelines were re-iterated in 2012.

Are all Rules under an Act required to be framed?

Usually, the expressions used in an Act are “The Central Government may, by notification, make rules for carrying out the provisions of this Act.”, or “as may be prescribed”.  Hence, it may appear that the laws aim to enable rule-making instead of mandate rule-making.  However, certain provisions of an Act cannot be brought into force if the required details have not been prescribed under the Rules.  This makes the implementation of the Act consequent to the publication of respective Rules.  For example, the Criminal Procedure (Identification) Act, 2022 enables the police and certain other persons to collect identity-related information about certain persons.  It provides that the manner of collection of such information may be specified by the central government.  Unless the manner is prescribed, such collection cannot take place.

That said, some other rule-making powers may be enabling in nature and subject to discretion by the concerned Ministry.  In 2016, Rajya Sabha Committee on Subordinate Legislation examined the status of Rules and Regulations to be framed under the Energy Conservation Act, 2001.  It observed that the Ministry of Power had held that two Rules and three Regulations under this Act were not necessary.   The Ministry of Law and Justice had opined that those deemed not necessary were enabling provisions meant for unforeseen circumstances.  The Rajya Sabha Committee (2016) had recommended that where the Ministry does not feel the need for framing subordinate legislation, the Minister should table a statement in Parliament, stating reasons for such a conclusion.

Some key issues related to subordinate legislation

The Legislature delegates the power to specify details for the implementation of a law to the Executive through powers for framing subordinate legislation.  Hence, it is important to ensure these are well-scrutinised so that they are within the limits envisaged in the law.

  • Capacity of Committees on Subordinate Legislation:  Parliamentary Committees on Subordinate Legislation have the responsibility to examine Rules in detail.  In past, they have examined some key rules, regulations, and notifications regarding e-commerceliability of internet-based services, and demonetisation.  However, usually, they are able to examine only a fraction of subordinate legislation in detail.  For more details, please see the PRS discussion paper here.
  • Uniformity of standards:  Countries such as UKUSAAustralia, and Canada have overarching legislation for regulating the framing of subordinate legislation.  These laws provide for the manner of public consultation, timelines, drafting standards, and a common register.  India does not have any similar law.  In India, the detail whether public consultation for subordinate legislation is required or not, is specified in respective Acts.  The General Clauses Act, 1897 also governs certain aspects of the framing of subordinate legislation.  In addition, the Pre-Legislative Consultation Policy, 2014 guides the pre-legislative consultation on subordinate legislation.