Recently, the Cabinet Committee on Economic Affairs approved an increase in the Minimum Support Prices (MSPs) for Kharif crops for the 2018-19 marketing season.  Subsequently, the Commission for Agricultural Costs and Prices (CACP) released its price policy report for Kharif crops for the marketing season 2018-19.

The central government notifies MSPs based on the recommendations of the CACP.  These recommendations are made separately for the Kharif marketing season (KMS) and the Rabi marketing season (RMS).  Post harvesting, the government procures crops from farmers at the MSP notified for that season, in order to ensure remunerative prices to farmers for their produce.

In this blog post, we look at how MSPs are determined, changes brought in them over time, and their effectiveness for farmers across different states.

How are Minimum Support Prices determined?

The CACP considers various factors such as the cost of cultivation and production, productivity of crops, and market prices for the determination of MSPs.  The National Commission on Farmers(Chair: Prof. M. S. Swaminathan) in 2006 had recommended that MSPs must be at least 50% more than the cost of production.  In this year’s budget speech, the Finance Minister said that MSPs would be fixed at least at 50% more than the cost of production.

The CACP calculates cost of production at three levels: (i) A2, which includes cost of inputs such as seeds, fertilizer, labour; (ii) A2+FL, which includes the implied cost of family labour (FL); and (iii) C2, which includes the implied rent on land and interest on capital assets over and above A2+FL.

Table 1 shows the cost of production as calculated by the CACP and the approved MSPs for KMS 2018-19.  For paddy (common), the MSP was increased from Rs 1,550/quintal in 2017-18 to Rs 1,750/quintal in 2018-19.  This price would give a farmer a profit of 50.1% on the cost of production A2+FL.  However, the profit calculated on the cost of production C2 would be 12.2%.  It has been argued that the cost of production should be taken as C2 for calculating MSPs.  In such a scenario, this would have increased the MSP to Rs 2,340/quintal, much above the current MSP of Rs 1,750/quintal.

Figure 1

Which are the major crops that are procured at MSPs?

Every year, MSPs are announced for 23 crops.  However, public procurement is limited to a few crops such as paddy, wheat and, to a limited extent, pulses as shown in Figure 1.

Figure 2

The procurement is also limited to a few states.  Three states which produce 49% of the national wheat output account for 93% of procurement.  For paddy, six states with 40% production share have 77% share of the procurement.  As a result, in these states, farmers focus on cultivating these crops over other crops such as pulses, oilseeds, and coarse grains.

Due to limitations on the procurement side (both crop-wise and state-wise), all farmers do not receive benefits of increase in MSPs.  The CACP has noted in its 2018-19 price policy report that the inability of farmers to sell at MSPs is one of the key areas of concern.  Farmers who are unable to sell their produce at MSPs have to sell it at market prices, which may be much lower than the MSPs.

How have MSPs for major crops changed over time?

Higher procurement of paddy and wheat, as compared to other crops at MSPs tilts the production cycle towards these crops.  In order to balance this and encourage the production of pulses, there is a larger proportional increase in the MSPs of pulses over the years as seen in Figure 2.  In addition to this, it is also used as a measure to encourage farmers to shift from water-intensive crops such as paddy and wheat to pulses, which relatively require less water for irrigation.

Figure 3

What is the effectiveness of MSPs across states?

The MSP fixed for each crop is uniform for the entire country.  However, the production cost of crops vary across states.  Figure 3 highlights the MSP of paddy and the variation in its cost of production across states in 2018-19.

Figure 4

For example, production cost for paddy at the A2+FL level is Rs 702/quintal in Punjab and Rs 2,102/quintal in Maharashtra.  Due to this differentiation, while the MSP of Rs 1,750/quintal of paddy will result in a profit of 149% to a farmer in Punjab, it will result in a loss of 17% to a farmer in Maharashtra.  Similarly, at the C2 level, the production cost for paddy is Rs 1,174/quintal in Punjab and Rs 2,481/quintal in Maharashtra.  In this scenario, a farmer in Punjab may get 49% return, while his counterpart in Maharashtra may make a loss of 29%.

Figure 5

Figure 4 highlights the MSP of wheat and the variation in its cost of production across states in 2017-18. In the case of wheat, the cost of production in Maharashtra and West Bengal is much more than the cost in rest of the states.  At the A2+FL level, the cost of production in West Bengal is Rs 1,777/quintal.  This is significantly higher than in states like Haryana and Punjab, where the cost is Rs 736/quintal and Rs 642/quintal, respectively.  In this case, while a wheat growing farmer suffers a loss of 2% in West Bengal, a farmer in Haryana makes a profit of 136%.  The return in Punjab is even higher at 1.5 times or more the cost of production.

Recently, the central government launched the Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya).[i],[ii]  The scheme seeks to ensure universal household electrification (in both rural and urban areas) by providing last mile connectivity.  The scheme is expected to cover three crore households.  Note that currently about four crore households are un-electrified.  A rural electrification scheme has also been under implementation since 2005.  In light of this, we discuss the current situation of, and key issues related to rural electrification in the country.

Regulatory and policy framework

Under the Electricity Act, 2003, the central and state governments have the joint responsibility of providing electricity to rural areas.  The 2003 Act also mandates that the central government should, in consultation with the state governments, provide for a national policy on (i) stand-alone power systems for rural areas (systems that are not connected to the electricity grid), and (ii) electrification and local distribution in rural areas.  Consequently, the Rural Electrification Policy was notified in August 2006.[iii]

The Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), launched in 2005, was the first scheme on rural electrification.  In December 2014, Ministry of Power launched the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), which subsumed the RGGVY.[iv]  Components of DDUGJY include: (i) separation of agricultural and non-agricultural electricity feeders to improve supply for consumers in rural areas, (ii) improving sub-transmission and distribution infrastructure in rural areas, and (iii) rural electrification by carrying forward targets specified under the RGGVY.

The total financial outlay for DDUGJY over the implementation period (until 2021-22) is Rs 82,300 crore which includes budgetary support of Rs 68,900 crore.  The central government provides 60% of the project cost as grant, the state power distribution companies (discoms) raise 10% of the funds, and 30% is borrowed from financial institutions and banks.

Status of rural electrification

As of August 2017, about 1% of the villages in India remain un-electrified (3,146 villages).  However, with regard to households, around 23% (4.1 crore households) are yet to be electrified.  Table 1 at the end of this post shows the status of rural electrification across all states.

Issues with rural electrification

Definition of an electrified village

An electrified village is defined as one that has the following: (i) provision of basic infrastructure such as distribution transformers and lines in the inhabited locality, (ii) provision of electricity in public places like schools, panchayat office, health centers, dispensaries, and community centers, and (iii) at least 10% of the total number of households in the village are electrified.[iv]

Therefore, a village is considered to be electrified if 10% of the total number of households in the village have been electrified.  This is apart from the basic infrastructure and electrification of certain public centers in the village.  The Standing Committee on Energy (2013) had observed that according to this definition, a village would be called electrified even if up to 90% of households in it do not have an electricity connection.[v]  It also noted that the infrastructure being provided under the scheme is highly inadequate, unreliable and unsustainable.  The Committee recommended that the actual electrification requirement of villages must be assessed, and it should be ensured that the state discoms provide electricity to the remaining households in the village.

Supply of electricity

The Standing Committee had also noted that while the rural electrification scheme looks at creating infrastructure, the actual supply of electricity to households rests with the state discoms.[v]  These discoms are already facing huge financial losses and hence are unable to supply electricity to the villages.  Discoms continue to supply subsidised power to agricultural and residential consumers, resulting in revenue losses.  Further, the average technical and commercial losses (theft and pilferage of electricity) (AT&C losses) are at around 25%.  While the Ujjwal Discom Assurance Yojana (UDAY) has eased off some of the financial losses of the discoms, it remains to be seen whether discoms are able to reduce the cost-tariff gap and AT&C losses in the future.

It has been recommended that generation capacity should be augmented so that states can meet the additional demand under the rural electrification schemes. Further, the assistance to financially weaker states should be increased so that they can better implement the scheme.[v]

Electricity to below poverty line (BPL) households

Under the rural electrification scheme, the cost for providing free electricity connection per BPL household is Rs 3,000.  It has been observed that this cost per household may be inadequate.[v]  Due to the low cost, the quantity and the quality of work has been getting compromised leading to poor implementation of the scheme.  It has been recommended that the Ministry should revisit the cost provided under the scheme.[v]

The new electrification scheme: Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya)

The new scheme, Saubhagya, seeks to ensure universal household electrification, that is, in both rural and urban areas.  Under Saubhagya, beneficiaries will be identified using the Socio Economic and Caste Census (SECC) 2011 data.  The identified poor households will get free electricity connections.  Other households not covered under the SECC, will be provided electricity connections at a cost of Rs 500.  This amount will be collected by the electricity distribution companies in 10 instalments.

The total outlay of the scheme will be Rs 16,320 crore, of which the central government will provide Rs 12,320 crore.  The outlay for the rural households will be Rs 14,025 crore, of which the centre will provide Rs 10,588 crore.  For urban households the outlay will be Rs 2,295 crore of which the centre will provide Rs. 1,733 crore.

The state discoms will execute the electrification works through contractors or other suitable agencies.  Information technology (mobile apps, web portals) will be used to organise camps in villages to identify beneficiaries.  In order to accelerate the process, applications for electricity connections will be completed on the spot.

So far the focus of electrification schemes has been on rural areas, where typically last mile connectivity has been difficult to provide.  Saubhagya extends the ambit of electrification projects to urban areas as well.  While DDUGJY has focused on the village as the principal unit to measure electrification, the new scheme shifts the targets to household electrification.  While the target for ensuring electricity connection in each household will be a significant step towards ensuring 24×7 power, the question of continuous and quality supply to these households will still rest on the ability of the discoms to provide electricity.  Further, while the scheme provides for free connections, the ability of these households to pay for the electricity they consume may be a concern.

Table 1: Status of rural electrification across states (as of August 2017)

Fig 1 edit

* all villages in Telangana were declared electrified before the bifurcation of the state.
Sources:  Ministry of Power; PRS.

 

[i] “PM launches Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 25, 2017.

[ii] “FAQs on Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 27, 2017.

[iii].  Rural Electrification Policy, Ministry of Power, August 23, 2006, http://powermin.nic.in/sites/default/files/uploads/RE%20Policy_1.pdf.

[iv].  “Office memorandum: Deendayal Upadhyaya Gram Jyoti Yojana”, Ministry of Power, December 3, 2014, http://powermin.nic.in/rural_electrification/pdf/Deendayal_Upadhyaya_Gram_Jyoti_Yojana.pdf.

[v].  “41st Report: Implementation of Rajiv Gandhi Grameen Vidyutikaran Yojana”, Standing Committee on Energy, December 13, 2013, http://164.100.47.134/lsscommittee/Energy/15_Energy_41.pdf.