This week, an in-house inquiry committee was constituted to consider a complaint against the current Chief Justice of India.  Over the years, three mechanisms have evolved to investigate cases of misconduct, including cases of sexual harassment, misbehaviour or incapacity against judges.  In this blog, we summarise the procedure for investigating such charges against judges of the Supreme Court.  

  • In-house procedure (1999): The Supreme Court has an in-house process to deal with allegations against a judge relating to the discharge of his judicial function, or with regard to his conduct or behaviour outside court.   
  • Sexual harassment guidelines: In 2013, Parliament passed the Sexual Harassment of Women at Workplace (Prevention, Prohibition and Redressal) Act, 2013.  Subsequently, the Supreme Court framed regulations for protection of women against sexual harassment in the Supreme Court. Under the regulations, the CJI is required to constitute a Gender Sensitisation and Internal Complaints Committee (GSICC).  The GSICC will include 7-13 members including: (i) one or two judges of the Supreme Court, and (ii) up to two outside members (having experience in social justice, women empowerment, gender justice, among others) to be nominated by the CJI.  The Regulations require the majority of the members of GSICC to be women.  As of 2018, the GSICC has received 13 complaints, out of which 10 have been disposed of. 
  • Removal for proven misbehaviour or incapacity: Charges of misconduct may also be investigated in the context of proceedings for removal of a judge.  Article 124(4) of the Constitution of India provides that a judge can be removed only by Parliament on the basis of a motion in either the Lok Sabha or Rajya Sabha.  The procedure for removal of judges is elaborated in the Judges Inquiry Act, 1968.  Till date, no judge of the higher judiciary has been impeached under this process. 

Table 1: Process for investigation of charges against a Supreme Court judge

 

In-house Procedure of Supreme Court

2013 SC Sexual Harassment Regulation

Removal Proceedings

Who may file a complaint

  • Complaint of misconduct may be filed by any person.
  • Written complaint of sexual harassment by a woman.
  • Signed notice by at least 100 members of the Lok Sabha, or 50 members of the Rajya Sabha on charges of misbehaviour or incapacity by a judge. 

Persons to whom complaint must be filed

  • CJI or President of India
  • GSICC
  • Presiding Officer of the relevant House of Parliament

Preliminary Inquiry

  • The CJI is required to determine whether the complaint is either frivolous or serious. If the complaint is frivolous or relates to a pending case, no further action will be taken.
  • If the CJI finds that the complaint involves serious misconduct or impropriety, he will seek the response of the concerned Judge. 
  • Based on the response and supporting materials, if the CJI finds that the complaint needs a deeper probe, he will constitute an inquiry committee. 
  • If the GSICC is satisfied that the complaint is genuine, it will constitute a three-member Internal Sub-Committee to conduct an inquiry into the complaint. 
  • If the notice is in order, the Presiding Officer will constitute a three-member committee to investigate the complaint.

Composition of Inquiry Committee

  • The Committee will comprise three judges including a Judge of the Supreme Court and two Chief Justices of other High Courts.
  • The Committee will comprise members of the GSICC or persons nominated by the GSICC, with majority members being a woman and an outside member.
  • The committee will comprise a Supreme Court judge, Chief Justice of a High Court, and a distinguished jurist. 

Time limit for submission of inquiry report

  • No specific time limit provided.
  • To be completed within 90 days of the constitution of the Internal Sub-Committee, and forwarded to the GSICC within 10 days of completion. 
  • To be submitted to the presiding officer within 90 days.

Findings of the Committee

  • The Committee may report to the CJI that:

​1.  there is no substance in the allegation made, or,

2.  there is substance in the allegations but the misconduct is not of such serious nature as to warrant removal, or,

3.  the misconduct is serious enough to initiate removal proceedings against the judge. 

  • If the committee concludes that the allegation has been proved, it will submit its report to the GSICC to pass appropriate orders within 45 days.
  • If more than two thirds of the GSICC members differ from the conclusion of the Committee, it will, after hearing the complainant and the accused, record its reasons for differing and pass orders.
  • After concluding its investigation, the Committee will submit its report to the presiding officer, who will lay the report before the relevant House.

 

Action taken upon submission of report

  • If the finding is under category (2) above, the CJI may call and advise the Judge accordingly and direct that the report be placed on record.
  • If the finding is under category (3) above, the CJI may ask the judge to resign or seek voluntary retirement.  If the judge refuses to resign, the CJI may decide to not allocate any judicial work to the judge concerned. 
  •  Further, the CJI may inform the President of India and the Prime Minister of his reasons for the action taken and forward a copy of the inquiry report to them.
  • The GSICC has the power to: (i) to pass an order of admonition (reprimand), which may also be published in the court precinct, or (ii) pass an order to prohibit the accused from harassing or communicating with the complainant, or (iii) pass any other order to end the sexual harassment faced by the complainant.
  • GSICC may also recommend to the CJI to pass orders against the accused, including: (i) prohibiting entry of the accused into the Supreme Court for up to a year, or (ii) filing a criminal complaint before the concerned disciplinary authority governing the accused.
  • If the report records a finding of misbehaviour or incapacity, the motion for removal will be taken up for consideration and debated. 
  • The motion is required to be adopted by each House by a majority of the total membership of that House and a majority of at least two-thirds of the members of that House present and voting.
  • Once the motion is adopted in both Houses, it is sent to the President, who will issue an order for the removal of the judge.

Process for Appeals

  • No specific provision.
  • Any aggrieved person may make a representation to the CJI to set aside/modify the orders passed by the GSICC.  The CJI also has the power to issue any other orders in order to secure justice to the victim.
  • No specific provision.

Sources: Report of the Committee on In-House Procedure, December 1999, Supreme Court of India; Gender Sensitisation and Sexual Harassment of Women at the Supreme Court of India (Prevention, Prohibition and Redressal) Regulations, 2013; Article 124(4), Constitution of India; Judges Inquiry Act, 1968 read with the Judges Inquiry Rules, 1969; PRS.

On March 14, 2022 Rajya Sabha discussed the working of the Ministry of Development of North Eastern Region (DoNER).  During the discussion, several issues around budgetary allocation, implementation of schemes and connectivity with the North Eastern Region were discussed.  The Ministry of DoNER is responsible for matters relating to the planning, execution and monitoring of development schemes and projects in the North Eastern Region.  In this blog post, we analyse the 2022-23 budgetary allocations for the Ministry and discuss related issues.  

A new scheme named PM-DevINE announced to boost infrastructure and social development

In 2022-23, the Ministry has seen a 5% increase in allocation from the revised estimates of 2021-22.  The Ministry has been allocated Rs 2,800 crore which will be used for various development schemes, such as the North East Special Infrastructure Development Scheme and North East Road Sector Development Scheme.  A scheme-wise break-up of the budget allocation for the Ministry is given below in Table 1.  

One of the key highlights of the Finance Minister’s Budget Speech was the announcement of a new scheme named the Prime Minister’s Development Initiative for North East (PM-DevINE).  It will be implemented through the North East Council (nodal agency for the economic and social development of the North Eastern Region).  PM-DevINE will fund infrastructure and social development projects in areas such as road connectivity, health, and agriculture.  The scheme will not replace or subsume existing central sector or centrally sponsored schemes.  The Scheme will be given an initial allocation of Rs 1,500 crore.

Table 1: Break-up of allocation to the Ministry of DoNER (in Rs crore)

Major Heads

2020-21 Actuals

2021-22 BE

2021-22 RE

2022-23 BE

% change from 2021-22 RE to 2022-23 BE

North East Special Infrastructure Development Scheme

446

675

674

1,419

111%

Schemes of North East Council

567

585

585

702

20%

North East Road Sector Development Scheme

416

696

674

496

-26%

Central pool of resources for North East and Sikkim

342

581

581

-

-

Others

270

322

344

241

-30%

Total

1,854

2,658

2,658

2,800

5%

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

 

Note: BE – Budget Estimate; RE – Revised Estimate; Schemes for North East Council includes Special Development Projects.

Sources: Demand No. 23 of Union Budget Documents 2022-23; PRS. 

Allocation towards capital outlay less than demand

The Standing Committee on Home Affairs (2022) noted that the amount allocated at the budget stage in 2022-23 (Rs 660 crore) was 17% less than the demand by the Ministry (Rs 794 crore).  Capital expenditure includes capital outlay which leads to the creation of assets such as schools, hospitals, and roads and bridges.  The Committee observed that this may severely affect the implementation of several projects and schemes that require capital outlay.  It recommended the Ministry to take up this matter with the Finance Ministry and demand additional assistance at the revised stage of the 2022-23 financial year.

Underutilisation of funds over the years

Since 2011-12 (barring 2016-17), the Ministry has not been able to utilise the funds allocated to it at the budgeted stage (See Figure 1).  For instance, in 2020-21, fund utilisation in case of the North East Road Sector Development Scheme was 52%, whereas only 34% of funds were utilised under the North East Special Infrastructure Development Scheme (for infrastructure projects relating to water supply, power, connectivity, social infrastructure).  Key reasons for underspending highlighted by the Ministry include late receipt of project proposals and non-receipt of utilisation certificates from state governments.

Figure 1: Underutilisation of funds by the Ministry since 2011-12

image
 Note: Revised Estimate has been used as the Actual Expenditure for 2021-22.
 Sources: Union Budget Documents (2011-12 to 2022-23); PRS
.

Delay in project completion

The Ministry implements several schemes for infrastructural projects such as roads and bridges.  The progress of the certain schemes has been inadequate.   The Standing Committee (2022) observed that the physical progress of many road sector projects under the North East Road Sector Development Scheme is either at zero or in single digit percent in spite of release of the amount for the project.  Similarly, projects under the Karbi Anglong Autonomous Territorial Council (autonomous district council in Assam) and Social and Infrastructure Development Fund (construction of roads, bridges, and construction of schools and water supply projects in the North Eastern Region) have seen inadequate progress.

Need to address declining forest cover

The Standing Committee (2021) has also recommended the Ministry of DoNER to work towards preserving forest cover.  The Committee took note of the declining forest cover in the North East India.  As per the India State of Forest Report (2021), states showing major loss of forest cover from 2019 to 2021 are: (i) Arunachal Pradesh (loss of 257 sq km of forest cover), (ii) Manipur (249 sq km), (iii) Nagaland (235 sq km), (iv) Mizoram (186 sq km), and (v) Meghalaya (73 sq km).  The loss of forest cover may be attributed to shifting cultivation, cutting down of trees, natural calamities, anthropogenic (environmental pollution) pressure, and developmental activities.  The Committee recommended that various measures to protect the forest and environment must be given priority and should implemented within the stipulated timeline.  It also suggested the Ministry to: (i) carry out regular plantation drives to increase forest cover/density, and (ii) accord priority towards the ultimate goal of preserving and protecting the forests under various centrally sponsored initiatives.

Key issues raised by Members during discussion in Rajya Sabha

The discussion on the working of the Ministry of DoNER took place in Rajya Sabha on March 14, 2022.  One of the issues highlighted by members was about the Ministry not having its own line Department.  This leads to the Ministry being dependent on the administrative strength of the states for implementation of projects.  Another issue highlighted by several members was the lack of connectivity of the region through railways and road networks which hampers the economic growth of region.  The DoNER Minister in his response to the House assured the members that the central government is making continuous efforts towards improving connectivity to the North East region through roads, railways, waterways, and telecommunication.         

Allocation by Union Ministries to the North East 

Union Ministries allocate 10% of their budget allocation for the North East (See Figure 2 for fund allocation and utilisation).  The Ministry of DoNER is the nodal Ministry that monitors and keeps track of the allocation done by various Ministries.  In 2022-23, Rs 76,040 crore has been allocated by all the Ministries for the North Eastern region.  The allocation has increased by 11% from the revised estimate of 2021-22 (Rs 68,440 crore).   In 2019-20 and 2021-21 the actual expenditure towards North Eastern areas was lower than budget estimates by 18% and 19% respectively.  

Figure 2: Budgetary allocation by all Union Ministries for the North East (amount in Rs crore)

image   

Source: Report No. 239: Demand for Grants (2022-23) of Ministry of Development of North Eastern Region, Standing Committee on Home Affairs; PRS.