In an Indian express editorial, Mandira Kala discusses the Bills, addressing corruption and good governance, pending in Parliament.  She discusses what their fate may be given that the Monsoon session is widely being viewed as a make or break session  for the government to get its legislative agenda through Parliament. The monsoon session of Parliament started on a stormy note last week. Question hour was disrupted on most days and only one government bill was passed. There are 11 days left in the session and more than 40 bills pending for parliamentary approval. With the 15th Lok Sabha drawing to an end, this session is being viewed as a "make or break" session for the government to get its legislative agenda through Parliament. Since 2010, there has been much debate in Parliament on corruption and an important part of the government's legislative agenda was the introduction of nine bills in the Lok Sabha to address corruption and improve governance through effective delivery of public services. Three of these bills have been passed by the Lok Sabha and are currently pending before the Rajya Sabha. These include legislation to address corruption in public office, enforce standards and accountability in the judiciary, and protect whistleblowers. The government has proposed amendments to each of these bills that the Rajya Sabha will have to consider and pass. If the Rajya Sabha passes these bills with amendments, they will be sent back to the Lok Sabha for approval. It is difficult to assess in what timeframe these bills will become law, given that both Houses need to agree on the amendments. The Lokpal and Lokayuktas Bill creates a process for receiving and investigating corruption complaints against public officials, including the Prime Minister, Ministers and Members of Parliament, and prosecuting these in a timebound manner. The government amendments include allowing states the flexibility to determine their respective Lokayuktas and giving the Lokpal power of superintendence over the CBI, if the case has been referred by him. A mechanism to protect whistleblowers and create a process for receiving and investigating complaints of corruption or wilful misuse of discretion against a public servant are proposed under the Whistleblowers' Protection Bill, 2010. The amendments proposed by the government prohibit whistleblowing if the disclosure of information affects the sovereignty of the country and its strategic, scientific and economic interest. The Judicial Standards and Accountability Bill requires judges to declare their assets, lays down judicial standards and establishes processes for the removal of judges of the Supreme Court and high courts. The bill is not listed in the government's legislative agenda for the monsoon session and media reports suggest that the government intends to make amendments to it. In the arena of strengthening governance and effective delivery of public services, there are three bills currently pending in Parliament. The Citizens' Charter Bill confers the right to timebound delivery of goods and services on every citizen and creates a mechanism for redressing complaints on such matters. The Electronic Delivery of Services Bill mandates that Central and state governments shall deliver public services electronically no later than eight years from the enactment of the law. The parliamentary standing committee had highlighted that the Citizens' Charter Bill and Electronic Delivery of Services Bill have an inherent overlap, which the government would have to resolve. While the former is listed for passing in this session, the government plans to withdraw the latter and replace it with a new bill. This new bill is not part of the list that is up for consideration and passing this session. To create a reliable method of identifying individuals to facilitate their access to benefits and services the National Identification Authority of India Bill was introduced in Parliament to provide unique identification numbers ("aadhaar") to residents of India. This bill has not been listed for parliamentary approval during this session. Two other pending bills do not find place in the government's legislative agenda for the session either. These include legislation that curbs the holding and transfer of benami property and regulates the procurement process in government departments to ensure transparency, accountability and probity. The Prevention of Bribery of Foreign Public Officials Bill, which imposes penalties on Indian companies and individuals who bribe officials of a foreign government or international agency, is listed for passing this session. Each of these nine bills were introduced in the Lok Sabha. If they are not passed by both Houses before the 15th Lok Sabha is dissolved in 2014, no matter where they are in the legislative process, the bills will lapse. This implies that the entire legislative process will have to start all over again, if and when there is political will to legislate on these issues in the 16th Lok Sabha. The challenges in getting legislation passed by Parliament are many, given that its overall productive time, especially time spent on legislation, is decreasing. Typically, Parliament spends about 25 per cent of its time debating legislation, but in the past few years this average has declined to 15 per cent. While the time lost by the House due to frequent adjournments is difficult to make up, parliamentarians will have to cautious about passing bills without the rigours of parliamentary debate. It is uncertain what the trajectory of the anti-corruption legislation in Parliament will be — enacted as law or resigned to a pool of lapsed legislation.

Recently, the central government launched the Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya).[i],[ii]  The scheme seeks to ensure universal household electrification (in both rural and urban areas) by providing last mile connectivity.  The scheme is expected to cover three crore households.  Note that currently about four crore households are un-electrified.  A rural electrification scheme has also been under implementation since 2005.  In light of this, we discuss the current situation of, and key issues related to rural electrification in the country.

Regulatory and policy framework

Under the Electricity Act, 2003, the central and state governments have the joint responsibility of providing electricity to rural areas.  The 2003 Act also mandates that the central government should, in consultation with the state governments, provide for a national policy on (i) stand-alone power systems for rural areas (systems that are not connected to the electricity grid), and (ii) electrification and local distribution in rural areas.  Consequently, the Rural Electrification Policy was notified in August 2006.[iii]

The Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), launched in 2005, was the first scheme on rural electrification.  In December 2014, Ministry of Power launched the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), which subsumed the RGGVY.[iv]  Components of DDUGJY include: (i) separation of agricultural and non-agricultural electricity feeders to improve supply for consumers in rural areas, (ii) improving sub-transmission and distribution infrastructure in rural areas, and (iii) rural electrification by carrying forward targets specified under the RGGVY.

The total financial outlay for DDUGJY over the implementation period (until 2021-22) is Rs 82,300 crore which includes budgetary support of Rs 68,900 crore.  The central government provides 60% of the project cost as grant, the state power distribution companies (discoms) raise 10% of the funds, and 30% is borrowed from financial institutions and banks.

Status of rural electrification

As of August 2017, about 1% of the villages in India remain un-electrified (3,146 villages).  However, with regard to households, around 23% (4.1 crore households) are yet to be electrified.  Table 1 at the end of this post shows the status of rural electrification across all states.

Issues with rural electrification

Definition of an electrified village

An electrified village is defined as one that has the following: (i) provision of basic infrastructure such as distribution transformers and lines in the inhabited locality, (ii) provision of electricity in public places like schools, panchayat office, health centers, dispensaries, and community centers, and (iii) at least 10% of the total number of households in the village are electrified.[iv]

Therefore, a village is considered to be electrified if 10% of the total number of households in the village have been electrified.  This is apart from the basic infrastructure and electrification of certain public centers in the village.  The Standing Committee on Energy (2013) had observed that according to this definition, a village would be called electrified even if up to 90% of households in it do not have an electricity connection.[v]  It also noted that the infrastructure being provided under the scheme is highly inadequate, unreliable and unsustainable.  The Committee recommended that the actual electrification requirement of villages must be assessed, and it should be ensured that the state discoms provide electricity to the remaining households in the village.

Supply of electricity

The Standing Committee had also noted that while the rural electrification scheme looks at creating infrastructure, the actual supply of electricity to households rests with the state discoms.[v]  These discoms are already facing huge financial losses and hence are unable to supply electricity to the villages.  Discoms continue to supply subsidised power to agricultural and residential consumers, resulting in revenue losses.  Further, the average technical and commercial losses (theft and pilferage of electricity) (AT&C losses) are at around 25%.  While the Ujjwal Discom Assurance Yojana (UDAY) has eased off some of the financial losses of the discoms, it remains to be seen whether discoms are able to reduce the cost-tariff gap and AT&C losses in the future.

It has been recommended that generation capacity should be augmented so that states can meet the additional demand under the rural electrification schemes. Further, the assistance to financially weaker states should be increased so that they can better implement the scheme.[v]

Electricity to below poverty line (BPL) households

Under the rural electrification scheme, the cost for providing free electricity connection per BPL household is Rs 3,000.  It has been observed that this cost per household may be inadequate.[v]  Due to the low cost, the quantity and the quality of work has been getting compromised leading to poor implementation of the scheme.  It has been recommended that the Ministry should revisit the cost provided under the scheme.[v]

The new electrification scheme: Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya)

The new scheme, Saubhagya, seeks to ensure universal household electrification, that is, in both rural and urban areas.  Under Saubhagya, beneficiaries will be identified using the Socio Economic and Caste Census (SECC) 2011 data.  The identified poor households will get free electricity connections.  Other households not covered under the SECC, will be provided electricity connections at a cost of Rs 500.  This amount will be collected by the electricity distribution companies in 10 instalments.

The total outlay of the scheme will be Rs 16,320 crore, of which the central government will provide Rs 12,320 crore.  The outlay for the rural households will be Rs 14,025 crore, of which the centre will provide Rs 10,588 crore.  For urban households the outlay will be Rs 2,295 crore of which the centre will provide Rs. 1,733 crore.

The state discoms will execute the electrification works through contractors or other suitable agencies.  Information technology (mobile apps, web portals) will be used to organise camps in villages to identify beneficiaries.  In order to accelerate the process, applications for electricity connections will be completed on the spot.

So far the focus of electrification schemes has been on rural areas, where typically last mile connectivity has been difficult to provide.  Saubhagya extends the ambit of electrification projects to urban areas as well.  While DDUGJY has focused on the village as the principal unit to measure electrification, the new scheme shifts the targets to household electrification.  While the target for ensuring electricity connection in each household will be a significant step towards ensuring 24×7 power, the question of continuous and quality supply to these households will still rest on the ability of the discoms to provide electricity.  Further, while the scheme provides for free connections, the ability of these households to pay for the electricity they consume may be a concern.

Table 1: Status of rural electrification across states (as of August 2017)

Fig 1 edit

* all villages in Telangana were declared electrified before the bifurcation of the state.
Sources:  Ministry of Power; PRS.

 

[i] “PM launches Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 25, 2017.

[ii] “FAQs on Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 27, 2017.

[iii].  Rural Electrification Policy, Ministry of Power, August 23, 2006, http://powermin.nic.in/sites/default/files/uploads/RE%20Policy_1.pdf.

[iv].  “Office memorandum: Deendayal Upadhyaya Gram Jyoti Yojana”, Ministry of Power, December 3, 2014, http://powermin.nic.in/rural_electrification/pdf/Deendayal_Upadhyaya_Gram_Jyoti_Yojana.pdf.

[v].  “41st Report: Implementation of Rajiv Gandhi Grameen Vidyutikaran Yojana”, Standing Committee on Energy, December 13, 2013, http://164.100.47.134/lsscommittee/Energy/15_Energy_41.pdf.