According to a press release, the Ministry of Civil Aviation is considering abolishing the development fee being levied at the Delhi and Mumbai airports.  The Ministry has already asked the Kolkata and Chennai airports not to levy a development fee.  According to the Ministry, this is being done to make air travel more affordable.  Currently, development fee charged at the Delhi Airport ranges from Rs 200 to Rs 1300.  At the Mumbai airport, the fee ranges from Rs 100 to Rs 600. It is pertinent to note that though, the Ministry has proposed abolishing the development fee, the airport operators may still levy a user development fee.  In this blog we discuss some of the aspects of development fee and user development fee. What is a development fee and a user development fee? Development Fee (DF) is primarily intended to fund the establishment or upgradation of an airport.  It is intended to bridge the gap between the cost of the project and the finance available with the airport operator.  Currently only the Mumbai and Delhi Airports levy a DF. However, there are other types of tariffs, such as a user development fee (UDF), which may be levied by the airports. UDF is generally regarded as a revenue enhancing measure.  It is levied by the airport operators to meet operational expenditure Section 22 A of the Airports Authority Act, 1994 (amended in 2003) gives the Airport Authority of India (AAI) the power to levy and collect a development fee on embarking passengers.  The Act provides that the development fee can be utilised only for: (a) funding or financing the upgradation of the airport; (b) establishing a new airport in lieu of the airport at which is levied; and (c) investing in shares of a private airport in lieu of an existing airport . Unlike DF,  UDF is not levied and collected under the Airport Authority of India Act but under Rule 89 of the Aircraft Rules, 1937. Under the Aircraft Rules, UDF may be levied and collected by either the AAI or the private operator.   According to the Airport Economic Regulatory Authority, UDF is levied to ensure that the airport operators can get a fair return on their investments. What is the role of the Airport Economic Regulatory Authority? In 2008, the Airport Economic Regulatory Authority (AERA) was established to regulate aeronautical tariffs.  Among others, AERA’s functions include determining the amount of DF and UDF for major airports.  In case of non-major airports, the UDF shall be determined by the central government. What has been the role of the Supreme Court? In 2009, the central government permitted the Mumbai and Delhi Airports to levy a DF.  The rate of was prescribed by the central government and not by AERA.  In 2011, the Supreme Court held that this levy of DF was illegal.  The Court based its decision on two grounds. Firstly, the court held that the rate of DF has to be determined by the AERA and not the central government.  Secondly, the Court held that the power to levy the fee lies with the Airport Authority as the development fee can only be utilised for the performance of the purpose specified in the Act.  The court held that while the Airport Authority can utilise the development fee for any of the functions prescribed in the Act, it can assign the power to levy a development fee to a private operator only for funding or financing the upgradation or expansion of the airport. Can private operators collect a development fee and a user development fee? In 2003, the government amended the Airport Authority of India Act to allow the AAI with the prior permission of the central government to: (i) to lease the premises of airports to private entities to undertake some of the functions of the AAI; (ii) levy and collect a development fee on the embarking passengers at a rate that may be prescribed. Till 2011, the power to collect the development fee lay only with the Airport Authority.  However with the notification of the Airports Authority of India (Major Airports) Development Fees Rules, 2011, private operators have also been permitted to collect the development fee.  

On November 28, 2012, the Comptroller and Auditor General submitted its report on the implementation of the Jawaharlal Nehru National Urban Renewal Mission (JNNURM).  According to the report most of the projects initiated under JNNURM have not been completed.  For instance with respect to urban infrastructure projects, only 231 projects out of the 1298 sanctioned projects have been completed.  Similarly, with respect to housing projects, only 22 of the 1517 projects have been completed.  Some of the other key recommendations of the report are:

  •  Some of the reasons for the delay in completing the projects include: (i) delay in acquiring land; (ii) deficiency in preparation of projects; and (iii) non-identification of beneficiaries which increased the risk of ineligible beneficiaries getting the benefits.
  •  A total allocation of Rs 66,084 crore had been made by the Planning Commission.  However, against this total allocation, the central government had made an allocation of only Rs 37,070 out of which until March 30, 2011 only Rs 32,934 had been released.
  • There was a delay in releasing these funds to the states.  A large portion of the funds was released only in the last quarter and more particularly in March.
  • The JNNURM guidelines were deficient as they did not provide adequate guidance to the states on the method of parking the funds and utilization of interest.

The need and objectives of JNNURM According to the 2011 census India’s urban population has increased from 286 million in 2001 to 377 million in 2011 .  With the increase in urban population, there is a requirement to improve the urban infrastructure and improve the service delivery mechanisms.  With these specific objectives in mind, the central government launched the Jawaharlal Nehru National Urban Renewal Mission 2005-2006.  The aim of the Mission is to encourage reforms and fast track planned development of identified cities (such as cities with a population of more than 1 million as per the 2001 census).  JNNURM has two main components namely : (i) Urban Infrastructure and Governance  and (ii) Urban Infrastructure Development for Small and Medium Towns. The duration of JNNURM was from 2005-06 to 2011-12. However, as the projects have not been completed the Government has extended its duration until March 2014. Funds for JNNURM The funds for JNNURM are provided through the Additional Central Assistance.  This implies that the funds are provided as grants to the states directly from the centre.   In the 2012 Union Budget, the central government has allocated Rs 12,522 crore for JNNURM. This represents around 10 % of the total central assistance through the different schemes to states and union territories in 2012-13. As on June 30 2012, 554 projects at a total cost of Rs 62,253 crore have been sanctioned under the Urban Infrastructure and Governance sub-mission of JNNURM.   The table below shows the status of the sanctioned JNNURM  projects in the different states. State wise status of the projects under JNNURM                 (as on August 6, 2012)

Name of State Total Allocation (Rs Lakh) Number of sanctioned projects Completed Projects
Andhra Pradesh 2,11,845 52 18
Arunachal Pradesh 10,740 3 NA
Assam 27,320 2 NA
Bihar 59,241 8 NA
Chandigarh 27,087 3 NA
Chattisgarh 24,803 1 NA
Delhi 2,82,318 23 4
Goa 12,094 2 NA
Gujarat 2,57,881 72 40
Haryana 32,332 4 NA
Himachal Pradesh 13,066 5 NA
Jammu & Kashmir 48,836 5 NA
Jharkhand 94,120 5 NA
Karnataka 1,52,459 47 22
Kerala 67,476 11 NA
Madhya Pradesh 1,32,850 23 7
Maharashtra 5,50,555 80 21
Manipur 15,287 3 NA
Meghalaya 15,668 2 NA
Mizoram 14,822 4 NA
Nagaland 11,628 3 NA
Orissa 32,235 5 NA
Punjab 70,775 6 1
Puducherry 20,680 2 NA
Rajasthan 74,869 13 2
Sikkim 10,613 2 NA
Tamil Nadu 2,25,066 48 12
Tripura 14,018 2 NA
Uttar Pradesh 2,76,941 33 4
Uttarakhand 40,534 14 NA
West Bengal 3,21,840 69 15

Source: Jawaharlal Nehru National Urban Renewal Mission; PRS.

  • Gujarat at 55.55% has the highest number of completed projects, while Uttar Pradesh at 12.24% has the lowest number of completed projects.
  • Out of the larger states, Delhi and Maharashtra at 17% and 26% have a comparatively low rate of completed projects.
  • Maharashtra has the highest number of sanctioned projects, while the North Eastern states, Chattisgarh and Puducherry have the lowest number of sanctioned projects.