Recently, there have been reports of price crashes and distress sales in case of farm produce, such as tomatoesmangoes, and garlic.  In some cases, farmers have dumped their produce on roads.  Produce such as fruits and vegetables are perishable and therefore have a short shelf life.  Further, due to inadequate storage facilities and poor food processing infrastructure farmers have limited options but to sell the produce at prevailing market prices.  This can lead to distress sales or roadside discards (in some cases to avoid additional cost of transportation).

Food processing allows raw food to be stored, marketed, or preserved for consumption later.  For instance, raw agricultural produce such as fruits may be processed into juices, jams, and pickles.  Activities such as waxing (for preservation), packaging, labelling, or ripening of produce also form part of the food processing industry.

Between 2001-02 and 2016-17, production of food grains grew annually at 1.7% on average.  Production of horticulture crops surpassed food grains with an average growth rate of 4.8%.  While production has been increasing over the years, surplus produce tends to go waste at various stages such as procurement, storage, and processing due to lack of infrastructure such as cold storages and food processing units.

Source: Horticulture Statistics at a Glance 2017, Union Budget 2018-19; PRS.

Source: Horticulture Statistics at a Glance 2017, Union Budget 2018-19; PRS.

Losses high among perishables such as fruits and vegetables

Crop losses ranged between 7-16% among fruits and around 5% among cereals in 2015.  The highest losses were witnessed in case of guava, followed by mango, which are perishable fruits.  Perishables such as fruits and vegetables are more prone to losses as compared to cereals.  Such crop losses can occur during operations such as harvesting, thrashing, grading, drying, packaging, transportation, and storage depending upon the commodity.

It was estimated that the annual value of harvest and post-harvest losses of major agricultural products at the national level was Rs 92,651 crore in 2015.  The Standing Committee on Agriculture (2017) stated that such wastage can be reduced with adequate food processing facilities.

Sources: Annual Report 2016-17, Ministry of Food Processing Industries; PRS.

Sources: Annual Report 2016-17, Ministry of Food Processing Industries; PRS.

Inadequate food processing infrastructure

As previously discussed, perishables such as fruits and vegetables are more prone to damages as compared to cereals.  Due to inadequate processing facilities in close proximity, farmers may be unable to hold their produce for a long time.  Hence, they may be forced to sell their produce soon after harvest, irrespective of the prevailing market situations.  Expert committees have recommended that agri-logistics such as cold chain infrastructure and market linkages should be strengthened.

Cold chain infrastructure: Cold chain infrastructure includes processing units, cold storages, and refrigerated vans.  As of 2014, out of a required cold storage capacity of 35 million metric tonnes (MT), almost 90% (31.8 million MT) of the capacity was available (see Table 1).  However, cold storage needs to be coupled with logistical support to facilitate smooth transfer of harvested value from farms to distant locations.  This includes: (i) pack-houses for packaging and preparing fresh produce for long distance transport, (ii) refrigerated transport such as reefer vehicles, and (iii) ripening chambers to ripen raw produce before marketing.  For instance, bananas which are harvested raw may be ripened in these chambers before being marketed.

While there are sufficient cold storages, there are wide gaps in the availability of other associated infrastructure.  This implies that even though almost 90% (32 million tonnes) of cold storage capacity is available, only 15% of the required refrigerated transport exists.  Further, the shortfall in the availability of infrastructure necessary for safe handling of farm produce, like pack-houses and ripening chambers, is over 90%.

Table 1:  Gaps in cold chain infrastructure (2014)

Facility Required Available Gap % gap
Cold storage
(in million MT)

35.1

31.8 3.2

9.3%

Pack-houses

70,080

249 69,831

99.6%

Reefer vehicles

61,826

9,000 52,826

85.4%

Ripening chambers

9,131

812 8,319

91.1%

Source: Standing Committee on Agriculture 2018; PRS.

To minimise post-harvest losses, the Standing Committee (2017) recommended that a country-wide integrated cold chain infrastructure network at block and district levels should be created.  It further recommended that a Cold Chain Coordination and Monitoring Committee should be constituted at the district-level.  The Standing Committee also recommended that farmers need to be trained in value addition activities such as sorting, grading, and pre-cooling harvested produce through facilities such as freezers and ripening chambers.

Between 2008 and 2017, 238 cold chain projects were sanctioned under the Scheme for Integrated Cold Chain and Value Addition Infrastructure.  Grants worth Rs 1,775 crore were approved for these projects.  Of this amount, Rs 964 crore (54%) has been released as of January 2018.  Consequently, out of the total projects sanctioned, 114 (48%) are completed.  The remaining 124 projects are currently under implementation.

Transport Facilities:  Currently, majority of food grains and certain quantities of tea, potato, and onion are transported through railways.  The Committee on Doubling Farmers Income had recommended that railways needs to upgrade its logistics to facilitate the transport of fresh produce directly to export hubs.  This includes creation of adjoining facilities for loading and unloading, and distribution to road transport.

Mega Food Parks: The Mega Food Parks scheme was launched in 2008.  It seeks to facilitate setting up of food processing units.  These units are to be located at a central processing centre with infrastructure required for processing, packaging, quality control labs, and trade facilitation centres.

As of March 2018, out of the 42 projects approved, 10 were operational.  The Standing Committee on Agriculture noted certain reasons for delay in implementation of projects under the scheme.  These include: (i) difficulty in getting loans from banks for the project, (ii) delay in obtaining clearances from the state governments and agencies for roads, power, and water at the project site, (iii) lack of special incentives for setting up food processing units in Mega Food Parks, and (iv) unwillingness of the co-promoters in contributing their share of equity.

Further, the Standing Committee stated that as the scheme requires a minimum area of 50 acres, it does not to promote smaller or individual food processing and preservation units.  It recommended that smaller agro-processing clusters near production areas must be promoted.  The Committee on Doubling Farmers Income recommended establishment of processing and value addition units at strategic places.  This includes rural or production areas for pulses, millets, fruits, vegetables, dairy, fisheries, and poultry in public private-partnership mode.

The Insolvency and Bankruptcy Code, 2016 was enacted to provide a time-bound process to resolve insolvency among companies and individuals.  Insolvency is a situation where an individual or company is unable to repay their outstanding debt.  Last month, the government promulgated the Insolvency and Bankruptcy Code (Amendment) Ordinance, 2018 amending certain provisions of the Code.  The Insolvency and Bankruptcy Code (Second Amendment) Bill, 2018, which replaces this Ordinance, was introduced in Lok Sabha last week and is scheduled to be passed in the ongoing monsoon session of Parliament.  In light of this, we discuss some of the changes being proposed under the Bill and possible implications of such changes.

What was the need for amending the Code?

In November 2017, the Insolvency Law Committee was set up to review the Code, identify issues in its implementation, and suggest changes.  The Committee submitted its report in March 2018.  It made several recommendations, such as treating allottees under a real estate project as financial creditors, exempting micro, small and medium enterprises from certain provisions of the Code, reducing voting thresholds of the committee of creditors, among others.  Subsequently, the Insolvency and Bankruptcy Code (Amendment) Ordinance, 2018, was promulgated on June 6, 2018, incorporating these recommendations.

What amendments have been proposed regarding real estate allottees?

The Code defines a financial creditor as anyone who has extended any kind of loan or financial credit to the debtor.  The Bill clarifies that an allottee under a real estate project (a buyer of an under-construction residential or commercial property) will be considered as a financial creditor.  These allottees will be represented on the committee of creditors by an authorised representative who will vote on their behalf.

This committee is responsible for taking key decisions related to the resolution process, such as appointing the resolution professional, and approving the resolution plan to be submitted to the National Company Law Tribunal (NCLT).  It also implies that real estate allottees can initiate a corporate insolvency resolution process against the debtor.

Can the amount raised by real estate allottees be considered as financial debt?

The Insolvency Law Committee (2017) had noted that the amount paid by allottees under a real estate project is a means of raising finance for the project, and hence would classify as financial debt.  It had also noted that, in certain cases, allottees provide more money towards a real estate project than banks.  The Bill provides that the amount raised from allottees during the sale of a real estate project would have the commercial effect of a borrowing, and therefore be considered as a financial debt for the real estate company (or the debtor).

However, it may be argued that the money raised from allottees under a real estate project is an advance payment for a future asset (or the property allotted to them).  It is not an explicit loan given to the developer against receipt of interest, or similar consideration for the time value of money, and therefore may not qualify as financial debt.

Do the amendments affect the priority of real estate allottees in the waterfall under liquidation?

During the corporate insolvency resolution process, a committee of creditors (comprising of all financial creditors) may choose to: (i) resolve the debtor company, or (ii) liquidate (sell) the debtor’s assets to repay loans.  If no decision is made by the committee within the prescribed time period, the debtor’s assets are liquidated to repay the debt.  In case of liquidation, secured creditors are paid first after payment of the resolution fees and other resolution costs.  Secured creditors are those whose loans are backed by collateral (security).  This is followed by payment of employee wages, and then payment to all the unsecured creditors.

While the Bill classifies allottees as financial creditors, it does not specify whether they would be treated as secured or unsecured creditors.  Therefore, their position in the order of priority is not clear.

What amendments have been proposed regarding Micro, Small, and Medium Enterprises (MSMEs)?

Earlier this year, the Code was amended to prohibit certain persons from submitting a resolution plan.  These include: (i) wilful defaulters, (ii) promoters or management of the company if it has an outstanding non-performing asset (NPA) for over a year, and (iii) disqualified directors, among others.  Further, it barred the sale of property of a defaulter to such persons during liquidation.  One of the concerns raised was that in case of some MSMEs, the promoter may be the only person submitting a plan to revive the company.  In such cases, the defaulting firm will go into liquidation even if there could have been a viable resolution plan.

The Bill amends the criteria which prohibits certain persons from submitting a resolution plan.  For example, the Code prohibits a person from being a resolution applicant if his account has been identified as a NPA for more than a year.  The Bill provides that this criterion will not apply if such an applicant is a financial entity, and is not a related party to the debtor (with certain exceptions).  Further, if the NPA was acquired under a resolution plan under this Code, then this criterion will not apply for a period of three years (instead of one).  Secondly, the Code also bars a guarantor of a defaulter from being an applicant.  The Bill specifies that such a bar will apply if such guarantee has been invoked by the creditor and remains unpaid.

In addition to amending these criteria, the Bill also states that the ineligibility criteria for resolution applicants regarding NPAs and guarantors will not be applicable to persons applying for resolution of MSMEs.  The central government may, in public interest, modify or remove other provisions of the Code while applying them to MSMEs.

What are some of the other key changes being proposed?

The Bill also makes certain changes to the procedures under the Code.  Under the Code, all decisions of the committee of creditors have to be taken by a 75% majority of the financial creditors.  The Bill lowers this threshold to 51%.  For certain key decisions, such as appointment of a resolution professional, approving the resolution plan, and making structural changes to the company, the voting threshold has been reduced from 75% to 66%.

The Bill also provides for withdrawal of a resolution application, after the resolution process has been initiated with the NCLT.  Such withdrawal will have to be approved by a 90% vote of the committee of creditors.