Recently, there have been reports of price crashes and distress sales in case of farm produce, such as tomatoesmangoes, and garlic.  In some cases, farmers have dumped their produce on roads.  Produce such as fruits and vegetables are perishable and therefore have a short shelf life.  Further, due to inadequate storage facilities and poor food processing infrastructure farmers have limited options but to sell the produce at prevailing market prices.  This can lead to distress sales or roadside discards (in some cases to avoid additional cost of transportation).

Food processing allows raw food to be stored, marketed, or preserved for consumption later.  For instance, raw agricultural produce such as fruits may be processed into juices, jams, and pickles.  Activities such as waxing (for preservation), packaging, labelling, or ripening of produce also form part of the food processing industry.

Between 2001-02 and 2016-17, production of food grains grew annually at 1.7% on average.  Production of horticulture crops surpassed food grains with an average growth rate of 4.8%.  While production has been increasing over the years, surplus produce tends to go waste at various stages such as procurement, storage, and processing due to lack of infrastructure such as cold storages and food processing units.

Source: Horticulture Statistics at a Glance 2017, Union Budget 2018-19; PRS.

Source: Horticulture Statistics at a Glance 2017, Union Budget 2018-19; PRS.

Losses high among perishables such as fruits and vegetables

Crop losses ranged between 7-16% among fruits and around 5% among cereals in 2015.  The highest losses were witnessed in case of guava, followed by mango, which are perishable fruits.  Perishables such as fruits and vegetables are more prone to losses as compared to cereals.  Such crop losses can occur during operations such as harvesting, thrashing, grading, drying, packaging, transportation, and storage depending upon the commodity.

It was estimated that the annual value of harvest and post-harvest losses of major agricultural products at the national level was Rs 92,651 crore in 2015.  The Standing Committee on Agriculture (2017) stated that such wastage can be reduced with adequate food processing facilities.

Sources: Annual Report 2016-17, Ministry of Food Processing Industries; PRS.

Sources: Annual Report 2016-17, Ministry of Food Processing Industries; PRS.

Inadequate food processing infrastructure

As previously discussed, perishables such as fruits and vegetables are more prone to damages as compared to cereals.  Due to inadequate processing facilities in close proximity, farmers may be unable to hold their produce for a long time.  Hence, they may be forced to sell their produce soon after harvest, irrespective of the prevailing market situations.  Expert committees have recommended that agri-logistics such as cold chain infrastructure and market linkages should be strengthened.

Cold chain infrastructure: Cold chain infrastructure includes processing units, cold storages, and refrigerated vans.  As of 2014, out of a required cold storage capacity of 35 million metric tonnes (MT), almost 90% (31.8 million MT) of the capacity was available (see Table 1).  However, cold storage needs to be coupled with logistical support to facilitate smooth transfer of harvested value from farms to distant locations.  This includes: (i) pack-houses for packaging and preparing fresh produce for long distance transport, (ii) refrigerated transport such as reefer vehicles, and (iii) ripening chambers to ripen raw produce before marketing.  For instance, bananas which are harvested raw may be ripened in these chambers before being marketed.

While there are sufficient cold storages, there are wide gaps in the availability of other associated infrastructure.  This implies that even though almost 90% (32 million tonnes) of cold storage capacity is available, only 15% of the required refrigerated transport exists.  Further, the shortfall in the availability of infrastructure necessary for safe handling of farm produce, like pack-houses and ripening chambers, is over 90%.

Table 1:  Gaps in cold chain infrastructure (2014)

Facility Required Available Gap % gap
Cold storage
(in million MT)

35.1

31.8 3.2

9.3%

Pack-houses

70,080

249 69,831

99.6%

Reefer vehicles

61,826

9,000 52,826

85.4%

Ripening chambers

9,131

812 8,319

91.1%

Source: Standing Committee on Agriculture 2018; PRS.

To minimise post-harvest losses, the Standing Committee (2017) recommended that a country-wide integrated cold chain infrastructure network at block and district levels should be created.  It further recommended that a Cold Chain Coordination and Monitoring Committee should be constituted at the district-level.  The Standing Committee also recommended that farmers need to be trained in value addition activities such as sorting, grading, and pre-cooling harvested produce through facilities such as freezers and ripening chambers.

Between 2008 and 2017, 238 cold chain projects were sanctioned under the Scheme for Integrated Cold Chain and Value Addition Infrastructure.  Grants worth Rs 1,775 crore were approved for these projects.  Of this amount, Rs 964 crore (54%) has been released as of January 2018.  Consequently, out of the total projects sanctioned, 114 (48%) are completed.  The remaining 124 projects are currently under implementation.

Transport Facilities:  Currently, majority of food grains and certain quantities of tea, potato, and onion are transported through railways.  The Committee on Doubling Farmers Income had recommended that railways needs to upgrade its logistics to facilitate the transport of fresh produce directly to export hubs.  This includes creation of adjoining facilities for loading and unloading, and distribution to road transport.

Mega Food Parks: The Mega Food Parks scheme was launched in 2008.  It seeks to facilitate setting up of food processing units.  These units are to be located at a central processing centre with infrastructure required for processing, packaging, quality control labs, and trade facilitation centres.

As of March 2018, out of the 42 projects approved, 10 were operational.  The Standing Committee on Agriculture noted certain reasons for delay in implementation of projects under the scheme.  These include: (i) difficulty in getting loans from banks for the project, (ii) delay in obtaining clearances from the state governments and agencies for roads, power, and water at the project site, (iii) lack of special incentives for setting up food processing units in Mega Food Parks, and (iv) unwillingness of the co-promoters in contributing their share of equity.

Further, the Standing Committee stated that as the scheme requires a minimum area of 50 acres, it does not to promote smaller or individual food processing and preservation units.  It recommended that smaller agro-processing clusters near production areas must be promoted.  The Committee on Doubling Farmers Income recommended establishment of processing and value addition units at strategic places.  This includes rural or production areas for pulses, millets, fruits, vegetables, dairy, fisheries, and poultry in public private-partnership mode.

Elections to the 13th Legislative Assembly of Gujarat are scheduled to be held in two phases on the 13th and 17th of December.  The BJP has been the dominant majority party in the Assembly since 1995.  The 2002 elections saw the largest victory for the party, winning 127 seats. The Congress last held power in Gujarat in 1985.  In the Assembly elections held for the the seventh Assembly, the Congress had a clear majority of 149 seats.  In 1990, the Janata Dal emerged as the largest party with 70 seats.  The BJP registered major gains in 1990, improving their tally of 11 seats in 1985 to 67 seats.  The Congress came third with 33 seats. The electoral trends over the last 22 years may be viewed here. In the current Assembly, 117 of the 182 seats are held by the BJP.  It is useful to look at the work done by the 12th Gujarat Assembly during its term from 2008 to 2012.  Here we look at key metrics like the number of days the assembly was in session, members’ attendance, and legislative business. Performance of the Assembly During its five year term, the assembly sat for a total of 157 days – an average of 31 days each year.  In comparison, the Lok Sabha sat for an average of 66 days each year during the period 2008 to 2011.  In the same period the Kerala Assembly sat for an average of 50 days – highest among states - followed by Maharashtra (44).  However, the Gujarat Assembly sat for more number of days than the Haryana Assembly which sat for an average of 13 days and Rajasthan (24). The average attendance among Gujarat MLAs stood at 83% for the whole term, with two members registering 100% attendance. 87 Bills were passed by the Assembly since the beginning of its term in 2008 till September 2011.  Of these, 80 Bills i.e. over 90% of all Bills were passed on the same day as they were introduced.  None of the Bills were referred to any Committee.  In the Budget Session of 2011, 31 Bills were passed of which 21 were introduced and passed within three sitting days Amendments sought by the President and the Governor One of the significant laws passed by the 12th Assembly was the Gujarat Control of Terrorism and Organised Crime Bill, 2003 which was introduced and passed in July 2009.  However the Bill did not receive the Presidents Assent and was sent back to the Gujarat Assembly for amendments. In December 2009, the assembly passed the Gujarat Local Authorities Laws (Amendment) Bill 2009 which sought to make voting compulsory in elections to local self-government bodies like municipal corporations and Panchayats.  The Gujarat governor returned the Bill for reconsideration in 2010.  It was re-introduced in the house in September 2010 without changes. Another Bill that was returned by the Governor was the Gujarat Regularisation of Unauthorised Development Bill which sought to regularise unauthorised construction on payment of an Impact Fee.  The Bill was passed by the Assembly in March 2011.  The Governor returned the Bill with a suggestion to include a provision to bar the regularisation of unauthorised construction beyond a specified date.  The Bill was re-introduced and passed with amendments by the Assembly in September 2011.