Recently, there have been reports of price crashes and distress sales in case of farm produce, such as tomatoesmangoes, and garlic.  In some cases, farmers have dumped their produce on roads.  Produce such as fruits and vegetables are perishable and therefore have a short shelf life.  Further, due to inadequate storage facilities and poor food processing infrastructure farmers have limited options but to sell the produce at prevailing market prices.  This can lead to distress sales or roadside discards (in some cases to avoid additional cost of transportation).

Food processing allows raw food to be stored, marketed, or preserved for consumption later.  For instance, raw agricultural produce such as fruits may be processed into juices, jams, and pickles.  Activities such as waxing (for preservation), packaging, labelling, or ripening of produce also form part of the food processing industry.

Between 2001-02 and 2016-17, production of food grains grew annually at 1.7% on average.  Production of horticulture crops surpassed food grains with an average growth rate of 4.8%.  While production has been increasing over the years, surplus produce tends to go waste at various stages such as procurement, storage, and processing due to lack of infrastructure such as cold storages and food processing units.

Source: Horticulture Statistics at a Glance 2017, Union Budget 2018-19; PRS.

Source: Horticulture Statistics at a Glance 2017, Union Budget 2018-19; PRS.

Losses high among perishables such as fruits and vegetables

Crop losses ranged between 7-16% among fruits and around 5% among cereals in 2015.  The highest losses were witnessed in case of guava, followed by mango, which are perishable fruits.  Perishables such as fruits and vegetables are more prone to losses as compared to cereals.  Such crop losses can occur during operations such as harvesting, thrashing, grading, drying, packaging, transportation, and storage depending upon the commodity.

It was estimated that the annual value of harvest and post-harvest losses of major agricultural products at the national level was Rs 92,651 crore in 2015.  The Standing Committee on Agriculture (2017) stated that such wastage can be reduced with adequate food processing facilities.

Sources: Annual Report 2016-17, Ministry of Food Processing Industries; PRS.

Sources: Annual Report 2016-17, Ministry of Food Processing Industries; PRS.

Inadequate food processing infrastructure

As previously discussed, perishables such as fruits and vegetables are more prone to damages as compared to cereals.  Due to inadequate processing facilities in close proximity, farmers may be unable to hold their produce for a long time.  Hence, they may be forced to sell their produce soon after harvest, irrespective of the prevailing market situations.  Expert committees have recommended that agri-logistics such as cold chain infrastructure and market linkages should be strengthened.

Cold chain infrastructure: Cold chain infrastructure includes processing units, cold storages, and refrigerated vans.  As of 2014, out of a required cold storage capacity of 35 million metric tonnes (MT), almost 90% (31.8 million MT) of the capacity was available (see Table 1).  However, cold storage needs to be coupled with logistical support to facilitate smooth transfer of harvested value from farms to distant locations.  This includes: (i) pack-houses for packaging and preparing fresh produce for long distance transport, (ii) refrigerated transport such as reefer vehicles, and (iii) ripening chambers to ripen raw produce before marketing.  For instance, bananas which are harvested raw may be ripened in these chambers before being marketed.

While there are sufficient cold storages, there are wide gaps in the availability of other associated infrastructure.  This implies that even though almost 90% (32 million tonnes) of cold storage capacity is available, only 15% of the required refrigerated transport exists.  Further, the shortfall in the availability of infrastructure necessary for safe handling of farm produce, like pack-houses and ripening chambers, is over 90%.

Table 1:  Gaps in cold chain infrastructure (2014)

Facility Required Available Gap % gap
Cold storage
(in million MT)

35.1

31.8 3.2

9.3%

Pack-houses

70,080

249 69,831

99.6%

Reefer vehicles

61,826

9,000 52,826

85.4%

Ripening chambers

9,131

812 8,319

91.1%

Source: Standing Committee on Agriculture 2018; PRS.

To minimise post-harvest losses, the Standing Committee (2017) recommended that a country-wide integrated cold chain infrastructure network at block and district levels should be created.  It further recommended that a Cold Chain Coordination and Monitoring Committee should be constituted at the district-level.  The Standing Committee also recommended that farmers need to be trained in value addition activities such as sorting, grading, and pre-cooling harvested produce through facilities such as freezers and ripening chambers.

Between 2008 and 2017, 238 cold chain projects were sanctioned under the Scheme for Integrated Cold Chain and Value Addition Infrastructure.  Grants worth Rs 1,775 crore were approved for these projects.  Of this amount, Rs 964 crore (54%) has been released as of January 2018.  Consequently, out of the total projects sanctioned, 114 (48%) are completed.  The remaining 124 projects are currently under implementation.

Transport Facilities:  Currently, majority of food grains and certain quantities of tea, potato, and onion are transported through railways.  The Committee on Doubling Farmers Income had recommended that railways needs to upgrade its logistics to facilitate the transport of fresh produce directly to export hubs.  This includes creation of adjoining facilities for loading and unloading, and distribution to road transport.

Mega Food Parks: The Mega Food Parks scheme was launched in 2008.  It seeks to facilitate setting up of food processing units.  These units are to be located at a central processing centre with infrastructure required for processing, packaging, quality control labs, and trade facilitation centres.

As of March 2018, out of the 42 projects approved, 10 were operational.  The Standing Committee on Agriculture noted certain reasons for delay in implementation of projects under the scheme.  These include: (i) difficulty in getting loans from banks for the project, (ii) delay in obtaining clearances from the state governments and agencies for roads, power, and water at the project site, (iii) lack of special incentives for setting up food processing units in Mega Food Parks, and (iv) unwillingness of the co-promoters in contributing their share of equity.

Further, the Standing Committee stated that as the scheme requires a minimum area of 50 acres, it does not to promote smaller or individual food processing and preservation units.  It recommended that smaller agro-processing clusters near production areas must be promoted.  The Committee on Doubling Farmers Income recommended establishment of processing and value addition units at strategic places.  This includes rural or production areas for pulses, millets, fruits, vegetables, dairy, fisheries, and poultry in public private-partnership mode.

On November 28, 2012, the Comptroller and Auditor General submitted its report on the implementation of the Jawaharlal Nehru National Urban Renewal Mission (JNNURM).  According to the report most of the projects initiated under JNNURM have not been completed.  For instance with respect to urban infrastructure projects, only 231 projects out of the 1298 sanctioned projects have been completed.  Similarly, with respect to housing projects, only 22 of the 1517 projects have been completed.  Some of the other key recommendations of the report are:

  •  Some of the reasons for the delay in completing the projects include: (i) delay in acquiring land; (ii) deficiency in preparation of projects; and (iii) non-identification of beneficiaries which increased the risk of ineligible beneficiaries getting the benefits.
  •  A total allocation of Rs 66,084 crore had been made by the Planning Commission.  However, against this total allocation, the central government had made an allocation of only Rs 37,070 out of which until March 30, 2011 only Rs 32,934 had been released.
  • There was a delay in releasing these funds to the states.  A large portion of the funds was released only in the last quarter and more particularly in March.
  • The JNNURM guidelines were deficient as they did not provide adequate guidance to the states on the method of parking the funds and utilization of interest.

The need and objectives of JNNURM According to the 2011 census India’s urban population has increased from 286 million in 2001 to 377 million in 2011 .  With the increase in urban population, there is a requirement to improve the urban infrastructure and improve the service delivery mechanisms.  With these specific objectives in mind, the central government launched the Jawaharlal Nehru National Urban Renewal Mission 2005-2006.  The aim of the Mission is to encourage reforms and fast track planned development of identified cities (such as cities with a population of more than 1 million as per the 2001 census).  JNNURM has two main components namely : (i) Urban Infrastructure and Governance  and (ii) Urban Infrastructure Development for Small and Medium Towns. The duration of JNNURM was from 2005-06 to 2011-12. However, as the projects have not been completed the Government has extended its duration until March 2014. Funds for JNNURM The funds for JNNURM are provided through the Additional Central Assistance.  This implies that the funds are provided as grants to the states directly from the centre.   In the 2012 Union Budget, the central government has allocated Rs 12,522 crore for JNNURM. This represents around 10 % of the total central assistance through the different schemes to states and union territories in 2012-13. As on June 30 2012, 554 projects at a total cost of Rs 62,253 crore have been sanctioned under the Urban Infrastructure and Governance sub-mission of JNNURM.   The table below shows the status of the sanctioned JNNURM  projects in the different states. State wise status of the projects under JNNURM                 (as on August 6, 2012)

Name of State Total Allocation (Rs Lakh) Number of sanctioned projects Completed Projects
Andhra Pradesh 2,11,845 52 18
Arunachal Pradesh 10,740 3 NA
Assam 27,320 2 NA
Bihar 59,241 8 NA
Chandigarh 27,087 3 NA
Chattisgarh 24,803 1 NA
Delhi 2,82,318 23 4
Goa 12,094 2 NA
Gujarat 2,57,881 72 40
Haryana 32,332 4 NA
Himachal Pradesh 13,066 5 NA
Jammu & Kashmir 48,836 5 NA
Jharkhand 94,120 5 NA
Karnataka 1,52,459 47 22
Kerala 67,476 11 NA
Madhya Pradesh 1,32,850 23 7
Maharashtra 5,50,555 80 21
Manipur 15,287 3 NA
Meghalaya 15,668 2 NA
Mizoram 14,822 4 NA
Nagaland 11,628 3 NA
Orissa 32,235 5 NA
Punjab 70,775 6 1
Puducherry 20,680 2 NA
Rajasthan 74,869 13 2
Sikkim 10,613 2 NA
Tamil Nadu 2,25,066 48 12
Tripura 14,018 2 NA
Uttar Pradesh 2,76,941 33 4
Uttarakhand 40,534 14 NA
West Bengal 3,21,840 69 15

Source: Jawaharlal Nehru National Urban Renewal Mission; PRS.

  • Gujarat at 55.55% has the highest number of completed projects, while Uttar Pradesh at 12.24% has the lowest number of completed projects.
  • Out of the larger states, Delhi and Maharashtra at 17% and 26% have a comparatively low rate of completed projects.
  • Maharashtra has the highest number of sanctioned projects, while the North Eastern states, Chattisgarh and Puducherry have the lowest number of sanctioned projects.