Recently, there have been reports of price crashes and distress sales in case of farm produce, such as tomatoesmangoes, and garlic.  In some cases, farmers have dumped their produce on roads.  Produce such as fruits and vegetables are perishable and therefore have a short shelf life.  Further, due to inadequate storage facilities and poor food processing infrastructure farmers have limited options but to sell the produce at prevailing market prices.  This can lead to distress sales or roadside discards (in some cases to avoid additional cost of transportation).

Food processing allows raw food to be stored, marketed, or preserved for consumption later.  For instance, raw agricultural produce such as fruits may be processed into juices, jams, and pickles.  Activities such as waxing (for preservation), packaging, labelling, or ripening of produce also form part of the food processing industry.

Between 2001-02 and 2016-17, production of food grains grew annually at 1.7% on average.  Production of horticulture crops surpassed food grains with an average growth rate of 4.8%.  While production has been increasing over the years, surplus produce tends to go waste at various stages such as procurement, storage, and processing due to lack of infrastructure such as cold storages and food processing units.

Source: Horticulture Statistics at a Glance 2017, Union Budget 2018-19; PRS.

Source: Horticulture Statistics at a Glance 2017, Union Budget 2018-19; PRS.

Losses high among perishables such as fruits and vegetables

Crop losses ranged between 7-16% among fruits and around 5% among cereals in 2015.  The highest losses were witnessed in case of guava, followed by mango, which are perishable fruits.  Perishables such as fruits and vegetables are more prone to losses as compared to cereals.  Such crop losses can occur during operations such as harvesting, thrashing, grading, drying, packaging, transportation, and storage depending upon the commodity.

It was estimated that the annual value of harvest and post-harvest losses of major agricultural products at the national level was Rs 92,651 crore in 2015.  The Standing Committee on Agriculture (2017) stated that such wastage can be reduced with adequate food processing facilities.

Sources: Annual Report 2016-17, Ministry of Food Processing Industries; PRS.

Sources: Annual Report 2016-17, Ministry of Food Processing Industries; PRS.

Inadequate food processing infrastructure

As previously discussed, perishables such as fruits and vegetables are more prone to damages as compared to cereals.  Due to inadequate processing facilities in close proximity, farmers may be unable to hold their produce for a long time.  Hence, they may be forced to sell their produce soon after harvest, irrespective of the prevailing market situations.  Expert committees have recommended that agri-logistics such as cold chain infrastructure and market linkages should be strengthened.

Cold chain infrastructure: Cold chain infrastructure includes processing units, cold storages, and refrigerated vans.  As of 2014, out of a required cold storage capacity of 35 million metric tonnes (MT), almost 90% (31.8 million MT) of the capacity was available (see Table 1).  However, cold storage needs to be coupled with logistical support to facilitate smooth transfer of harvested value from farms to distant locations.  This includes: (i) pack-houses for packaging and preparing fresh produce for long distance transport, (ii) refrigerated transport such as reefer vehicles, and (iii) ripening chambers to ripen raw produce before marketing.  For instance, bananas which are harvested raw may be ripened in these chambers before being marketed.

While there are sufficient cold storages, there are wide gaps in the availability of other associated infrastructure.  This implies that even though almost 90% (32 million tonnes) of cold storage capacity is available, only 15% of the required refrigerated transport exists.  Further, the shortfall in the availability of infrastructure necessary for safe handling of farm produce, like pack-houses and ripening chambers, is over 90%.

Table 1:  Gaps in cold chain infrastructure (2014)

Facility Required Available Gap % gap
Cold storage
(in million MT)

35.1

31.8 3.2

9.3%

Pack-houses

70,080

249 69,831

99.6%

Reefer vehicles

61,826

9,000 52,826

85.4%

Ripening chambers

9,131

812 8,319

91.1%

Source: Standing Committee on Agriculture 2018; PRS.

To minimise post-harvest losses, the Standing Committee (2017) recommended that a country-wide integrated cold chain infrastructure network at block and district levels should be created.  It further recommended that a Cold Chain Coordination and Monitoring Committee should be constituted at the district-level.  The Standing Committee also recommended that farmers need to be trained in value addition activities such as sorting, grading, and pre-cooling harvested produce through facilities such as freezers and ripening chambers.

Between 2008 and 2017, 238 cold chain projects were sanctioned under the Scheme for Integrated Cold Chain and Value Addition Infrastructure.  Grants worth Rs 1,775 crore were approved for these projects.  Of this amount, Rs 964 crore (54%) has been released as of January 2018.  Consequently, out of the total projects sanctioned, 114 (48%) are completed.  The remaining 124 projects are currently under implementation.

Transport Facilities:  Currently, majority of food grains and certain quantities of tea, potato, and onion are transported through railways.  The Committee on Doubling Farmers Income had recommended that railways needs to upgrade its logistics to facilitate the transport of fresh produce directly to export hubs.  This includes creation of adjoining facilities for loading and unloading, and distribution to road transport.

Mega Food Parks: The Mega Food Parks scheme was launched in 2008.  It seeks to facilitate setting up of food processing units.  These units are to be located at a central processing centre with infrastructure required for processing, packaging, quality control labs, and trade facilitation centres.

As of March 2018, out of the 42 projects approved, 10 were operational.  The Standing Committee on Agriculture noted certain reasons for delay in implementation of projects under the scheme.  These include: (i) difficulty in getting loans from banks for the project, (ii) delay in obtaining clearances from the state governments and agencies for roads, power, and water at the project site, (iii) lack of special incentives for setting up food processing units in Mega Food Parks, and (iv) unwillingness of the co-promoters in contributing their share of equity.

Further, the Standing Committee stated that as the scheme requires a minimum area of 50 acres, it does not to promote smaller or individual food processing and preservation units.  It recommended that smaller agro-processing clusters near production areas must be promoted.  The Committee on Doubling Farmers Income recommended establishment of processing and value addition units at strategic places.  This includes rural or production areas for pulses, millets, fruits, vegetables, dairy, fisheries, and poultry in public private-partnership mode.

The Minister of Railways, Dinesh Trivedi, presented the Railways Budget 2012 to Parliament on 14th March.  While commenting on the financial position of Railways, the Minister said that 'the Indian Railways are passing through a difficult phase'. The Operating Ratio for the closing year is now estimated to equal 95%. This is significantly higher than the 91.1% figure budgeted last year. Operating Ratio is a metric that compares operating expenses to revenues. A higher ratio indicates lower ability to generate surplus. Surplus is used for capital investments such as laying of new lines, deploying more coaches etc. Therefore, a smaller surplus affects the Railway’s capability to make such investments. Budget v/s Revised estimates 2011-12 Budget 2011-12 had estimated the performance of Railways for the financial year. Revised estimates have now been submitted. Taken together, these two figures help in comparing actual performance against targets. Some observations are enumerated below:

  • Total receipts decreased by Rs 2,746 crore.
  • Total expenditure increased by Rs 2,102 crore.
  • Operating Ratio increased from 91.1% to 95%. This implies a decrease in surplus.
  • Appropriations to the ‘Development Fund’ and the ‘Capital Fund’ decreased from Rs 5,258 crore to Rs 1,492 crore (a decrease of 72%). The ‘Development Fund’ finances expenditure such as passenger amenities; the ‘Capital Fund’ is used for capital augmentation such as laying of new lines.

Budget estimates 2012-13 In 2012-13, Railways plan to improve Operating Ratio to 84.9% and to increase surplus to Rs 15,557 crore. This is more than 10 times the surplus generated in 2011-12 (Revised Estimates). The effective increase in freight rates is estimated to average 23%. During this time, passenger fares are also estimated to increase by an effective average rate of 19%. [1] Infrastructure Performance during the 11th Plan Under the 11th Five Year Plan, the total plan expenditure for Railways had been approved at Rs 2,33,289 crore. The Outcome Budget shows that the actual expenditure is only likely to be Rs 1,92,291 crore. Thus, expenditure will fall short by Rs 40,998 crore. This gaps exists despite a significant increase in the Gross Budgetary Support approved by Parliament. Plan expenditure during 2007-12 (In Rs Crore)

 

Approved Expenditure

Actual Expenditure

Gross Budgetary Support

63,635

75,979

Internal Resources

90,000

67,763

Extra Budgetary Support

79,654

48,549

Total

2,33,289

1,92,291

The Standing Committee on Railways, in its 11th report presented in August 2011, had sought an explanation from the Ministry. According to the Ministry, lower mobilization of internal resources and lack of extra budgetary support are the main reasons for the shortfall.  Internal resource mobilization has been low because of (i) impact of the 6th Pay Commission; and (ii) slow growth in freight earnings due to the economic slowdown. Extra budgetary resources have been low due to non-materialization of funds through the Public-Private Partnership route. Proposals for the 12th Plan Two recent committees – Kakodkar Committee on Railway Safety and the Pitroda Committee on Railway Modernization – have called for large investments in the next five years. The Kakodkar Committee has recommended an investment of Rs 1,00,000 crore in the next five years to improve safety; the Pitroda Committee has recommended an expenditure of Rs 3,96,000 crore in the next five years on modernization. The Railway sub-group of the 12th Five Year Plan has also estimated a requirement of Rs 4,42,744 crore for various other investments proposed to be undertaken during the Plan period. [2] All three groups have called for significant investments in infrastructure augmentation in the next five years. Budget proposals 2012-13 According to the Minister’s speech, the Annual Plan outlay for the year 2012-13 has been set at Rs 60,100 crore. The plan would be financed through:

  • Gross Budgetary Support of Rs 24,000 crore
  • Railway Safety Fund of Rs 2,000 crore
  • Internal Resources of Rs 18,050 crore
  • Extra Budgetary Resources of Rs 16,050 crore. Of this, Rs 15,000 crore would be borrowed from the market through IRFC (Indian Railway Finance Corporation).

What happens now? The Budget is likely to be discussed in the two Houses within the next few days.  Post the discussion, the Ministry's proposals will be put to vote.  Once passed, the Ministry can put its proposals into action. For more details on the Railway Budget, including the projects proposed this year and the status of proposals made last year, please see our analysis here. To understand some of the challenges faced by the Indian Railways, see our blog post from last year. Notes: [1] The ‘effective average fare’ has been calculated by dividing the total income from the segment (freight/ passenger) by the total traffic (in NTKM/ PKM).  This would vary with changes in fares as well as the usage by different categories of users (including the proportion of tickets booked through Tatkal). [2] Source: Report of the Expert Group on Railway Modernization (Chairman: Sam Pitroda)