Last week, the Planning Commission filed an affidavit in the Supreme Court updating the official poverty line to Rs 965 per month in urban areas and Rs 781 in rural areas. This works out to Rs 32 and and Rs 26 per day, respectively. The perceived inadequacy of these figures has led to widespread discussion and criticism in the media. In light of the controversy, it may be worth looking at where the numbers come from in the first place. Two Measures of the BPL Population The official poverty line is determined by the Planning Commission, on the basis of data provided by the National Sample Survey Organisation (NSSO). NSSO data is based on a survey of consumer expenditure which takes place every five years.  The most recent Planning Commission poverty estimates are for the year 2004-05. In addition to Planning Commission efforts to determine the poverty line, the Ministry of Rural Development has conducted a BPL Census in 1992, 1997, 2002, and 2011 to identify poor households. The BPL Census is used to target families for assistance through various schemes of the central government. The 2011 BPL Census is being conducted along with a caste census, and is dubbed the Socio-Economic & Caste Census (SECC) 2011. Details on the methodology of SECC 2011 are available in this short Ministry of Rural Development circular. Planning Commission Methodology Rural and urban poverty lines were first defined in 1973-74 in terms of Per Capita Total Expenditure (PCTE). Consumption is measured in terms of a collection of goods and services known as reference Poverty Line Baskets (PLB). These PLB were determined separately for urban and rural areas and based on a per-day calorie intake of 2400 (rural) and 2100 (urban), each containing items such as food, clothing, fuel, rent, conveyance and entertainment, among others. The official poverty line is the national average expenditure per person incurred to obtain the goods in the PLB. Since 1973-74, prices for goods in the PLB have been periodically adjusted over time and across states to deduce the official poverty line. Uniform Reference Period (URP) vs Mixed Reference Period (MRP) Until 1993-94, consumption information collected by the NSSO was based on the Uniform Reference Period (URP), which measured consumption across a 30-day recall period. That is, survey respondents were asked about their consumption  in the previous 30 days. From 1999-2000 onwards, the NSSO switched to a method known as the Mixed Reference Period (MRP). The MRP measures consumption of five low-frequency items (clothing, footwear, durables, education and institutional health expenditure) over the previous year, and all other items over the previous 30 days. That is to say, for the five items, survey respondents are asked about consumption in the previous one year. For the remaining items, they are asked about consumption in the previous 30 days. Tendulkar Committee Report In 2009, the Tendulkar Committee Report suggested several changes to the way poverty is measured.  First, it recommended a shift away from basing the PLB in caloric intake and towards target nutritional outcomes instead. Second, it recommended that a uniform PLB be used for both rural and urban areas. In addition, it recommended a change in the way prices are adjusted, and called for an explicit provision in the PLB to account for private expenditure in health and education. For these reasons, the Tendulkar estimate of poverty for the years 1993-94 and 2004-05 is higher than the official estimate, regardless of whether one looks at URP or MRP figures. For example, while the official 1993-94 All-India poverty figure is 36% (URP), applying the Tendulkar methodology yields a rate of 45.3%. Similarly, the official 2004-05 poverty rate is 21.8% (MRP) or 27.5% (URP), while applying the the Tendulkar methodology brings the number to 37.2%. A Planning Commission table of poverty rates by state comparing the two methodologies by is available here.  

On November 28, 2012, the Comptroller and Auditor General submitted its report on the implementation of the Jawaharlal Nehru National Urban Renewal Mission (JNNURM).  According to the report most of the projects initiated under JNNURM have not been completed.  For instance with respect to urban infrastructure projects, only 231 projects out of the 1298 sanctioned projects have been completed.  Similarly, with respect to housing projects, only 22 of the 1517 projects have been completed.  Some of the other key recommendations of the report are:

  •  Some of the reasons for the delay in completing the projects include: (i) delay in acquiring land; (ii) deficiency in preparation of projects; and (iii) non-identification of beneficiaries which increased the risk of ineligible beneficiaries getting the benefits.
  •  A total allocation of Rs 66,084 crore had been made by the Planning Commission.  However, against this total allocation, the central government had made an allocation of only Rs 37,070 out of which until March 30, 2011 only Rs 32,934 had been released.
  • There was a delay in releasing these funds to the states.  A large portion of the funds was released only in the last quarter and more particularly in March.
  • The JNNURM guidelines were deficient as they did not provide adequate guidance to the states on the method of parking the funds and utilization of interest.

The need and objectives of JNNURM According to the 2011 census India’s urban population has increased from 286 million in 2001 to 377 million in 2011 .  With the increase in urban population, there is a requirement to improve the urban infrastructure and improve the service delivery mechanisms.  With these specific objectives in mind, the central government launched the Jawaharlal Nehru National Urban Renewal Mission 2005-2006.  The aim of the Mission is to encourage reforms and fast track planned development of identified cities (such as cities with a population of more than 1 million as per the 2001 census).  JNNURM has two main components namely : (i) Urban Infrastructure and Governance  and (ii) Urban Infrastructure Development for Small and Medium Towns. The duration of JNNURM was from 2005-06 to 2011-12. However, as the projects have not been completed the Government has extended its duration until March 2014. Funds for JNNURM The funds for JNNURM are provided through the Additional Central Assistance.  This implies that the funds are provided as grants to the states directly from the centre.   In the 2012 Union Budget, the central government has allocated Rs 12,522 crore for JNNURM. This represents around 10 % of the total central assistance through the different schemes to states and union territories in 2012-13. As on June 30 2012, 554 projects at a total cost of Rs 62,253 crore have been sanctioned under the Urban Infrastructure and Governance sub-mission of JNNURM.   The table below shows the status of the sanctioned JNNURM  projects in the different states. State wise status of the projects under JNNURM                 (as on August 6, 2012)

Name of State Total Allocation (Rs Lakh) Number of sanctioned projects Completed Projects
Andhra Pradesh 2,11,845 52 18
Arunachal Pradesh 10,740 3 NA
Assam 27,320 2 NA
Bihar 59,241 8 NA
Chandigarh 27,087 3 NA
Chattisgarh 24,803 1 NA
Delhi 2,82,318 23 4
Goa 12,094 2 NA
Gujarat 2,57,881 72 40
Haryana 32,332 4 NA
Himachal Pradesh 13,066 5 NA
Jammu & Kashmir 48,836 5 NA
Jharkhand 94,120 5 NA
Karnataka 1,52,459 47 22
Kerala 67,476 11 NA
Madhya Pradesh 1,32,850 23 7
Maharashtra 5,50,555 80 21
Manipur 15,287 3 NA
Meghalaya 15,668 2 NA
Mizoram 14,822 4 NA
Nagaland 11,628 3 NA
Orissa 32,235 5 NA
Punjab 70,775 6 1
Puducherry 20,680 2 NA
Rajasthan 74,869 13 2
Sikkim 10,613 2 NA
Tamil Nadu 2,25,066 48 12
Tripura 14,018 2 NA
Uttar Pradesh 2,76,941 33 4
Uttarakhand 40,534 14 NA
West Bengal 3,21,840 69 15

Source: Jawaharlal Nehru National Urban Renewal Mission; PRS.

  • Gujarat at 55.55% has the highest number of completed projects, while Uttar Pradesh at 12.24% has the lowest number of completed projects.
  • Out of the larger states, Delhi and Maharashtra at 17% and 26% have a comparatively low rate of completed projects.
  • Maharashtra has the highest number of sanctioned projects, while the North Eastern states, Chattisgarh and Puducherry have the lowest number of sanctioned projects.