By Chakshu Rai and Anirudh Burman What is the difference between a JPC and a PAC? A structured committee system was introduced in 1993 to provide for greater scrutiny of government functioning by Parliament. Most committees of Parliament include MPs from both the Lok Sabha and Rajya Sabha. A Joint Parliamentary Committee (JPC) is an ad-hoc body. It is set up for a specific object and duration. Joint committees are set up by a motion passed in one house of Parliament and agreed to by the other. The details regarding membership and subjects are also decided by Parliament. For example, the motion to constitute a JPC on the stock market scam (2001) and pesticide residues in soft drinks (2003) was moved by the government in the Lok Sabha. The motion on the stock market scam constituted a JPC of 30 members of which 20 were from the Lok Sabha and 10 were from the Rajya Sabha. The motion to constitute the JPC on pesticides included 10 members from the Lok Sabha and 5 from the Rajya Sabha. The terms of reference for the JPC on the stock market scam asked the committee to look into financial irregularities, to fix responsibility on persons and institutions for the scam, to identify regulatory loopholes and also to make suitable recommendations. The Public Accounts Committee (PAC), however, is constituted every year. Its main duty is to ascertain how the money granted (budget) by Parliament has been spent by the government. The PAC scrutinises the accounts of the government on the basis of CAG reports. The composition and functions of the committee are governed by parliamentary procedures. The PAC can consist of 15 to 22 members. Not more than 15 members can be from the Lok Sabha, and the representation from the Rajya Sabha cannot exceed 7 members. A minister cannot be a member of the PAC. What can a JPC do that a PAC cannot? The PAC examines cases involving losses and financial irregularities. Its examination is usually limited to the scrutiny of CAG reports and issues raised by the reports. The committee expresses no opinion on points of general policy, but it is within PAC’s jurisdiction to point out whether there has been waste in carrying out that policy. The mandate of a JPC depends on the motion constituting it. This need not be limited to the scrutiny of government finances. How many JPCs have we had so far? Although a number of joint committees have been formed since Independence, four major JPCs have been formed to investigate significant issues that have caused controversy. These are: (1) Joint Committee on Bofors Contracts; (2) Joint Committee to enquire into irregularities in securities and banking transactions; (3) Joint Committee on stock-market scam; and (4) Joint Committee on pesticide residues in and safety standards for soft drinks. How effective have JPCs been? Is the government bound by their recommendations? JPC recommendations have persuasive value but the committee cannot force the government to take any action on the basis of its report. The government may decide to launch fresh investigations on the basis of a JPC report. However, the discretion to do so rests entirely with the government. The government is required to report on the follow-up action taken on the basis of the recommendations of the JPC and other committees. The committees then submit ‘Action Taken Reports’ in Parliament on the basis of the government’s reply. These reports can be discussed in Parliament and the government can be questioned on the basis of the same. How effective is the PAC process? Between 2005 and 2010, the PAC has prepared 54 reports and examined ministries that have cumulatively received around 80% of the budgetary allocations in the last five financial years. Since it is not possible to examine every CAG audit finding in a formal manner, ministries have to submit Action Taken Notes to the PAC on all audit paragraphs. A 2009-10 report of the PAC, however, noted that there were 4,934 audit paragraphs still pending with various ministries. What can the JPC or the PAC find in the 2G case that is not already known, that the CAG and the Trai have not already said? The JPC or the PAC can only look at the documents and examine ministry officials who testify before the committee. The parliamentary committees can arrive at independent conclusions based on the documents placed before them. Members of the committee can also place dissent notes if they do not agree with the majority. Can Raja be tried and the telecom licences cancelled on basis of a JPC report or do we need a CBI report as well? Prosecution of individuals and cancellation of licences are executive functions and can only be initiated by the government. A JPC report can recommend the prosecution of a particular person or the cancellation of certain licences. However, the government can disagree with the JPC’s findings and refuse to take such action. How much of Parliament time have we lost already and how many critical Bills are stuck? The Lok Sabha and Rajya Sabha are supposed to work daily for six hours and five hours, respectively. The Lok Sabha has worked for five hours and forty five minutes and Rajya Sabha has worked for an hour and twenty five minutes in the past 12 days. Some important Bills that are listed for consideration and passing in Parliament are the Seeds Bill, 2004; the Commercial Division of High Courts Bill, 2009; and the Amendment to the Right to Education Act, 2010. Bills listed for introduction include the National Identification Authority Bill, 2010; the Protection of Women from Sexual Harassment in Workplace Bill, 2010; the Judicial Standards and Accountability Bill, 2010; Land Acquisition (Amendment) Bill; and the Rehabilitation and Resettlement Bill. This article appeared in Financial Express.

In Budget Session 2018, Rajya Sabha has planned to examine the working of four ministries.  The Ministry of Drinking Water and Sanitation is one of the ministries listed for discussion.  In this post, we look at the key schemes being implemented by the Ministry and their status.

What are the key functions of the Ministry of Drinking Water and Sanitation?

As per the Constitution, supply of water and sanitation are state subjects which means that states regulate and provide these services.  The Ministry of Drinking Water and Sanitation is primarily responsible for policy planning, funding, and coordination of programs for: (i) safe drinking water; and (ii) sanitation, in rural areas.  From 1999 till 2011, the Ministry operated as a Department under the Ministry of Rural Development.  In 2011, the Department was made an independent Ministry.  Presently, the Ministry oversees the implementation of two key schemes of the government: (i) Swachh Bharat Mission-Gramin (SBM-G), and (ii) National Rural Drinking Water Programme (NRDWP).

How have the finances and spending priorities of the Ministry changed over time?

In the Union Budget 2018-19, the Ministry has been allocated Rs 22,357 crore.  This is a decrease of Rs 1,654 crore (7%) over the revised expenditure of 2017-18.  In 2015-16, the Ministry over-shot its budget by 178%.  Consequently, the allocation in 2016-17 was more than doubled (124%) to Rs 14,009 crore.

In recent years, the priorities of the Ministry have seen a shift (see Figure 1).  The focus has been on providing sanitation facilities in rural areas, mobilising behavioural change to increase usage of toilets, and consequently eliminating open defecation.  However, this has translated into a decrease in the share of allocation towards drinking water (from 87% in 2009-10 to 31% in 2018-19).  In the same period, the share of allocation to rural sanitation has increased from 13% to 69%.Figure 1

What has been the progress under Swacch Bharat Mission- Gramin?

The Swachh Bharat Mission was launched on October 2, 2014 with an aim to achieve universal sanitation coverage, improve cleanliness, and eliminate open defecation in the country by October 2, 2019.

Expenditure on SBM-G:  In 2018-19, Rs 15,343 crore has been allocated towards SBM-G.  The central government allocation to SBM-G for the five year period from 2014-15 to 2018-19 has been estimated to be Rs 1,00,447 crore.  Of this, up to 2018-19, Rs 52,166 crore (52%) has been allocated to the scheme.  This implies that 48% of the funds are still left to be released before October 2019.  Figure 2

Construction of Individual Household Latrines (IHHLs):  For construction of IHHLs, funds are shared between the centre and states in the 60:40 ratio.  Construction of IHHLs account for the largest share of total expenditure under the scheme (97%-98%).  Although the number of toilets constructed each year has increased, the pace of annual growth of constructing these toilets has come down.  In 2015-16, the number of toilets constructed was 156% higher than the previous year.  This could be due to the fact that 2015-16 was the first full year of implementation of the scheme.  The growth in construction of new toilets reduced to 74% in 2016-17, and further to 4% in 2017-18.Table 1

As of February 2018, 78.8% of households in India had a toilet.  This implies that 15 crore toilets have been constructed so far.  However, four crore more toilets need to be construced in the next 20 months for the scheme to achieve its target by 2019.

Open Defecation Free (ODF) villages:  Under SBM-G, a village is ODF when: (i) there are no visible faeces in the village, and (ii) every household as well as public/community institution uses safe technology options for faecal disposal.  After a village declares itself ODF, states are required to carry out verification of the ODF status of such a village.  This includes access to a toilet facility and its usage, and safe disposal of faecal matter through septic tanks.  So far, out of all villages in the country, 72% have been verified as ODF.  This implies that 28% villages are left to be verified as ODF for the scheme to achieve its target by 2019.Table 2

Information, Education and Communication (IEC) activities:  As per the SBM-G guidelines, 8% of funds earmarked for SBM-G in a year should be utilised for IEC activities.  These activities primarily aim to mobilise behavioural change towards the use of toilets among people.  However, allocation towards this component has remained in the 1%-4% range.  In 2017-18, Rs 229 crore is expected to be spent, amounting to 2% of total expenditure.

What is the implementation status of the National Rural Drinking Water Programme?

The National Rural Drinking Water Programme (NRDWP) aims at assisting states in providing adequate and safe drinking water to the rural population in the country.  In 2018-19, the scheme has been allocated Rs 7,000 crore, accounting for 31% of the Ministry’s finances.Figure 3

Coverage under the scheme:  As of August 2017, 96% of rural habitations have access to safe drinking water.  In 2011, the Ministry came out with a strategic plan for the period 2011-22.  The plan identified certain standards for coverage of habitations with water supply, including targets for per day supply of drinking water.  As of February 2018, 74% habitations are fully covered (receiving 55 litres per capita per day), and 22% habitations are partially covered (receiving less than 55 litres per capita per day).  The Ministry aims to cover 90% rural households with piped water supply and 80% rural households with tap connections by 2022.  The Estimates Committee of Parliament (2015) observed that piped water supply was available to only 47% of rural habitations, out of which only 15% had household tap connections.

Contamination of drinking water:  It has been noted that NRDWP is over-dependant on ground water.  However, ground water is contaminated in over 20 states.  For instance, high arsenic contamination has been found in 68 districts of 10 states.  These states are Haryana, Punjab, Uttar Pradesh, Bihar, Jharkhand, Chhattisgarh, West Bengal, Assam, Manipur, and Karnataka.Table 3

Chemical contamination of ground water has also been reported due to deeper drilling for drinking water sources.  It has been recommended that out of the total funds for NRDWP, allocation for water quality monitoring and surveillance should not be less than 5%.  Presently, it is 3% of the total funds.  It has also been suggested that water quality laboratories for water testing should be set up throughout the country.