By Chakshu Rai and Anirudh Burman What is the difference between a JPC and a PAC? A structured committee system was introduced in 1993 to provide for greater scrutiny of government functioning by Parliament. Most committees of Parliament include MPs from both the Lok Sabha and Rajya Sabha. A Joint Parliamentary Committee (JPC) is an ad-hoc body. It is set up for a specific object and duration. Joint committees are set up by a motion passed in one house of Parliament and agreed to by the other. The details regarding membership and subjects are also decided by Parliament. For example, the motion to constitute a JPC on the stock market scam (2001) and pesticide residues in soft drinks (2003) was moved by the government in the Lok Sabha. The motion on the stock market scam constituted a JPC of 30 members of which 20 were from the Lok Sabha and 10 were from the Rajya Sabha. The motion to constitute the JPC on pesticides included 10 members from the Lok Sabha and 5 from the Rajya Sabha. The terms of reference for the JPC on the stock market scam asked the committee to look into financial irregularities, to fix responsibility on persons and institutions for the scam, to identify regulatory loopholes and also to make suitable recommendations. The Public Accounts Committee (PAC), however, is constituted every year. Its main duty is to ascertain how the money granted (budget) by Parliament has been spent by the government. The PAC scrutinises the accounts of the government on the basis of CAG reports. The composition and functions of the committee are governed by parliamentary procedures. The PAC can consist of 15 to 22 members. Not more than 15 members can be from the Lok Sabha, and the representation from the Rajya Sabha cannot exceed 7 members. A minister cannot be a member of the PAC. What can a JPC do that a PAC cannot? The PAC examines cases involving losses and financial irregularities. Its examination is usually limited to the scrutiny of CAG reports and issues raised by the reports. The committee expresses no opinion on points of general policy, but it is within PAC’s jurisdiction to point out whether there has been waste in carrying out that policy. The mandate of a JPC depends on the motion constituting it. This need not be limited to the scrutiny of government finances. How many JPCs have we had so far? Although a number of joint committees have been formed since Independence, four major JPCs have been formed to investigate significant issues that have caused controversy. These are: (1) Joint Committee on Bofors Contracts; (2) Joint Committee to enquire into irregularities in securities and banking transactions; (3) Joint Committee on stock-market scam; and (4) Joint Committee on pesticide residues in and safety standards for soft drinks. How effective have JPCs been? Is the government bound by their recommendations? JPC recommendations have persuasive value but the committee cannot force the government to take any action on the basis of its report. The government may decide to launch fresh investigations on the basis of a JPC report. However, the discretion to do so rests entirely with the government. The government is required to report on the follow-up action taken on the basis of the recommendations of the JPC and other committees. The committees then submit ‘Action Taken Reports’ in Parliament on the basis of the government’s reply. These reports can be discussed in Parliament and the government can be questioned on the basis of the same. How effective is the PAC process? Between 2005 and 2010, the PAC has prepared 54 reports and examined ministries that have cumulatively received around 80% of the budgetary allocations in the last five financial years. Since it is not possible to examine every CAG audit finding in a formal manner, ministries have to submit Action Taken Notes to the PAC on all audit paragraphs. A 2009-10 report of the PAC, however, noted that there were 4,934 audit paragraphs still pending with various ministries. What can the JPC or the PAC find in the 2G case that is not already known, that the CAG and the Trai have not already said? The JPC or the PAC can only look at the documents and examine ministry officials who testify before the committee. The parliamentary committees can arrive at independent conclusions based on the documents placed before them. Members of the committee can also place dissent notes if they do not agree with the majority. Can Raja be tried and the telecom licences cancelled on basis of a JPC report or do we need a CBI report as well? Prosecution of individuals and cancellation of licences are executive functions and can only be initiated by the government. A JPC report can recommend the prosecution of a particular person or the cancellation of certain licences. However, the government can disagree with the JPC’s findings and refuse to take such action. How much of Parliament time have we lost already and how many critical Bills are stuck? The Lok Sabha and Rajya Sabha are supposed to work daily for six hours and five hours, respectively. The Lok Sabha has worked for five hours and forty five minutes and Rajya Sabha has worked for an hour and twenty five minutes in the past 12 days. Some important Bills that are listed for consideration and passing in Parliament are the Seeds Bill, 2004; the Commercial Division of High Courts Bill, 2009; and the Amendment to the Right to Education Act, 2010. Bills listed for introduction include the National Identification Authority Bill, 2010; the Protection of Women from Sexual Harassment in Workplace Bill, 2010; the Judicial Standards and Accountability Bill, 2010; Land Acquisition (Amendment) Bill; and the Rehabilitation and Resettlement Bill. This article appeared in Financial Express.

Recently, the central government launched the Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya).[i],[ii]  The scheme seeks to ensure universal household electrification (in both rural and urban areas) by providing last mile connectivity.  The scheme is expected to cover three crore households.  Note that currently about four crore households are un-electrified.  A rural electrification scheme has also been under implementation since 2005.  In light of this, we discuss the current situation of, and key issues related to rural electrification in the country.

Regulatory and policy framework

Under the Electricity Act, 2003, the central and state governments have the joint responsibility of providing electricity to rural areas.  The 2003 Act also mandates that the central government should, in consultation with the state governments, provide for a national policy on (i) stand-alone power systems for rural areas (systems that are not connected to the electricity grid), and (ii) electrification and local distribution in rural areas.  Consequently, the Rural Electrification Policy was notified in August 2006.[iii]

The Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), launched in 2005, was the first scheme on rural electrification.  In December 2014, Ministry of Power launched the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), which subsumed the RGGVY.[iv]  Components of DDUGJY include: (i) separation of agricultural and non-agricultural electricity feeders to improve supply for consumers in rural areas, (ii) improving sub-transmission and distribution infrastructure in rural areas, and (iii) rural electrification by carrying forward targets specified under the RGGVY.

The total financial outlay for DDUGJY over the implementation period (until 2021-22) is Rs 82,300 crore which includes budgetary support of Rs 68,900 crore.  The central government provides 60% of the project cost as grant, the state power distribution companies (discoms) raise 10% of the funds, and 30% is borrowed from financial institutions and banks.

Status of rural electrification

As of August 2017, about 1% of the villages in India remain un-electrified (3,146 villages).  However, with regard to households, around 23% (4.1 crore households) are yet to be electrified.  Table 1 at the end of this post shows the status of rural electrification across all states.

Issues with rural electrification

Definition of an electrified village

An electrified village is defined as one that has the following: (i) provision of basic infrastructure such as distribution transformers and lines in the inhabited locality, (ii) provision of electricity in public places like schools, panchayat office, health centers, dispensaries, and community centers, and (iii) at least 10% of the total number of households in the village are electrified.[iv]

Therefore, a village is considered to be electrified if 10% of the total number of households in the village have been electrified.  This is apart from the basic infrastructure and electrification of certain public centers in the village.  The Standing Committee on Energy (2013) had observed that according to this definition, a village would be called electrified even if up to 90% of households in it do not have an electricity connection.[v]  It also noted that the infrastructure being provided under the scheme is highly inadequate, unreliable and unsustainable.  The Committee recommended that the actual electrification requirement of villages must be assessed, and it should be ensured that the state discoms provide electricity to the remaining households in the village.

Supply of electricity

The Standing Committee had also noted that while the rural electrification scheme looks at creating infrastructure, the actual supply of electricity to households rests with the state discoms.[v]  These discoms are already facing huge financial losses and hence are unable to supply electricity to the villages.  Discoms continue to supply subsidised power to agricultural and residential consumers, resulting in revenue losses.  Further, the average technical and commercial losses (theft and pilferage of electricity) (AT&C losses) are at around 25%.  While the Ujjwal Discom Assurance Yojana (UDAY) has eased off some of the financial losses of the discoms, it remains to be seen whether discoms are able to reduce the cost-tariff gap and AT&C losses in the future.

It has been recommended that generation capacity should be augmented so that states can meet the additional demand under the rural electrification schemes. Further, the assistance to financially weaker states should be increased so that they can better implement the scheme.[v]

Electricity to below poverty line (BPL) households

Under the rural electrification scheme, the cost for providing free electricity connection per BPL household is Rs 3,000.  It has been observed that this cost per household may be inadequate.[v]  Due to the low cost, the quantity and the quality of work has been getting compromised leading to poor implementation of the scheme.  It has been recommended that the Ministry should revisit the cost provided under the scheme.[v]

The new electrification scheme: Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya)

The new scheme, Saubhagya, seeks to ensure universal household electrification, that is, in both rural and urban areas.  Under Saubhagya, beneficiaries will be identified using the Socio Economic and Caste Census (SECC) 2011 data.  The identified poor households will get free electricity connections.  Other households not covered under the SECC, will be provided electricity connections at a cost of Rs 500.  This amount will be collected by the electricity distribution companies in 10 instalments.

The total outlay of the scheme will be Rs 16,320 crore, of which the central government will provide Rs 12,320 crore.  The outlay for the rural households will be Rs 14,025 crore, of which the centre will provide Rs 10,588 crore.  For urban households the outlay will be Rs 2,295 crore of which the centre will provide Rs. 1,733 crore.

The state discoms will execute the electrification works through contractors or other suitable agencies.  Information technology (mobile apps, web portals) will be used to organise camps in villages to identify beneficiaries.  In order to accelerate the process, applications for electricity connections will be completed on the spot.

So far the focus of electrification schemes has been on rural areas, where typically last mile connectivity has been difficult to provide.  Saubhagya extends the ambit of electrification projects to urban areas as well.  While DDUGJY has focused on the village as the principal unit to measure electrification, the new scheme shifts the targets to household electrification.  While the target for ensuring electricity connection in each household will be a significant step towards ensuring 24×7 power, the question of continuous and quality supply to these households will still rest on the ability of the discoms to provide electricity.  Further, while the scheme provides for free connections, the ability of these households to pay for the electricity they consume may be a concern.

Table 1: Status of rural electrification across states (as of August 2017)

Fig 1 edit

* all villages in Telangana were declared electrified before the bifurcation of the state.
Sources:  Ministry of Power; PRS.

 

[i] “PM launches Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 25, 2017.

[ii] “FAQs on Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 27, 2017.

[iii].  Rural Electrification Policy, Ministry of Power, August 23, 2006, http://powermin.nic.in/sites/default/files/uploads/RE%20Policy_1.pdf.

[iv].  “Office memorandum: Deendayal Upadhyaya Gram Jyoti Yojana”, Ministry of Power, December 3, 2014, http://powermin.nic.in/rural_electrification/pdf/Deendayal_Upadhyaya_Gram_Jyoti_Yojana.pdf.

[v].  “41st Report: Implementation of Rajiv Gandhi Grameen Vidyutikaran Yojana”, Standing Committee on Energy, December 13, 2013, http://164.100.47.134/lsscommittee/Energy/15_Energy_41.pdf.