The issue of the General Anti Avoidance Rule (GAAR) has dominated the news recently and there are fears that GAAR will discourage foreign investment in India.  However, tax avoidance can hinder public finance objectives and it is in this context GAAR was introduced in this year’s Budget.  Last week, the Finance Minister pushed back the implementation of GAAR by a year. What is GAAR? GAAR was first introduced in the Direct Taxes Code Bill 2010.  The original proposal gave the Commissioner of Income Tax the authority to declare any arrangement or transaction by a taxpayer as ‘impermissible’ if he believed the main purpose of the arrangement was to obtain a tax benefit.  The 2012-13 Finance Bill (Bill), that was passed by Parliament yesterday, defines ‘impermissible avoidance arrangements’ as an arrangement that satisfies one of four tests.  Under these tests, an agreement would be an ‘impermissible avoidance arrangement’ if it  (i) creates rights and obligations not normally created between parties dealing at arm’s length, (ii) results in misuse or abuse of provisions of tax laws, (iii) is carried out in a way not normally employed for bona fide purpose or (iv) lacks commercial substance. As per the Bill, arrangements which lack commercial substance could involve round trip financing, an accommodating party and elements that have the effect of offsetting or cancelling each other.  A transaction that disguises the value, location, source, ownership or control of funds would also be deemed to lack commercial substance. The Bill as introduced also presumed that obtaining a tax benefit was the main purpose of an arrangement unless the taxpayer could prove otherwise. Why? GAAR was introduced to address tax avoidance and ensure that those in different tax brackets are taxed the correct amount.  In many instances of tax avoidance, arrangements may take place with the sole intention of gaining a tax advantage while complying with the law.  This is when the doctrine of ‘substance over form’ may apply.  ‘Substance over form’ is where real intention of parties and the purpose of an arrangement is taken into account rather than just the nomenclature of the arrangement.  Many countries, like Canada and South Africa, have codified the doctrine of ‘substance over form’ through a GAAR – type ruling. Issues with GAARcommon criticism of GAAR is that it provides discretion and authority to the tax administration which can be misused.  The Standing Committee responded to GAAR in their report on the Direct Taxes Code Bill in March, 2012. They suggested that the provisions should ensure that taxpayers entering genuinely valid arrangements are not harassed.  They recommended that the onus should be on tax authorities, not the taxpayer, to prove tax avoidance.  In addition, the committee suggested an independent body to act as the approving panel to ensure impartiality.  They also recommended that the assessing officer be designated in the code to reduce harassment and unwarranted litigation. GAAR Amendments On May 8, 2012 the Finance Minister amended the GAAR provisions following the Standing Committee’s recommendations.  The main change was to delay the implementation of GAAR by a year to “provide more time to both taxpayers and the tax administration to address all related issues”.  GAAR will now apply on income earned in 2013-14 and thereafter.  In addition, the Finance Minister removed the burden upon the taxpayer to prove that the main purpose of an alleged impermissible arrangement was not to obtain tax benefit.  These amendments were approved with the passing of the Bill. In his speech, the Finance Minister stated that a Committee had also been formed under the Chairmanship of the Director General of Income Tax.  The Committee will suggest rules, guidelines and safeguards for implementation of GAAR.  The Committee is expected to submit its recommendations by May 31, 2012 after holding discussions with various stakeholders in the debate.

 

On November 28, 2012, the Comptroller and Auditor General submitted its report on the implementation of the Jawaharlal Nehru National Urban Renewal Mission (JNNURM).  According to the report most of the projects initiated under JNNURM have not been completed.  For instance with respect to urban infrastructure projects, only 231 projects out of the 1298 sanctioned projects have been completed.  Similarly, with respect to housing projects, only 22 of the 1517 projects have been completed.  Some of the other key recommendations of the report are:

  •  Some of the reasons for the delay in completing the projects include: (i) delay in acquiring land; (ii) deficiency in preparation of projects; and (iii) non-identification of beneficiaries which increased the risk of ineligible beneficiaries getting the benefits.
  •  A total allocation of Rs 66,084 crore had been made by the Planning Commission.  However, against this total allocation, the central government had made an allocation of only Rs 37,070 out of which until March 30, 2011 only Rs 32,934 had been released.
  • There was a delay in releasing these funds to the states.  A large portion of the funds was released only in the last quarter and more particularly in March.
  • The JNNURM guidelines were deficient as they did not provide adequate guidance to the states on the method of parking the funds and utilization of interest.

The need and objectives of JNNURM According to the 2011 census India’s urban population has increased from 286 million in 2001 to 377 million in 2011 .  With the increase in urban population, there is a requirement to improve the urban infrastructure and improve the service delivery mechanisms.  With these specific objectives in mind, the central government launched the Jawaharlal Nehru National Urban Renewal Mission 2005-2006.  The aim of the Mission is to encourage reforms and fast track planned development of identified cities (such as cities with a population of more than 1 million as per the 2001 census).  JNNURM has two main components namely : (i) Urban Infrastructure and Governance  and (ii) Urban Infrastructure Development for Small and Medium Towns. The duration of JNNURM was from 2005-06 to 2011-12. However, as the projects have not been completed the Government has extended its duration until March 2014. Funds for JNNURM The funds for JNNURM are provided through the Additional Central Assistance.  This implies that the funds are provided as grants to the states directly from the centre.   In the 2012 Union Budget, the central government has allocated Rs 12,522 crore for JNNURM. This represents around 10 % of the total central assistance through the different schemes to states and union territories in 2012-13. As on June 30 2012, 554 projects at a total cost of Rs 62,253 crore have been sanctioned under the Urban Infrastructure and Governance sub-mission of JNNURM.   The table below shows the status of the sanctioned JNNURM  projects in the different states. State wise status of the projects under JNNURM                 (as on August 6, 2012)

Name of State Total Allocation (Rs Lakh) Number of sanctioned projects Completed Projects
Andhra Pradesh 2,11,845 52 18
Arunachal Pradesh 10,740 3 NA
Assam 27,320 2 NA
Bihar 59,241 8 NA
Chandigarh 27,087 3 NA
Chattisgarh 24,803 1 NA
Delhi 2,82,318 23 4
Goa 12,094 2 NA
Gujarat 2,57,881 72 40
Haryana 32,332 4 NA
Himachal Pradesh 13,066 5 NA
Jammu & Kashmir 48,836 5 NA
Jharkhand 94,120 5 NA
Karnataka 1,52,459 47 22
Kerala 67,476 11 NA
Madhya Pradesh 1,32,850 23 7
Maharashtra 5,50,555 80 21
Manipur 15,287 3 NA
Meghalaya 15,668 2 NA
Mizoram 14,822 4 NA
Nagaland 11,628 3 NA
Orissa 32,235 5 NA
Punjab 70,775 6 1
Puducherry 20,680 2 NA
Rajasthan 74,869 13 2
Sikkim 10,613 2 NA
Tamil Nadu 2,25,066 48 12
Tripura 14,018 2 NA
Uttar Pradesh 2,76,941 33 4
Uttarakhand 40,534 14 NA
West Bengal 3,21,840 69 15

Source: Jawaharlal Nehru National Urban Renewal Mission; PRS.

  • Gujarat at 55.55% has the highest number of completed projects, while Uttar Pradesh at 12.24% has the lowest number of completed projects.
  • Out of the larger states, Delhi and Maharashtra at 17% and 26% have a comparatively low rate of completed projects.
  • Maharashtra has the highest number of sanctioned projects, while the North Eastern states, Chattisgarh and Puducherry have the lowest number of sanctioned projects.