Recently, the Kelkar Committee published a roadmap for fiscal consolidation.  The report stresses the need and urgency to address India’s fiscal deficit.  A high fiscal deficit – the excess of government expenditure over receipts – can be problematic for many reasons.  The fiscal deficit is financed by government borrowing; increased borrowing can crowd out funds available for private investment. High government spending can also lead to a rise in price levels.  A full PRS summary of the report can be found here. Recent fiscal trends Last year (2011-12), the central government posted a fiscal deficit of 5.8% (of GDP), significantly higher than the targeted 4.6%.  This is in stark contrast to five years ago in 2007-08, when after embarking on a path of fiscal consolidation the government’s fiscal deficit had shrunk to a 30 year low of 2.5%. In 2008-09, a combination of the Sixth Pay Commission, farmers’ debt waiver and a crisis-driven stimulus led to the deficit rising to 6% and it has not returned to those levels since.  As of August this year, government accounts reveal a fiscal deficit of Rs 3,37,538 crore which is 65.7% of the targeted deficit with seven months to go in the fiscal year.   With growth slowing this year, the committee expects tax receipts to fall short of expectations significantly and expenditure to overshoot budget estimates, leaving the economy on the edge of a “fiscal precipice”.

Figure 1 (source: RBI)

 

  Committee recommendations - expenditure To tackle the deficit on the expenditure side, the committee wants to ease the subsidy burden.  Subsidy expenditure, as a percentage of GDP, has crept up in the last two years (see Figure 2) and the committee expects it to reach 2.6% of GDP in 2012-13.  In response, the committee calls for an immediate increase in the price of diesel, kerosene and LPG.  The committee also recommends phasing out the subsidy on diesel and LPG by 2014-15.   Initial reports suggest that the government may not support this phasing out of subsidies.

Figure 2 (source: RBI, Union Budget documents, PRS)

 

  For the fertiliser subsidy, the committee recommends implementing the Department of Fertilisers proposal of a 10% price increase on urea.  Last week , the government raised the price of urea by Rs 50 per tonne (a 0.9% increase). Finally, the committee explains the rising food subsidy expenditure as a mismatch between the issue price and the minimum support price and wants this to be addressed. Committee recommendations - receipts Rising subsidies have not been matched by a significant increase in receipts through taxation: gross tax revenue as a percentage of GDP has remained around 10% of GDP (see Figure 3). The committee seeks to improve collections in both direct and indirect taxes via better tax administration.  Over the last decade, income from direct taxes – the tax on income – has emerged as the biggest contributor to the Indian exchequer.  The committee feels that the pending Direct Tax Code Bill would result in significant losses and should be reviewed. To boost income from indirect taxes – the tax on goods and services – the committee wants the proposed Goods and Service Tax regime to be implemented as soon as possible.

Figure 3 (source: RBI)

 

  Increasing disinvestment, the process of selling government stake in public enterprises, is another proposal to boost receipts. India has failed to meet the disinvestment estimate set out in the Budget in the last two years (Figure 4).  The committee believes introducing new channels [1.  The committee suggests introducing a ‘call option model’. This is a mechanism allowing  the government to offer for sale multiple securities over a period of time till disinvestment targets are achieved.  Investors would have the option to purchase securities at the cost of a premium.  They also propose introducing ‘exchange traded funds’ which would comprise all listed securities of Central Public Sector Enterprises and would provide investors with the benefits of diversification, low cost access and flexibility.] for disinvestment would ensure that disinvestment receipts would meet this year’s target of Rs 30,000 crore.

Figure 4 (source: Union Budget documents, PRS)

 

  Taken together, these policy changes, the committee believe would significantly improve India’s fiscal health and boost growth.  Their final projections for 2012-13, in both a reform and no reform scenario, and the medium term (2013-14 and 2014-15) are presented in the table below: [table id=2 /]  


By Rohit & Anirudh A modified 'Modernization of State Police Forces' scheme was started by the central government in 2000-01. One of the objectives was to help police forces in meeting the emerging challenges to internal security in the form of terrorism, naxalism etc. The scheme aims to modernize police forces in terms of:

  • Mobility (including purchase of bullet proof and mine proof vehicles)
  • Weaponry
  • Communication Systems
  • Training
  • Forensic Science Laboratory/ Finger Printing Bureau
  • Equipments
  • Buildings

Under this scheme, States have been clubbed into different categories and Centre-State cost sharing is category specific. Since 2005-06, States have been categorized as category ‘A’ and ‘B’ with 100% and 75% Central funding respectively. All the North Eastern States, namely Arunachal Pradesh, Assam, Manipur, Meghalaya, Mizoram, Nagaland, Tripura and Sikkim have been placed in category ‘A’ and thus, are entitled to receive 100% Central assistance for implementation of their annual approved plans. Recently, CAG decided to evaluate the working of the scheme and commissioned ‘performance audit’ reviews covering select general category and special category States. Each review covers a contiguous five year period between 2000 and 2007, but varies across selected states. For the periods under review, each state had a plan outlay (the total amount proposed to be spent in modernizing the state's police forces). However, in most cases, the actual release of funds fell significantly short of this outlay - in some cases the Centre did not contribute its share, in others the States lagged behind. For instance, in the case of Bihar, the Centre released only 56% of its share; while in the case of Rajasthan and West Bengal, the States did not release any funds at all. The graph below shows the actual releases by the Centre and the States (as percentages of their share in the proposed outlays): Further, even the funds that were released were not fully utilized. Thus, the amount finally spent fell significantly short of the initial proposal. The graph below shows the actual expenditure by State: Following are some of the other main findings from the CAG report:

Table 1: Summary of main findings in the CAG audit for different states for Modernisation of State Police Forces

Purpose for which money was sanctioned

Summary of CAG Findings

Planning

(Every state has to propose an Annual Action Plan every year. The plan is approved by the Ministry of Home Affairs and money is released as per the plan.)

§ Submissions by the states to the MHA were delayed.

§ There were also delays in the clearance granted by the MHA.

§ In various states such as,

a) Andhra Pradesh – the government spent money on works not covered by the Annual Action Plan.

b) Bihar – Persistent delays in preparation of the Plan by the state police.

c) West Bengal – the plans drawn up by the state did not include items covered under the scheme.

Mobility

§ Overall shortage of vehicles was observed. Most of the new vehicles replaced the old ones.

§ The police response time was too long in some states.

§ To give examples from some states:

a) Andhra Pradesh – 58 percent of vehicles procured were utilised for replacing old vehicles.

b) Bihar – the shortage of vehicles was 43 percent.

c) Uttar Pradesh – 2400 vehicles were procured against a shortage of nearly 10,000 vehicles.

Residential and non-residential buildings

§ There were considerable delays in construction of buildings in most states. Consequently, police forces’ own security was in jeopardy.

§ In states such as:

a) Andhra Pradesh – 53 percent of staff quarters and 43 percent of official buildings were not completed (2007).

b) Bihar – The total requirement of housing was nearly 60,000. Only six percent of this were included in the Plan.

c) Jharkhand – District Control rooms remained non-functional because of shortage of manpower.

Weapons

§ Police force in states continue to depend on outdated weapons.

§ Shortages of weapons also happened as acquisition from ordnance factories was very slow.

§ The weapons that were procured were mostly kept in the district headquarters.

§ In some states such as,

a) Bihar – AK-47s were kept at the disposal of bodyguards of VIPs.

b) West Bengal – Adequate weapons were not supplied to extremist prone police stations.

Communication

§ Police Telecommunication Networks were not set up successfully in some states. In others, network was functional only up to the district level.

§ Shortages of various communication equipments were also observed.

§ In some states such as,

a) Bihar - The Police Telecommunication Network system (costing Rs. 4.96 crore) remained non-functional due to non-construction of tower.

b) Maharashtra – Of the 850 purchased Remote Station Units, 452 were lying in stores.

Forensic Science Laboratory/ Finger Printing Bureau

§ In most States the Forensic Science Laboratories lacked adequate infrastructure.

§ In the absence of automatic finger print identification systems, investigation was being done manually in some States.

§ In some states such as,

a) Maharashtra - There were significant delays in receipt and installation. There was also shortage (284 vacant posts) of technical manpower.

b) West Bengal - Performance of the Forensic Science Laboratory was poor and in some cases, the delay in issue of investigation reports was as high as 45 months.

Training

§ It was observed that the percentage of police personnel trained was very low.

§ Training infrastructure was also inadequate.

§ In some states such as,

a) Bihar - Only 10 per cent of total force was trained.

b) West Bengal - Live training was not imparted for handling useful weapons and this severely affected the performance of police forces.

Sources: CAG Compendium of Performance Audit Reviews on Modernisation of Police Force; PRS.

Note: The audit has been done broadly from 2000 to 2007. Consequently, the period of audit for different states may vary.

Table 1: Summary of main findings in the CAG audit for different states for Modernisation of State Police Forces

Purpose for which money was sanctioned

Summary of CAG Findings

Planning

(Every state has to propose an Annual Action Plan every year. The plan is approved by the Ministry of Home Affairs and money is released as per the plan.)

§ Submissions by the states to the Ministry of Home Affairs (MHA) were delayed.

§ There were also delays in the clearance granted by the MHA.

§ In various states such as,

a) Andhra Pradesh – the government spent Rs 32 crore on works not covered by the Annual Action Plan.

b) Bihar – Persistent delays in preparation of the Plan by the state police.

c) West Bengal – the plans drawn up by the state did not include items covered under the scheme.

Mobility

§ Overall shortage of vehicles was observed. Most of the new vehicles replaced the old ones, and no additions were made.

§ The police response time was too long in some states.

§ To give examples from some states:

a) Andhra Pradesh – 58 percent of vehicles procured were utilised for replacing old vehicles.

b) Bihar – the shortage of vehicles was 43 percent.

c) Uttar Pradesh – 2400 vehicles were procured against a shortage of nearly 10,000 vehicles. 203 ambassador cars were procured, though only 55 were approved by the MHA.

Residential and non-residential buildings

§ There were considerable delays in construction of buildings in most states. Consequently, police forces’ own security was in jeopardy. Satisfaction levels with the housing provided were also very low.

§ In states such as:

a) Andhra Pradesh – 53 percent of staff quarters and 43 percent of official buildings were not completed (2007).

b) Bihar – The total requirement of housing was nearly 60,000. Only six percent of this were included in the Plan, and only 1045 units were completed by 2006.

c) Jharkhand – District Control rooms remained non-functional even after spending Rs 2 crore because of shortage of manpower.

Weapons

§ It was observed that the police force in states continue to depend on outdated weapons.

§ Shortages of weapons also happened as acquisition from ordnance factories was very slow.

§ The weapons that were procured were mostly kept in the district headquarters.

§ In some states such as,

a) Bihar – AK-47s were kept at the disposal of bodyguards of VIPs.

b) West Bengal – Adequate weapons were not supplied to extremist prone police stations.

Communication

§ Police Telecommunication Networks were not set up successfully in some states. In others, network was functional only up to the district level.

§ Shortages of various communication equipments were also observed.

§ In some states such as,

a) Bihar - The Police Telecommunication Network system (costing Rs. 4.96 crore) remained non-functional due to non-construction of tower.

b) Maharashtra – Of the 850 purchased Remote Station Units, 452 were lying in stores.

Forensic Science Laboratory/ Finger Printing Bureau

§ In most States the Forensic Science Laboratories lacked adequate infrastructure.

§ In the absence of automatic finger print identification systems, investigation was being done manually in some States.

§ In some states such as,

a) Maharashtra - There were significant delays in receipt and installation. There was also shortage (284 vacant posts) of technical manpower.

b) West Bengal - Performance of the Forensic Science Laboratory was poor and in some cases, the delay in issue of investigation reports was as high as 45 months.

Training

§ It was observed that the percentage of police personnel trained was very low.

§ Training infrastructure was also inadequate.

§ In some states such as,

a) Bihar - Only 10 per cent of total force was trained.

b) West Bengal - Live training was not imparted for handling useful weapons and this severely affected the performance of police forces.

Sources: CAG Compendium of Performance Audit Reviews on Modernisation of Police Force; PRS.

Note: The audit has been done broadly from 2000 to 2007. Consequently, the period of audit for different states may vary.