The Saansad Adarsh Gram Yojana was launched last week, for the development of model villages.  Under the Yojana, Members of Parliament (MPs) will be responsible for developing the socio-economic and physical infrastructure of three villages each by 2019, and a total of eight villages each by 2024.

The first Adarsh Gram must be developed by 2016, and two more by 2019.  From 2019 to 2024, five more Adarsh Grams must be developed by each MP, one each year.  This implies that a total of 6,433 Adarsh Grams, of the 2,65,000 gram panchayats, will be created by 2024. Key features of the Yojana are outlined below.

Objectives

Key objectives of the Yojana include:

  1. The development of model villages, called Adarsh Grams, through the implementation of existing schemes, and certain new initiatives to be designed for the local context, which may vary from village to village.
  2. Creating models of local development which can be replicated in other villages.

Identification of villages

MPs can select any gram panchayat, other than their own village or that of their spouse, to be developed as an Adarsh Gram.  The village must have a population of 3000-5000 people if it is located in the plains, or 1000-3000 people if located in hilly areas.

Lok Sabha MPs can choose a village from their constituency, and Rajya Sabha MPs from the state from which they are elected.  Nominated members can choose a village from any district of the country.  MPs which represent urban constituencies can identify a village from a neighbouring rural constituency.

Funding

No new funds have been allocated for the Yojana.  Resources may be raised through:

  1. Funds from existing schemes, such as the Indira Awas Yojana, Pradhan Mantri Gram Sadak Yojana, Mahatma Gandhi National Rural Employment Guarantee Scheme, and Backward Regions Grant Fund, etc.,
  2. The Member of Parliament Local Area Development Scheme (MPLADS),
  3. The gram panchayat’s own revenue,
  4. Central and State Finance Commission Grants, and
  5. Corporate Social Responsibility funds.

Implementation

A Village Development Plan must be created for each Adarsh Gram.  While each village will develop a list of activities to be carried out, based on its own resources and requirements, possible activities have been listed in the guidelines for the scheme.  For example, Adarsh Grams can work towards providing universal access to basic healthcare facilities, promoting diversified livelihoods through agriculture related livelihoods and skill development, providing pension for all eligible families, housing for all, and promoting social forestry.

The table below outlines key functionaries at the national, state, district, and village level and their responsibilities.

Table 1: Roles and responsibilities of key functionaries

Level Functionary Key roles and responsibilities
National Member of Parliament
  • Identify the Adarsh Gram
  • Facilitate the planning process
  • Mobilise additional funds
  • Monitor the scheme
  Two committees, headed by the Minister of Rural Development, and Secretary, Rural Development, respectively.*
  • Monitor the process of identification and planning
  • Review the implementation of the scheme
  • Identify bottlenecks in the scheme
  • Issue operational guidelines
  • Indicate specific resource support which each Ministry can provide
State A committee headed by the Chief Secretary
  • Supplement central guidelines for the scheme
  • Review Village Development Plans
  • Review implementation
  • Outline monitoring mechanisms
  • Design a grievance redressal mechanism for the scheme
District District Collector
  • Conduct the baseline survey
  • Facilitate the preparation of the Village Development Plan
  • Converge relevant schemes
  • Ensure grievance redressal
  • Monthly progress review of the scheme
Village Gram Panchayat and functionaries of schemes (at various levels)
  • Implement of the scheme
  • Identify common needs of the village
  • Leverage resources from various programmes
  • Ensure participation in the scheme

Note: *These committees will include members from other Ministries.

Sources: Saansad Adarsh Gram Yojana Guidelines, Ministry of Rural Development; PRS

Monitoring

A web based monitoring system will be established to enable the MP and other stakeholders to monitor the scheme.  Outputs relating to physical and financial targets will be measured each quarter.  A mid-term evaluation and post-project evaluation will be conducted through an independent agency.

More information on the scheme is available in the guidelines for the scheme, here.

On November 28, 2012, the Comptroller and Auditor General submitted its report on the implementation of the Jawaharlal Nehru National Urban Renewal Mission (JNNURM).  According to the report most of the projects initiated under JNNURM have not been completed.  For instance with respect to urban infrastructure projects, only 231 projects out of the 1298 sanctioned projects have been completed.  Similarly, with respect to housing projects, only 22 of the 1517 projects have been completed.  Some of the other key recommendations of the report are:

  •  Some of the reasons for the delay in completing the projects include: (i) delay in acquiring land; (ii) deficiency in preparation of projects; and (iii) non-identification of beneficiaries which increased the risk of ineligible beneficiaries getting the benefits.
  •  A total allocation of Rs 66,084 crore had been made by the Planning Commission.  However, against this total allocation, the central government had made an allocation of only Rs 37,070 out of which until March 30, 2011 only Rs 32,934 had been released.
  • There was a delay in releasing these funds to the states.  A large portion of the funds was released only in the last quarter and more particularly in March.
  • The JNNURM guidelines were deficient as they did not provide adequate guidance to the states on the method of parking the funds and utilization of interest.

The need and objectives of JNNURM According to the 2011 census India’s urban population has increased from 286 million in 2001 to 377 million in 2011 .  With the increase in urban population, there is a requirement to improve the urban infrastructure and improve the service delivery mechanisms.  With these specific objectives in mind, the central government launched the Jawaharlal Nehru National Urban Renewal Mission 2005-2006.  The aim of the Mission is to encourage reforms and fast track planned development of identified cities (such as cities with a population of more than 1 million as per the 2001 census).  JNNURM has two main components namely : (i) Urban Infrastructure and Governance  and (ii) Urban Infrastructure Development for Small and Medium Towns. The duration of JNNURM was from 2005-06 to 2011-12. However, as the projects have not been completed the Government has extended its duration until March 2014. Funds for JNNURM The funds for JNNURM are provided through the Additional Central Assistance.  This implies that the funds are provided as grants to the states directly from the centre.   In the 2012 Union Budget, the central government has allocated Rs 12,522 crore for JNNURM. This represents around 10 % of the total central assistance through the different schemes to states and union territories in 2012-13. As on June 30 2012, 554 projects at a total cost of Rs 62,253 crore have been sanctioned under the Urban Infrastructure and Governance sub-mission of JNNURM.   The table below shows the status of the sanctioned JNNURM  projects in the different states. State wise status of the projects under JNNURM                 (as on August 6, 2012)

Name of State Total Allocation (Rs Lakh) Number of sanctioned projects Completed Projects
Andhra Pradesh 2,11,845 52 18
Arunachal Pradesh 10,740 3 NA
Assam 27,320 2 NA
Bihar 59,241 8 NA
Chandigarh 27,087 3 NA
Chattisgarh 24,803 1 NA
Delhi 2,82,318 23 4
Goa 12,094 2 NA
Gujarat 2,57,881 72 40
Haryana 32,332 4 NA
Himachal Pradesh 13,066 5 NA
Jammu & Kashmir 48,836 5 NA
Jharkhand 94,120 5 NA
Karnataka 1,52,459 47 22
Kerala 67,476 11 NA
Madhya Pradesh 1,32,850 23 7
Maharashtra 5,50,555 80 21
Manipur 15,287 3 NA
Meghalaya 15,668 2 NA
Mizoram 14,822 4 NA
Nagaland 11,628 3 NA
Orissa 32,235 5 NA
Punjab 70,775 6 1
Puducherry 20,680 2 NA
Rajasthan 74,869 13 2
Sikkim 10,613 2 NA
Tamil Nadu 2,25,066 48 12
Tripura 14,018 2 NA
Uttar Pradesh 2,76,941 33 4
Uttarakhand 40,534 14 NA
West Bengal 3,21,840 69 15

Source: Jawaharlal Nehru National Urban Renewal Mission; PRS.

  • Gujarat at 55.55% has the highest number of completed projects, while Uttar Pradesh at 12.24% has the lowest number of completed projects.
  • Out of the larger states, Delhi and Maharashtra at 17% and 26% have a comparatively low rate of completed projects.
  • Maharashtra has the highest number of sanctioned projects, while the North Eastern states, Chattisgarh and Puducherry have the lowest number of sanctioned projects.