On March 10, Lok Sabha passed a Bill to amend the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013.  The Bill is now pending in Rajya Sabha.  This blog briefly outlines the context and the major legislative changes to the land acquisition law. I. Context Land acquisition, unlike the purchase of land, is the forcible take-over of privately owned land by the government.  Land is acquired for projects which serve a ‘public purpose’.  These include government projects, public-private partnership projects, and private projects.  Currently, what qualifies as ‘public purpose’ has been defined to include defence projects, infrastructure projects, and projects related to housing for the poor, among others. Till 2014, the Land Acquisition Act, 1894 regulated the process of land acquisition.  While the 1894 Act provided compensation to land owners, it did not provide for rehabilitation and resettlement (R&R) to displaced families.  These were some of the reasons provided by the government to justify the need for a new legislation to regulate the process of land acquisition.  Additionally, the Supreme Court had also pointed out issues with determination of fair compensation, and what constitutes public purpose, etc., in the 1894 Act.  To this end, the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 was passed by Parliament, in 2013. II. Current legislative framework for land acquisition The 2013 Act brought in several changes to the process of land acquisition in the country.   Firstly, it increased the compensation provided to land owners, from 1.3 times the price of land to 2 times the price of land in urban areas, and 2-4 times the price of land in rural areas.  Secondly, unlike the earlier Act which did not provide rehabilitation and resettlement, the 2013 Act provided R&R to land owners as well as those families which did not own land, but were dependent on the land for their livelihood.  The Act permits states to provide higher compensation and R&R. Thirdly, unlike the previous Act, it mandated that a Social Impact Assessment be conducted for all projects, except those for which land was required urgently.  An SIA assesses certain aspects of the acquisition such as whether the project serves a public purpose, whether the minimum area that is required is being acquired, and the social impact of the acquisition.  Fourthly, it also mandated that the consent of 80% of land owners be obtained for private projects, and the consent of 70% of land owners be obtained for public-private partnership projects.  However, consent of land owners is not required for government projects.   The 2013 Act also made certain other changes to the process of land acquisition, including prohibiting the acquisition of irrigated multi-cropped land, except in certain cases where the limit may be specified by the government. III. Promulgation of an Ordinance to amend the 2013 Act In addition to the 2013 Act, there are certain other laws which govern land acquisition in particular sectors, such as the National Highways Act, 1956 and the Railways Act, 1989.  The 2013 Act required that the compensation and R&R provisions of 13 such laws be brought in consonance with it, within a year of its enactment, (that is, by January 1, 2015) through a notification.  Since this was not done by the required date, the government issued an Ordinance (as Parliament was not in session) to extend the compensation and R&R provisions of the 2013 Act to these 13 laws.  However, the Ordinance also made other changes to the 2013 Act. The Ordinance was promulgated on December 31, 2014 and will lapse on April 5, 2015 if not passed as a law by Parliament.  Thus, the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (Amendment) Bill, 2015 has been introduced in Parliament to replace the Ordinance.  The Bill has been passed by Lok Sabha, with certain changes, and is pending in Rajya Sabha.  The next section outlines the major changes the Bill (as passed by Lok Sabha) proposes to make to 2013 Act. IV. Changes proposed by the 2015 Bill to the 2013 Act Some of the major changes proposed by the 2015 Bill (as passed by Lok Sabha) relate to provisions such as obtaining the consent of land owners; conducting an SIA; return of unutilised land; inclusion of private entities; and commission of offences by the government. Certain exemptions for five categories of projects: As mentioned above, the 2013 Act requires that the consent of 80% of land owners is obtained when land is acquired for private projects, and the consent of 70% of land owners is obtained when land is acquired for public-private partnership projects.  The Bill exempts five categories of projects from this provision of the 2013 Act.  These five categories are: (i) defence, (ii) rural infrastructure, (iii) affordable housing, (iv) industrial corridors (set up by the government/government undertakings, up to 1 km on either side of the road/railway), and (v) infrastructure projects. The Bill also allows the government to exempt these five categories of projects from: (i) the requirement of a Social Impact Assessment, and (ii) the limits that apply for acquisition of irrigated multi-cropped land, through issuing a notification.  Before issuing this notification, the government must ensure that the extent of land being acquired is in keeping with the minimum land required for such a project. The government has stated that these exemptions are being made in order to expedite the process of land acquisition in these specific areas.  However, the opponents of the Bill have pointed out that these five exempted categories could cover a majority of projects for which land can be acquired, and consent and SIA will not apply for these projects. Return of unutilised land: Secondly, the Bill changes the time period after which unutilised, acquired land must be returned.  The 2013 Act states that if land acquired under it remains unutilised for five years, it must be returned to the original owners or the land bank.  The Bill changes this to state that the period after which unutilised land will need to be returned will be the later of: (i) five years, or (ii) any period specified at the time of setting up the project. Acquisition of land for private entities: Under the 2013 Act, as mentioned above, land can be acquired for the government, a public-private partnership, or a private company, if the acquisition serves a public purpose.  The third major change the Bill seeks to make is that it changes the term ‘private company’ to ‘private entity’.  This implies that land may now be acquired for a proprietorship, partnership, corporation, non-profit organisation, or other entity, in addition to a private company, if the project serves a public purpose. Offences by the government: Fourthly, under the 2013 Act, if an offence is committed by a government department, the head of the department will be held guilty unless he can show that he had exercised due diligence to prevent the commission of the offence.  The Bill removes this section.  It adds a provision to state that if an offence is committed by a government employee, he can be prosecuted only with the prior sanction of the government. Acquisition of land for private hospitals and educational institutions: While the 2013 Act excluded acquisition of land for private hospitals and private educational institutions, the Bill sought to include these two within its scope.  However, the Lok Sabha removed this provision of the Bill.  Thus, in its present form, the Bill does not include the acquisition of land for private hospitals and private educational institutions. Other changes proposed in Lok Sabha: In addition to removing social infrastructure from one of the five exempted categories of projects, clarifying the definition of industrial corridors, and removing the provision related to acquisition for private hospitals and private educational institutions, the Lok Sabha made a few other changes to the Bill, prior to passing it.  These include: (i) employment must be provided to ‘one member of an affected family of farm labour’ as a part of the R&R award, in addition to the current provision which specifies that one member of an affected family must be provided employment as a part of R&R; (ii) hearings of the Land Acquisition, Rehabilitation and Resettlement Authority to address grievances related to compensation be held in the district where land is being acquired; and (iii) a survey of wasteland must be conducted and records of these land must be maintained. For more details on the 2015 Bill, see the PRS Bill page, here. A version of this blog appeared on rediff.com on February 27, 2015. 

The government's acquisition of land for projects has been facing protests across the country, the violence in Uttar Pradesh being only the latest. What is Land Acquisition? Land acquisition is the process by which the government forcibly acquires private property for public purpose without the consent of the land-owner. It is thus different from a land purchase, in which the sale is made by a willing seller. How is this process governed? Land Acquisition is governed by the Land Acquisition Act, 1894.  The government has to follow a process of declaring the land to be acquired, notify the interested persons, and acquire the land after paying due compensation. Various state legislatures have also passed Acts that detail various aspects of the acquisition process. Land is a state subject.  Why is Parliament passing a law? Though land is a state subject, "acquisition and requisitioning of property" is in the concurrent list. Both Parliament and state legislatures can make laws on this subject. Is there a new Act being proposed? The government had introduced a Bill to amend this Act in 2007. That Bill lapsed in 2009 at the time of the general elections. The government has stated its intent to re-introduce a similar Bill, but has not yet done so. What are the major changes being proposed? There are significant changes proposed in the 2007 Bill with regard to (a) the purpose for which land may be acquired; (b) the amount of compensation to be paid; (c) the process of acquisition; (d) use of the land acquired; and (e) dispute settlement mechanisms. We explain these briefly below. Purpose: Currently, land may be acquired for a range of uses such as village sites, town or rural planning, residential purposes for poor or displaced persons, planned development (education, housing, health, slum clearance), and for state corporations. Land may also be acquired for use by private companies for the above purposes or if the work "is likely to prove useful to the public". The 2007 Bill had a narrower list: (a) for strategic naval, military or air force purposes; (b) for public infrastructure projects; and (c) for any purpose useful to the general public if 70% of the land has been purchased from willing sellers through the free market. Compensation: The current Act requires market value to be paid for the land and any other property on it (buildings, trees, irrigation work etc) as well as expenses for compelling the person change place of residence or business. It explicitly prohibits taking into account the intended use of land while computing market value. The 2007 Bill requires payment of the highest of three items: the minimum value specified for stamp duty, the average of the top 50 per cent by price of land sale in the vicinity, and the average of the top 50 pc of the land purchased for the project from willing sellers. For computing recent land sale, the intended land use is to be used. Thus, agricultural land being acquired for an industrial project will be paid the price of industrial land. Process of acquisition: Several changes are proposed, including the requirement of a social impact assessment. Any project that displaces more than 400 families (200 in hilly, tribal and desert areas) will require an SIA before the acquisition is approved. Use of land acquired: The 2007 Bill requires the land acquired to be used for that purpose within five years. If this condition is not met, the land reverts to the government (it is not returned to the original land owners). If any acquired land is transferred to another entity, 80 pc of the capital gains has to be shared with the original land-owners and their legal heirs. Dispute Settlement: Currently, all disputes are resolved by civil courts, which results in delays. The 2007 Bill sets up Land Acquisition Compensation Dispute Resolution Authority at the state and national levels. These authorities will have the power of civil courts, and will adjudicate disputes related to compensation claims. Does the proposed Bill address the major issues? The Bill narrows the uses for which land may be acquired. It also changes the compensation due and links that to the market price for which land is to be used. There could be significant changes in acquisition for use by private industry. Firstly, they would have to purchase at least 70 pc of the required land from willing sellers (presumably, at fair market price). Second, the compensation amount for the remaining (upto 30 pc of land) could be significantly higher than the current method. This would be at a premium to the average paid to the willing sellers, and it would be based on intended industrial or commercial use which usually commands a higher price than agricultural land. However, the effect on acquisition for projects such as highways and railways will not be significant, as there is no benchmark for price determination for such use. This article appeared in Rediff News on May 12, 2011 and can be accessed here.