On March 10, Lok Sabha passed a Bill to amend the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013.  The Bill is now pending in Rajya Sabha.  This blog briefly outlines the context and the major legislative changes to the land acquisition law. I. Context Land acquisition, unlike the purchase of land, is the forcible take-over of privately owned land by the government.  Land is acquired for projects which serve a ‘public purpose’.  These include government projects, public-private partnership projects, and private projects.  Currently, what qualifies as ‘public purpose’ has been defined to include defence projects, infrastructure projects, and projects related to housing for the poor, among others. Till 2014, the Land Acquisition Act, 1894 regulated the process of land acquisition.  While the 1894 Act provided compensation to land owners, it did not provide for rehabilitation and resettlement (R&R) to displaced families.  These were some of the reasons provided by the government to justify the need for a new legislation to regulate the process of land acquisition.  Additionally, the Supreme Court had also pointed out issues with determination of fair compensation, and what constitutes public purpose, etc., in the 1894 Act.  To this end, the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013 was passed by Parliament, in 2013. II. Current legislative framework for land acquisition The 2013 Act brought in several changes to the process of land acquisition in the country.   Firstly, it increased the compensation provided to land owners, from 1.3 times the price of land to 2 times the price of land in urban areas, and 2-4 times the price of land in rural areas.  Secondly, unlike the earlier Act which did not provide rehabilitation and resettlement, the 2013 Act provided R&R to land owners as well as those families which did not own land, but were dependent on the land for their livelihood.  The Act permits states to provide higher compensation and R&R. Thirdly, unlike the previous Act, it mandated that a Social Impact Assessment be conducted for all projects, except those for which land was required urgently.  An SIA assesses certain aspects of the acquisition such as whether the project serves a public purpose, whether the minimum area that is required is being acquired, and the social impact of the acquisition.  Fourthly, it also mandated that the consent of 80% of land owners be obtained for private projects, and the consent of 70% of land owners be obtained for public-private partnership projects.  However, consent of land owners is not required for government projects.   The 2013 Act also made certain other changes to the process of land acquisition, including prohibiting the acquisition of irrigated multi-cropped land, except in certain cases where the limit may be specified by the government. III. Promulgation of an Ordinance to amend the 2013 Act In addition to the 2013 Act, there are certain other laws which govern land acquisition in particular sectors, such as the National Highways Act, 1956 and the Railways Act, 1989.  The 2013 Act required that the compensation and R&R provisions of 13 such laws be brought in consonance with it, within a year of its enactment, (that is, by January 1, 2015) through a notification.  Since this was not done by the required date, the government issued an Ordinance (as Parliament was not in session) to extend the compensation and R&R provisions of the 2013 Act to these 13 laws.  However, the Ordinance also made other changes to the 2013 Act. The Ordinance was promulgated on December 31, 2014 and will lapse on April 5, 2015 if not passed as a law by Parliament.  Thus, the Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (Amendment) Bill, 2015 has been introduced in Parliament to replace the Ordinance.  The Bill has been passed by Lok Sabha, with certain changes, and is pending in Rajya Sabha.  The next section outlines the major changes the Bill (as passed by Lok Sabha) proposes to make to 2013 Act. IV. Changes proposed by the 2015 Bill to the 2013 Act Some of the major changes proposed by the 2015 Bill (as passed by Lok Sabha) relate to provisions such as obtaining the consent of land owners; conducting an SIA; return of unutilised land; inclusion of private entities; and commission of offences by the government. Certain exemptions for five categories of projects: As mentioned above, the 2013 Act requires that the consent of 80% of land owners is obtained when land is acquired for private projects, and the consent of 70% of land owners is obtained when land is acquired for public-private partnership projects.  The Bill exempts five categories of projects from this provision of the 2013 Act.  These five categories are: (i) defence, (ii) rural infrastructure, (iii) affordable housing, (iv) industrial corridors (set up by the government/government undertakings, up to 1 km on either side of the road/railway), and (v) infrastructure projects. The Bill also allows the government to exempt these five categories of projects from: (i) the requirement of a Social Impact Assessment, and (ii) the limits that apply for acquisition of irrigated multi-cropped land, through issuing a notification.  Before issuing this notification, the government must ensure that the extent of land being acquired is in keeping with the minimum land required for such a project. The government has stated that these exemptions are being made in order to expedite the process of land acquisition in these specific areas.  However, the opponents of the Bill have pointed out that these five exempted categories could cover a majority of projects for which land can be acquired, and consent and SIA will not apply for these projects. Return of unutilised land: Secondly, the Bill changes the time period after which unutilised, acquired land must be returned.  The 2013 Act states that if land acquired under it remains unutilised for five years, it must be returned to the original owners or the land bank.  The Bill changes this to state that the period after which unutilised land will need to be returned will be the later of: (i) five years, or (ii) any period specified at the time of setting up the project. Acquisition of land for private entities: Under the 2013 Act, as mentioned above, land can be acquired for the government, a public-private partnership, or a private company, if the acquisition serves a public purpose.  The third major change the Bill seeks to make is that it changes the term ‘private company’ to ‘private entity’.  This implies that land may now be acquired for a proprietorship, partnership, corporation, non-profit organisation, or other entity, in addition to a private company, if the project serves a public purpose. Offences by the government: Fourthly, under the 2013 Act, if an offence is committed by a government department, the head of the department will be held guilty unless he can show that he had exercised due diligence to prevent the commission of the offence.  The Bill removes this section.  It adds a provision to state that if an offence is committed by a government employee, he can be prosecuted only with the prior sanction of the government. Acquisition of land for private hospitals and educational institutions: While the 2013 Act excluded acquisition of land for private hospitals and private educational institutions, the Bill sought to include these two within its scope.  However, the Lok Sabha removed this provision of the Bill.  Thus, in its present form, the Bill does not include the acquisition of land for private hospitals and private educational institutions. Other changes proposed in Lok Sabha: In addition to removing social infrastructure from one of the five exempted categories of projects, clarifying the definition of industrial corridors, and removing the provision related to acquisition for private hospitals and private educational institutions, the Lok Sabha made a few other changes to the Bill, prior to passing it.  These include: (i) employment must be provided to ‘one member of an affected family of farm labour’ as a part of the R&R award, in addition to the current provision which specifies that one member of an affected family must be provided employment as a part of R&R; (ii) hearings of the Land Acquisition, Rehabilitation and Resettlement Authority to address grievances related to compensation be held in the district where land is being acquired; and (iii) a survey of wasteland must be conducted and records of these land must be maintained. For more details on the 2015 Bill, see the PRS Bill page, here. A version of this blog appeared on rediff.com on February 27, 2015. 

In law, the addition or deletion a single punctuation or a single word can have a major impact on the effect of that law.  One such example can be seen from the recommended changes in the Civil Liability for Nuclear Damage Bill, 2010 by Parliament’s Standing Committee. The Civil Liability for Nuclear Damage Bill, 2010 was introduced in the Lok Sabha on May 7, 2010.  The Bill was referred to the Parliamentary Committee on Science and Technology, Environment and Forests, which submitted its report on the Bill yesterday (August 18, 2010).  The Committee has made a number of recommendations regarding certain clauses in the Bill (See summary here).  One of these may have the effect of diluting the provision currently in the Bill.  The main recommendations pertain to:

  • Preventing the entry of private operators.
  • Allowing the government to increase the total liability for a nuclear incident by notification, but not decrease it.
  • Increasing the liability of the operator to Rs 1,500 crore from Rs 500 crore.
  • Increasing the time limit for claiming compensation to 20 years from 10 years.
  • Changing the provision giving operators a right of recourse against persons actually responsible for causing damage.

Clause 17 of the Bill which gives operators a right of recourse against those actually causing damage had been opposed as it was felt that it was not strong enough to hold suppliers liable in case the damage was caused by them.  Clause 17 gave a right of recourse under three conditions.  The exact clause is reproduced below: The operator of a nuclear installation shall have a right of recourse where — (a) such right is expressly provided for in a contract in writing; (b) the nuclear incident has resulted from the wilful act or gross negligence on the part of the supplier of the material, equipment or services, or of his employee; (c) the nuclear incident has resulted from the act of commission or omission of a person done with the intent to cause nuclear damage. Under this clause, a right of recourse exists when (a) there is a contract giving such a right, or (b) the supplier acts deliberately or in a grossly negligent manner to cause nuclear damage, or (c) a person causes nuclear damage with the intent to do so.  If any of the three cases can be proved by the operator, he has a right of recourse. The Committee has stated that “Clause 17(b) gives escape route to the suppliers of nuclear materials, equipments, services of his employees as their willful act or gross negligence would be difficult to establish in a civil nuclear compensation case.” It recommended that Clause 17(b) should be modified to cover consequences “of latent or patent defect, supply of sub-standard material, defective equipment or services or from the gross negligence on the part of the supplier of the material, equipment or service.” The Committee also recommended another change in Clause 17.  It recommended that clause 17(a) may end with “and”. This provision may dilute the right of recourse available to operators.  The modified clause 17 would read as: The operator of a nuclear installation shall have a right of recourse where — (a) such right is expressly provided for in a contract in writing; and, (b) the nuclear incident has resulted as a consequence of latent or patent defect, supply of sub-standard material, defective equipment or services or from the gross negligence on the part of the supplier of the material, equipment or services.; (c) the nuclear incident has resulted from the act of commission or omission of a person done with the intent to cause nuclear damage. This implies that for Clauses 17(b) or (c) to be applicable, the condition specified in clause 17(a) has to be compulsorily satisfied.  Two examples highlight the consequence of the recommended change in Clause 17(a) of the Bill:

  1. A person X deliberately commits sabotage in a nuclear plant and causes damage.  Under the Bill, the operator has recourse under Clause 17(c).  If the recommendation regarding clause 17 is accepted, the operator may also have to also prove the existence of a pre-existing contract with X in addition to clause 17(c).
  2. If a supplier supplies defective equipment, but does not have a contract in writing stating that he will be liable for damage caused by defective equipment, the operator may not have a right of recourse against the supplier under 17(b).

The effect of the changes recommended by the committee may thus dilute the provision as it exists in the Bill.  The table below compares the position in the Bill and the position as per the Standing Committee’s recommendations:

Right of recourse - The Bill gives operators a right to recourse under three conditions:  (a) if there is a clear contract; (b) if the damage is caused by someone with intent to cause damage; (c) against suppliers if damage is caused by their wilful act or negligence. In the Bill the three conditions are separated by a semi-colon.  The Committee recommended that the semi-colon in clause 17(a) should be replaced by “and”. This might imply that all three conditions mentioned need to exist for an operator to have recourse.
Right to recourse against suppliers exists in cases of “willful act or gross negligence on the part of the supplier”. (Clause 17) The Committee felt that the right of recourse against suppliers is vague.  It recommended that recourse against the supplier should be strengthened.  The supplier is liable if an incident has occurred due to (i) defects, or (ii) sub-standard material, or (iii) gross negligence of the supplier of the material, equipment or services. The variance with the Convention continues to exist.