Applications for LAMP Fellowship 2025-26 are now open. Apply here. The last date for submitting applications is December 21, 2024
One of the most politically contentious issues in recent times has been the government’s right to acquire land for ‘public purpose’. Increasingly, farmers are refusing to part with their land without adequate compensation, the most recent example being the agitation in Uttar Pradesh over the acquisition of land for the Yamuna Express Highway. Presently, land acquisition in India is governed by the Land Acquisition Act, an archaic law passed more than a century ago in 1894. According to the Act, the government has the right to acquire private land without the consent of the land owners if the land is acquired for a “public purpose” project (such as development of towns and village sites, building of schools, hospitals and housing and state run corporations). The land owners get only the current price value of the land as compensation. The key provision that has triggered most of the discontent is the one that allows the government to acquire land for private companies if it is for a “public purpose” project. This has led to conflict over issues of compensation, rehabilitation of displaced people and the type of land that is being acquired. The UPA government introduced the Land Acquisition (Amendment) Bill in conjunction with the Rehabilitation and Resettlement Bill on December 6, 2007 in the Lok Sabha and referred them to the Standing Committee on Rural Development for scrutiny. The Committee submitted its report on October 21, 2008 but the Bills lapsed at the end of the 14th Lok Sabha. The government is planning to introduce revised versions of the Bills. The following paragraphs discuss the lapsed Bills to give some idea of the government’s perspective on the issue while analysing the lacunae in the Bills. The Land Acquisition (Amendment) Bill, 2007 redefined “public purpose” to allow land acquisition only for defence purposes, infrastructure projects, or any project useful to the general public where 70% of the land had already been purchased from willing sellers through the free market. It prohibited land acquisition for companies unless they had already purchased 70% of the required land. The Bill also made it mandatory for the government to conduct a social impact assessment if land acquisition resulted in displacement of 400 families in the plains or 200 families in the hills or tribal areas. The compensation was to be extended to tribals and individuals with tenancy rights under state laws. The compensation was based on many factors such as market rates, the intended use of the land, and the value of standing crop. A Land Acquisition Compensation Disputes Settlement Authority was to be established to adjudicate disputes. The Rehabilitation and Resettlement Bill, 2007 sought to provide for benefits and compensation to people displaced by land acquisition or any other involuntary displacements. The Bill created project-specific authorities to formulate, implement and monitor the rehabilitation process. It also outlined minimum benefits for displaced families such as land, house, monetary compensation, skill training and preference for jobs. A grievance redressal system was also provided for. Although the Bills were a step in the right direction, many issues still remained unresolved. Since the Land Acquisition Bill barred the civil courts from entertaining any disputes related to land acquisition, it was unclear whether there was a mechanism by which a person could challenge the qualification of a project as “public purpose”. Unlike the Special Economic Zone Act, 2005, the Bill did not specify the type of land that could be acquired (such as waste and barren lands). The Bill made special provision for land taken in the case of ‘urgency’. However, it did not define the term urgency, which could lead to confusion and misuse of the term. The biggest loop-hole in the Rehabilitation and Resettlement Bill was the use of non-binding language. Take for example Clause 25, which stated that “The Government may, by notification, declare any area…as a resettlement area.” Furthermore, Clause 36(1) stated that land for land “shall be allotted…if Government land is available.” The government could effectively get away with not providing many of the benefits listed in the Bill. Also, most of the safeguards and benefits were limited to families affected by large-scale displacements (400 or more families in the plains and 200 or more families in the hills and tribal areas). The benefits for affected families in case of smaller scale displacements were not clearly spelt out. Lastly, the Bill stated that compensation to displaced families should be borne by the requiring body (body which needs the land for its projects). Who would bear the expenditure of rehabilitation in case of natural disasters remained ambiguous. If India is to attain economic prosperity, the government needs to strike a balance between the need for development and protecting the rights of people whose land is being acquired. Kaushiki Sanyal The article was published in Sahara Time (Issue dated September 4, 2010, page 36)
Recently, the central government launched the Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya).[i],[ii] The scheme seeks to ensure universal household electrification (in both rural and urban areas) by providing last mile connectivity. The scheme is expected to cover three crore households. Note that currently about four crore households are un-electrified. A rural electrification scheme has also been under implementation since 2005. In light of this, we discuss the current situation of, and key issues related to rural electrification in the country.
Regulatory and policy framework
Under the Electricity Act, 2003, the central and state governments have the joint responsibility of providing electricity to rural areas. The 2003 Act also mandates that the central government should, in consultation with the state governments, provide for a national policy on (i) stand-alone power systems for rural areas (systems that are not connected to the electricity grid), and (ii) electrification and local distribution in rural areas. Consequently, the Rural Electrification Policy was notified in August 2006.[iii]
The Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), launched in 2005, was the first scheme on rural electrification. In December 2014, Ministry of Power launched the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), which subsumed the RGGVY.[iv] Components of DDUGJY include: (i) separation of agricultural and non-agricultural electricity feeders to improve supply for consumers in rural areas, (ii) improving sub-transmission and distribution infrastructure in rural areas, and (iii) rural electrification by carrying forward targets specified under the RGGVY.
The total financial outlay for DDUGJY over the implementation period (until 2021-22) is Rs 82,300 crore which includes budgetary support of Rs 68,900 crore. The central government provides 60% of the project cost as grant, the state power distribution companies (discoms) raise 10% of the funds, and 30% is borrowed from financial institutions and banks.
Status of rural electrification
As of August 2017, about 1% of the villages in India remain un-electrified (3,146 villages). However, with regard to households, around 23% (4.1 crore households) are yet to be electrified. Table 1 at the end of this post shows the status of rural electrification across all states.
Issues with rural electrification
Definition of an electrified village
An electrified village is defined as one that has the following: (i) provision of basic infrastructure such as distribution transformers and lines in the inhabited locality, (ii) provision of electricity in public places like schools, panchayat office, health centers, dispensaries, and community centers, and (iii) at least 10% of the total number of households in the village are electrified.[iv]
Therefore, a village is considered to be electrified if 10% of the total number of households in the village have been electrified. This is apart from the basic infrastructure and electrification of certain public centers in the village. The Standing Committee on Energy (2013) had observed that according to this definition, a village would be called electrified even if up to 90% of households in it do not have an electricity connection.[v] It also noted that the infrastructure being provided under the scheme is highly inadequate, unreliable and unsustainable. The Committee recommended that the actual electrification requirement of villages must be assessed, and it should be ensured that the state discoms provide electricity to the remaining households in the village.
Supply of electricity
The Standing Committee had also noted that while the rural electrification scheme looks at creating infrastructure, the actual supply of electricity to households rests with the state discoms.[v] These discoms are already facing huge financial losses and hence are unable to supply electricity to the villages. Discoms continue to supply subsidised power to agricultural and residential consumers, resulting in revenue losses. Further, the average technical and commercial losses (theft and pilferage of electricity) (AT&C losses) are at around 25%. While the Ujjwal Discom Assurance Yojana (UDAY) has eased off some of the financial losses of the discoms, it remains to be seen whether discoms are able to reduce the cost-tariff gap and AT&C losses in the future.
It has been recommended that generation capacity should be augmented so that states can meet the additional demand under the rural electrification schemes. Further, the assistance to financially weaker states should be increased so that they can better implement the scheme.[v]
Electricity to below poverty line (BPL) households
Under the rural electrification scheme, the cost for providing free electricity connection per BPL household is Rs 3,000. It has been observed that this cost per household may be inadequate.[v] Due to the low cost, the quantity and the quality of work has been getting compromised leading to poor implementation of the scheme. It has been recommended that the Ministry should revisit the cost provided under the scheme.[v]
The new electrification scheme: Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya)
The new scheme, Saubhagya, seeks to ensure universal household electrification, that is, in both rural and urban areas. Under Saubhagya, beneficiaries will be identified using the Socio Economic and Caste Census (SECC) 2011 data. The identified poor households will get free electricity connections. Other households not covered under the SECC, will be provided electricity connections at a cost of Rs 500. This amount will be collected by the electricity distribution companies in 10 instalments.
The total outlay of the scheme will be Rs 16,320 crore, of which the central government will provide Rs 12,320 crore. The outlay for the rural households will be Rs 14,025 crore, of which the centre will provide Rs 10,588 crore. For urban households the outlay will be Rs 2,295 crore of which the centre will provide Rs. 1,733 crore.
The state discoms will execute the electrification works through contractors or other suitable agencies. Information technology (mobile apps, web portals) will be used to organise camps in villages to identify beneficiaries. In order to accelerate the process, applications for electricity connections will be completed on the spot.
So far the focus of electrification schemes has been on rural areas, where typically last mile connectivity has been difficult to provide. Saubhagya extends the ambit of electrification projects to urban areas as well. While DDUGJY has focused on the village as the principal unit to measure electrification, the new scheme shifts the targets to household electrification. While the target for ensuring electricity connection in each household will be a significant step towards ensuring 24×7 power, the question of continuous and quality supply to these households will still rest on the ability of the discoms to provide electricity. Further, while the scheme provides for free connections, the ability of these households to pay for the electricity they consume may be a concern.
Table 1: Status of rural electrification across states (as of August 2017)
[i] “PM launches Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 25, 2017.
[ii] “FAQs on Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 27, 2017.
[iii]. Rural Electrification Policy, Ministry of Power, August 23, 2006, http://powermin.nic.in/sites/default/files/uploads/RE%20Policy_1.pdf.
[iv]. “Office memorandum: Deendayal Upadhyaya Gram Jyoti Yojana”, Ministry of Power, December 3, 2014, http://powermin.nic.in/rural_electrification/pdf/Deendayal_Upadhyaya_Gram_Jyoti_Yojana.pdf.
[v]. “41st Report: Implementation of Rajiv Gandhi Grameen Vidyutikaran Yojana”, Standing Committee on Energy, December 13, 2013, http://164.100.47.134/lsscommittee/Energy/15_Energy_41.pdf.