Applications for the LAMP Fellowship 2025-26 will open soon. Sign up here to be notified when the dates are announced.

Authored by Anil Nair and CV Madhukar PRS just concluded a workshop for MLAs from 50+ from more than a dozen states.  What an AMAZING experience this was, even though this is the sixth such workshop we have held in this past year! This three day workshop on 'Mastering the Budget' was designed to help MLAs understand how to work with budget documents and numbers, find trends, understand the most critical macro numbers to track, etc. The second day of the workshop was tailored to reflect on the big thematic issues that have an impact on state finances. The Fiscal Responsibility and Budget Management Act, the Goods and Services Tax, the pattern of quantum of funds flow from the Centre to the state and local governments, the 13th Finance Commission, etc. The final day was devoted to doing an inter-state comparison of states on important budget parameters, and gleaning lessons from them. The idea for this budget workshop germinated at a previous workshop held at IIM Bangalore. The participating MLAs requested PRS to organise a special session on 'Mastering the Budget'. So this workshop was being organised as a result of their feedback. The choice of location was easy -- this was held at the National Institute for Public Finance and Policy in Delhi, which is amongst India's foremost institutions working on state budgets and public finance issues. Invitations were sent out to MLAs in several states. Responses started coming in within a few days, with about 70 confirmations. But there is always an uncertainty on the participation until the very last minute because elected politicians have immense demands on their time, at least some of which are unpredictable. So it was heartening to see that more than 50 MLAs came to the workshop representing 15 states -- Bihar, Rajasthan, Odisha, Uttar Pradesh, Assam, Kerala, West Bengal, Andhra Pradesh, Meghalaya, Tamil Nadu, Madhya Pradesh, Himachal Pradesh, Gujarat, Haryana, Manipur. The participants ranged from first time MLAs (about 50%), to a sitting Minister, a sitting Speaker, former Ministers, and senior leaders of political parties from some states. But the best part about the interaction in this workshop was that even on seemingly complex issues being discussed in the classroom, the MLAs were not mere recipients of 'gyan' that was being dished out. They had important questions to raise, and well articulated points of disagreement with the faculty, and brought in practical perspectives that might not have otherwise come up in the discussions. They went beyond the scope of the workshop to engage the economists on discussions on subjects like FDI in retail, state of India’s economy… Based on our experience of several workshops with MLAs, we want to share some observations about the participating MLAs: -         There are MLAs in every state who want to understand substantive policy issues, and are willing to invest time and energy to do so. -         When the MLAs participate in these workshops, they choose to do so on their own, and are not compelled by anyone to do so. -         The sessions almost always begin and end on time, even in the freezing cold mornings in the Delhi winter. -         The MLAs are very engaged in the discussions, ask questions, and bring in their experiences into the classroom discussions. -         They keep partylines completely out of the substantive classroom discussions, and in the rare event that some new participant mentions anything partisan, other participants quickly ask him to avoid making any such mentions. In 2011, we have engaged with over 250 MLAs through these workshops and more. These workshops are just a starting point of what we hope will develop into a sustained, longer term engagement with MLAs on policy issues coming up in their states. In an important partnership with the Indian School of Business, Hyderabad, PRS has already conducted two workshops  at the world class facilities at the ISB campus, and is planning to hold more in 2012. Just as PRS engages with about 300 MPs in Parliament, the hope is that more MLAs will be able to derive value from the work of PRS in the years to come, thereby making their decisions better informed. Some feedback from MLAs from our earlier workshops can be seen here: http://www.youtube.com/watch?v=9XlgKCp2bvs or http://www.youtube.com/watch?v=01kLLTVtJOU&feature=related or http://www.youtube.com/watch?v=WA4NZqCj2xk&feature=related  

Recently, the central government launched the Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya).[i],[ii]  The scheme seeks to ensure universal household electrification (in both rural and urban areas) by providing last mile connectivity.  The scheme is expected to cover three crore households.  Note that currently about four crore households are un-electrified.  A rural electrification scheme has also been under implementation since 2005.  In light of this, we discuss the current situation of, and key issues related to rural electrification in the country.

Regulatory and policy framework

Under the Electricity Act, 2003, the central and state governments have the joint responsibility of providing electricity to rural areas.  The 2003 Act also mandates that the central government should, in consultation with the state governments, provide for a national policy on (i) stand-alone power systems for rural areas (systems that are not connected to the electricity grid), and (ii) electrification and local distribution in rural areas.  Consequently, the Rural Electrification Policy was notified in August 2006.[iii]

The Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), launched in 2005, was the first scheme on rural electrification.  In December 2014, Ministry of Power launched the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), which subsumed the RGGVY.[iv]  Components of DDUGJY include: (i) separation of agricultural and non-agricultural electricity feeders to improve supply for consumers in rural areas, (ii) improving sub-transmission and distribution infrastructure in rural areas, and (iii) rural electrification by carrying forward targets specified under the RGGVY.

The total financial outlay for DDUGJY over the implementation period (until 2021-22) is Rs 82,300 crore which includes budgetary support of Rs 68,900 crore.  The central government provides 60% of the project cost as grant, the state power distribution companies (discoms) raise 10% of the funds, and 30% is borrowed from financial institutions and banks.

Status of rural electrification

As of August 2017, about 1% of the villages in India remain un-electrified (3,146 villages).  However, with regard to households, around 23% (4.1 crore households) are yet to be electrified.  Table 1 at the end of this post shows the status of rural electrification across all states.

Issues with rural electrification

Definition of an electrified village

An electrified village is defined as one that has the following: (i) provision of basic infrastructure such as distribution transformers and lines in the inhabited locality, (ii) provision of electricity in public places like schools, panchayat office, health centers, dispensaries, and community centers, and (iii) at least 10% of the total number of households in the village are electrified.[iv]

Therefore, a village is considered to be electrified if 10% of the total number of households in the village have been electrified.  This is apart from the basic infrastructure and electrification of certain public centers in the village.  The Standing Committee on Energy (2013) had observed that according to this definition, a village would be called electrified even if up to 90% of households in it do not have an electricity connection.[v]  It also noted that the infrastructure being provided under the scheme is highly inadequate, unreliable and unsustainable.  The Committee recommended that the actual electrification requirement of villages must be assessed, and it should be ensured that the state discoms provide electricity to the remaining households in the village.

Supply of electricity

The Standing Committee had also noted that while the rural electrification scheme looks at creating infrastructure, the actual supply of electricity to households rests with the state discoms.[v]  These discoms are already facing huge financial losses and hence are unable to supply electricity to the villages.  Discoms continue to supply subsidised power to agricultural and residential consumers, resulting in revenue losses.  Further, the average technical and commercial losses (theft and pilferage of electricity) (AT&C losses) are at around 25%.  While the Ujjwal Discom Assurance Yojana (UDAY) has eased off some of the financial losses of the discoms, it remains to be seen whether discoms are able to reduce the cost-tariff gap and AT&C losses in the future.

It has been recommended that generation capacity should be augmented so that states can meet the additional demand under the rural electrification schemes. Further, the assistance to financially weaker states should be increased so that they can better implement the scheme.[v]

Electricity to below poverty line (BPL) households

Under the rural electrification scheme, the cost for providing free electricity connection per BPL household is Rs 3,000.  It has been observed that this cost per household may be inadequate.[v]  Due to the low cost, the quantity and the quality of work has been getting compromised leading to poor implementation of the scheme.  It has been recommended that the Ministry should revisit the cost provided under the scheme.[v]

The new electrification scheme: Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya)

The new scheme, Saubhagya, seeks to ensure universal household electrification, that is, in both rural and urban areas.  Under Saubhagya, beneficiaries will be identified using the Socio Economic and Caste Census (SECC) 2011 data.  The identified poor households will get free electricity connections.  Other households not covered under the SECC, will be provided electricity connections at a cost of Rs 500.  This amount will be collected by the electricity distribution companies in 10 instalments.

The total outlay of the scheme will be Rs 16,320 crore, of which the central government will provide Rs 12,320 crore.  The outlay for the rural households will be Rs 14,025 crore, of which the centre will provide Rs 10,588 crore.  For urban households the outlay will be Rs 2,295 crore of which the centre will provide Rs. 1,733 crore.

The state discoms will execute the electrification works through contractors or other suitable agencies.  Information technology (mobile apps, web portals) will be used to organise camps in villages to identify beneficiaries.  In order to accelerate the process, applications for electricity connections will be completed on the spot.

So far the focus of electrification schemes has been on rural areas, where typically last mile connectivity has been difficult to provide.  Saubhagya extends the ambit of electrification projects to urban areas as well.  While DDUGJY has focused on the village as the principal unit to measure electrification, the new scheme shifts the targets to household electrification.  While the target for ensuring electricity connection in each household will be a significant step towards ensuring 24×7 power, the question of continuous and quality supply to these households will still rest on the ability of the discoms to provide electricity.  Further, while the scheme provides for free connections, the ability of these households to pay for the electricity they consume may be a concern.

Table 1: Status of rural electrification across states (as of August 2017)

Fig 1 edit

* all villages in Telangana were declared electrified before the bifurcation of the state.
Sources:  Ministry of Power; PRS.

 

[i] “PM launches Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 25, 2017.

[ii] “FAQs on Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 27, 2017.

[iii].  Rural Electrification Policy, Ministry of Power, August 23, 2006, http://powermin.nic.in/sites/default/files/uploads/RE%20Policy_1.pdf.

[iv].  “Office memorandum: Deendayal Upadhyaya Gram Jyoti Yojana”, Ministry of Power, December 3, 2014, http://powermin.nic.in/rural_electrification/pdf/Deendayal_Upadhyaya_Gram_Jyoti_Yojana.pdf.

[v].  “41st Report: Implementation of Rajiv Gandhi Grameen Vidyutikaran Yojana”, Standing Committee on Energy, December 13, 2013, http://164.100.47.134/lsscommittee/Energy/15_Energy_41.pdf.