Authored by Anil Nair and CV Madhukar PRS just concluded a workshop for MLAs from 50+ from more than a dozen states.  What an AMAZING experience this was, even though this is the sixth such workshop we have held in this past year! This three day workshop on 'Mastering the Budget' was designed to help MLAs understand how to work with budget documents and numbers, find trends, understand the most critical macro numbers to track, etc. The second day of the workshop was tailored to reflect on the big thematic issues that have an impact on state finances. The Fiscal Responsibility and Budget Management Act, the Goods and Services Tax, the pattern of quantum of funds flow from the Centre to the state and local governments, the 13th Finance Commission, etc. The final day was devoted to doing an inter-state comparison of states on important budget parameters, and gleaning lessons from them. The idea for this budget workshop germinated at a previous workshop held at IIM Bangalore. The participating MLAs requested PRS to organise a special session on 'Mastering the Budget'. So this workshop was being organised as a result of their feedback. The choice of location was easy -- this was held at the National Institute for Public Finance and Policy in Delhi, which is amongst India's foremost institutions working on state budgets and public finance issues. Invitations were sent out to MLAs in several states. Responses started coming in within a few days, with about 70 confirmations. But there is always an uncertainty on the participation until the very last minute because elected politicians have immense demands on their time, at least some of which are unpredictable. So it was heartening to see that more than 50 MLAs came to the workshop representing 15 states -- Bihar, Rajasthan, Odisha, Uttar Pradesh, Assam, Kerala, West Bengal, Andhra Pradesh, Meghalaya, Tamil Nadu, Madhya Pradesh, Himachal Pradesh, Gujarat, Haryana, Manipur. The participants ranged from first time MLAs (about 50%), to a sitting Minister, a sitting Speaker, former Ministers, and senior leaders of political parties from some states. But the best part about the interaction in this workshop was that even on seemingly complex issues being discussed in the classroom, the MLAs were not mere recipients of 'gyan' that was being dished out. They had important questions to raise, and well articulated points of disagreement with the faculty, and brought in practical perspectives that might not have otherwise come up in the discussions. They went beyond the scope of the workshop to engage the economists on discussions on subjects like FDI in retail, state of India’s economy… Based on our experience of several workshops with MLAs, we want to share some observations about the participating MLAs: -         There are MLAs in every state who want to understand substantive policy issues, and are willing to invest time and energy to do so. -         When the MLAs participate in these workshops, they choose to do so on their own, and are not compelled by anyone to do so. -         The sessions almost always begin and end on time, even in the freezing cold mornings in the Delhi winter. -         The MLAs are very engaged in the discussions, ask questions, and bring in their experiences into the classroom discussions. -         They keep partylines completely out of the substantive classroom discussions, and in the rare event that some new participant mentions anything partisan, other participants quickly ask him to avoid making any such mentions. In 2011, we have engaged with over 250 MLAs through these workshops and more. These workshops are just a starting point of what we hope will develop into a sustained, longer term engagement with MLAs on policy issues coming up in their states. In an important partnership with the Indian School of Business, Hyderabad, PRS has already conducted two workshops  at the world class facilities at the ISB campus, and is planning to hold more in 2012. Just as PRS engages with about 300 MPs in Parliament, the hope is that more MLAs will be able to derive value from the work of PRS in the years to come, thereby making their decisions better informed. Some feedback from MLAs from our earlier workshops can be seen here: http://www.youtube.com/watch?v=9XlgKCp2bvs or http://www.youtube.com/watch?v=01kLLTVtJOU&feature=related or http://www.youtube.com/watch?v=WA4NZqCj2xk&feature=related  

On November 28, 2012, the Comptroller and Auditor General submitted its report on the implementation of the Jawaharlal Nehru National Urban Renewal Mission (JNNURM).  According to the report most of the projects initiated under JNNURM have not been completed.  For instance with respect to urban infrastructure projects, only 231 projects out of the 1298 sanctioned projects have been completed.  Similarly, with respect to housing projects, only 22 of the 1517 projects have been completed.  Some of the other key recommendations of the report are:

  •  Some of the reasons for the delay in completing the projects include: (i) delay in acquiring land; (ii) deficiency in preparation of projects; and (iii) non-identification of beneficiaries which increased the risk of ineligible beneficiaries getting the benefits.
  •  A total allocation of Rs 66,084 crore had been made by the Planning Commission.  However, against this total allocation, the central government had made an allocation of only Rs 37,070 out of which until March 30, 2011 only Rs 32,934 had been released.
  • There was a delay in releasing these funds to the states.  A large portion of the funds was released only in the last quarter and more particularly in March.
  • The JNNURM guidelines were deficient as they did not provide adequate guidance to the states on the method of parking the funds and utilization of interest.

The need and objectives of JNNURM According to the 2011 census India’s urban population has increased from 286 million in 2001 to 377 million in 2011 .  With the increase in urban population, there is a requirement to improve the urban infrastructure and improve the service delivery mechanisms.  With these specific objectives in mind, the central government launched the Jawaharlal Nehru National Urban Renewal Mission 2005-2006.  The aim of the Mission is to encourage reforms and fast track planned development of identified cities (such as cities with a population of more than 1 million as per the 2001 census).  JNNURM has two main components namely : (i) Urban Infrastructure and Governance  and (ii) Urban Infrastructure Development for Small and Medium Towns. The duration of JNNURM was from 2005-06 to 2011-12. However, as the projects have not been completed the Government has extended its duration until March 2014. Funds for JNNURM The funds for JNNURM are provided through the Additional Central Assistance.  This implies that the funds are provided as grants to the states directly from the centre.   In the 2012 Union Budget, the central government has allocated Rs 12,522 crore for JNNURM. This represents around 10 % of the total central assistance through the different schemes to states and union territories in 2012-13. As on June 30 2012, 554 projects at a total cost of Rs 62,253 crore have been sanctioned under the Urban Infrastructure and Governance sub-mission of JNNURM.   The table below shows the status of the sanctioned JNNURM  projects in the different states. State wise status of the projects under JNNURM                 (as on August 6, 2012)

Name of State Total Allocation (Rs Lakh) Number of sanctioned projects Completed Projects
Andhra Pradesh 2,11,845 52 18
Arunachal Pradesh 10,740 3 NA
Assam 27,320 2 NA
Bihar 59,241 8 NA
Chandigarh 27,087 3 NA
Chattisgarh 24,803 1 NA
Delhi 2,82,318 23 4
Goa 12,094 2 NA
Gujarat 2,57,881 72 40
Haryana 32,332 4 NA
Himachal Pradesh 13,066 5 NA
Jammu & Kashmir 48,836 5 NA
Jharkhand 94,120 5 NA
Karnataka 1,52,459 47 22
Kerala 67,476 11 NA
Madhya Pradesh 1,32,850 23 7
Maharashtra 5,50,555 80 21
Manipur 15,287 3 NA
Meghalaya 15,668 2 NA
Mizoram 14,822 4 NA
Nagaland 11,628 3 NA
Orissa 32,235 5 NA
Punjab 70,775 6 1
Puducherry 20,680 2 NA
Rajasthan 74,869 13 2
Sikkim 10,613 2 NA
Tamil Nadu 2,25,066 48 12
Tripura 14,018 2 NA
Uttar Pradesh 2,76,941 33 4
Uttarakhand 40,534 14 NA
West Bengal 3,21,840 69 15

Source: Jawaharlal Nehru National Urban Renewal Mission; PRS.

  • Gujarat at 55.55% has the highest number of completed projects, while Uttar Pradesh at 12.24% has the lowest number of completed projects.
  • Out of the larger states, Delhi and Maharashtra at 17% and 26% have a comparatively low rate of completed projects.
  • Maharashtra has the highest number of sanctioned projects, while the North Eastern states, Chattisgarh and Puducherry have the lowest number of sanctioned projects.