In the run up to the Budget session of Parliament, the Cabinet has decided to accept some of the key recommendations of the Select Committee on the Lokpal and Lokayuktas Bill, 2011.  The Bill, passed by the Lok Sabha in December 2011, was referred to a Select Committee by the Rajya Sabha.  The Select Committee gave its recommendations on the Bill a year later in November 2012.  At the Cabinet meeting held on January 31, 2013, the government has accepted some of these recommendations (see here for PRS comparison of the Bill, Select Committee recommendations and the approved amendments). Key approved amendments Lokayuktas: One of the most contentious issues in the Lokpal debate has been the establishment of Lokayuktas at the state level.  The Bill that was passed by the Lok Sabha gave a detailed structure of the Lokayuktas.  However, the Committee was of the opinion that while each state has to set up a Lokayukta within a year of the Act coming into force, the nature and type of the Lokayuktas should be decided by the states.  The Cabinet has agreed with the suggestion of the Committee. Inclusion of NGOs: Currently, “public servant” is defined in the Indian Penal Code to include government officials, judges, employees of universities, Members of Parliament, Ministers etc. The Bill expanded this definition by bringing societies and trusts which receive donations from the public (over a specified annual income) and, organizations which receive foreign donations (over Rs 10 lakh a year) within the purview of the Lokpal.  The Committee had however objected to the inclusion of organisations that receive donations from the public on the ground that bodies such as a rotary club or a resident’s welfare association may also be covered under the Lokpal. Bringing such entities within the Lokpal’s purview would make it unmanageable.  The Cabinet decided not to accept this recommendation stating that this view had been accepted by the Standing Committee while examining the version of the Bill introduced in the Lok Sabha.  However, the government has exempted trusts or societies for religious or charitable purposes registered under the Societies Registration Act. Procedure of inquiry and investigation:  A key recommendation of the Committee was to allow the Lokpal to directly order an investigation if a prima facie case existed (based on the complaint received).  The Cabinet has accepted this suggestion but suggested that the Lokpal should, before deciding that a prima facie case exists, call the public servant for a hearing.  An investigation should be ordered only after hearing the public servant.  Also, the Cabinet has not accepted the recommendation of the Committee that a public servant should be allowed a hearing only at the end of the investigation before filing the charge-sheet and not at any of the previous stages of the inquiry.  Power to grant sanction:  One of the key reasons cited for delays in prosecuting corrupt public officials is the requirement of a sanction from the government before a public servant can be prosecuted.  The Bill shifts the power to grant sanction from the government to the Lokpal.  It states that the investigation report shall be considered by a 3-member Lokpal bench before filing a charge-sheet or initiating disciplinary proceedings against the public servant.  The Committee recommended that at this point both the competent authority (to whom the public servant is responsible) and the concerned public servant should be given a hearing.  This has been accepted by the Cabinet. Reforms of CBI:  There are divergent views over the role and independence of the CBI.  The Committee made several recommendations for strengthening the CBI.  They include:  (a) the appointment of the Director of CBI will be through a collegium comprising of the PM, Leader of the Opposition of the Lok Sabha and Chief Justice of India; (b) the power of superintendence over CBI in relation to Lok Pal referred cases shall vest in the Lokpal; (c) CBI officers investigating cases referred by the Lokpal will be transferred with the approval of the Lokpal; and (d) for cases referred by the Lokpal, the CBI may appoint a panel of advocates (other than government advocates) with the consent of the Lok pal.  All the recommendations regarding the CBI has been accepted by the Cabinet except one that requires the approval of the Lokpal to transfer officers of CBI investigating cases referred by the Lokpal. Eligibility of Lokpal member:  According to the Bill, any person connected with a political party cannot be a member of the Lokpal.  The Committee’s recommendation was to change the term connected to affiliated to remove any ambiguity about the meaning.  This suggestion was accepted by the government. Now the interesting question is what happens if the Rajya Sabha passes the Bill with these amendments.  The Bill will have to go back to the Lok Sabha for its approval since new amendments were added by the Rajya Sabha.  If the Lok Sabha passes these amendments, the office of the Lokpal may finally see the light of day.  (See here for PRS analysis of the Lokpal and Lokayukta Bill, 2011).

Recently, the central government launched the Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya).[i],[ii]  The scheme seeks to ensure universal household electrification (in both rural and urban areas) by providing last mile connectivity.  The scheme is expected to cover three crore households.  Note that currently about four crore households are un-electrified.  A rural electrification scheme has also been under implementation since 2005.  In light of this, we discuss the current situation of, and key issues related to rural electrification in the country.

Regulatory and policy framework

Under the Electricity Act, 2003, the central and state governments have the joint responsibility of providing electricity to rural areas.  The 2003 Act also mandates that the central government should, in consultation with the state governments, provide for a national policy on (i) stand-alone power systems for rural areas (systems that are not connected to the electricity grid), and (ii) electrification and local distribution in rural areas.  Consequently, the Rural Electrification Policy was notified in August 2006.[iii]

The Rajiv Gandhi Grameen Vidyutikaran Yojana (RGGVY), launched in 2005, was the first scheme on rural electrification.  In December 2014, Ministry of Power launched the Deendayal Upadhyaya Gram Jyoti Yojana (DDUGJY), which subsumed the RGGVY.[iv]  Components of DDUGJY include: (i) separation of agricultural and non-agricultural electricity feeders to improve supply for consumers in rural areas, (ii) improving sub-transmission and distribution infrastructure in rural areas, and (iii) rural electrification by carrying forward targets specified under the RGGVY.

The total financial outlay for DDUGJY over the implementation period (until 2021-22) is Rs 82,300 crore which includes budgetary support of Rs 68,900 crore.  The central government provides 60% of the project cost as grant, the state power distribution companies (discoms) raise 10% of the funds, and 30% is borrowed from financial institutions and banks.

Status of rural electrification

As of August 2017, about 1% of the villages in India remain un-electrified (3,146 villages).  However, with regard to households, around 23% (4.1 crore households) are yet to be electrified.  Table 1 at the end of this post shows the status of rural electrification across all states.

Issues with rural electrification

Definition of an electrified village

An electrified village is defined as one that has the following: (i) provision of basic infrastructure such as distribution transformers and lines in the inhabited locality, (ii) provision of electricity in public places like schools, panchayat office, health centers, dispensaries, and community centers, and (iii) at least 10% of the total number of households in the village are electrified.[iv]

Therefore, a village is considered to be electrified if 10% of the total number of households in the village have been electrified.  This is apart from the basic infrastructure and electrification of certain public centers in the village.  The Standing Committee on Energy (2013) had observed that according to this definition, a village would be called electrified even if up to 90% of households in it do not have an electricity connection.[v]  It also noted that the infrastructure being provided under the scheme is highly inadequate, unreliable and unsustainable.  The Committee recommended that the actual electrification requirement of villages must be assessed, and it should be ensured that the state discoms provide electricity to the remaining households in the village.

Supply of electricity

The Standing Committee had also noted that while the rural electrification scheme looks at creating infrastructure, the actual supply of electricity to households rests with the state discoms.[v]  These discoms are already facing huge financial losses and hence are unable to supply electricity to the villages.  Discoms continue to supply subsidised power to agricultural and residential consumers, resulting in revenue losses.  Further, the average technical and commercial losses (theft and pilferage of electricity) (AT&C losses) are at around 25%.  While the Ujjwal Discom Assurance Yojana (UDAY) has eased off some of the financial losses of the discoms, it remains to be seen whether discoms are able to reduce the cost-tariff gap and AT&C losses in the future.

It has been recommended that generation capacity should be augmented so that states can meet the additional demand under the rural electrification schemes. Further, the assistance to financially weaker states should be increased so that they can better implement the scheme.[v]

Electricity to below poverty line (BPL) households

Under the rural electrification scheme, the cost for providing free electricity connection per BPL household is Rs 3,000.  It has been observed that this cost per household may be inadequate.[v]  Due to the low cost, the quantity and the quality of work has been getting compromised leading to poor implementation of the scheme.  It has been recommended that the Ministry should revisit the cost provided under the scheme.[v]

The new electrification scheme: Pradhan Mantri Sahaj Bijli Har Ghar Yojana (or Saubhagya)

The new scheme, Saubhagya, seeks to ensure universal household electrification, that is, in both rural and urban areas.  Under Saubhagya, beneficiaries will be identified using the Socio Economic and Caste Census (SECC) 2011 data.  The identified poor households will get free electricity connections.  Other households not covered under the SECC, will be provided electricity connections at a cost of Rs 500.  This amount will be collected by the electricity distribution companies in 10 instalments.

The total outlay of the scheme will be Rs 16,320 crore, of which the central government will provide Rs 12,320 crore.  The outlay for the rural households will be Rs 14,025 crore, of which the centre will provide Rs 10,588 crore.  For urban households the outlay will be Rs 2,295 crore of which the centre will provide Rs. 1,733 crore.

The state discoms will execute the electrification works through contractors or other suitable agencies.  Information technology (mobile apps, web portals) will be used to organise camps in villages to identify beneficiaries.  In order to accelerate the process, applications for electricity connections will be completed on the spot.

So far the focus of electrification schemes has been on rural areas, where typically last mile connectivity has been difficult to provide.  Saubhagya extends the ambit of electrification projects to urban areas as well.  While DDUGJY has focused on the village as the principal unit to measure electrification, the new scheme shifts the targets to household electrification.  While the target for ensuring electricity connection in each household will be a significant step towards ensuring 24×7 power, the question of continuous and quality supply to these households will still rest on the ability of the discoms to provide electricity.  Further, while the scheme provides for free connections, the ability of these households to pay for the electricity they consume may be a concern.

Table 1: Status of rural electrification across states (as of August 2017)

Fig 1 edit

* all villages in Telangana were declared electrified before the bifurcation of the state.
Sources:  Ministry of Power; PRS.

 

[i] “PM launches Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 25, 2017.

[ii] “FAQs on Pradhan Mantri Sahaj Bijli Har Ghar Yojana “Saubhagya””, Press Information Bureau, Ministry of Power, September 27, 2017.

[iii].  Rural Electrification Policy, Ministry of Power, August 23, 2006, http://powermin.nic.in/sites/default/files/uploads/RE%20Policy_1.pdf.

[iv].  “Office memorandum: Deendayal Upadhyaya Gram Jyoti Yojana”, Ministry of Power, December 3, 2014, http://powermin.nic.in/rural_electrification/pdf/Deendayal_Upadhyaya_Gram_Jyoti_Yojana.pdf.

[v].  “41st Report: Implementation of Rajiv Gandhi Grameen Vidyutikaran Yojana”, Standing Committee on Energy, December 13, 2013, http://164.100.47.134/lsscommittee/Energy/15_Energy_41.pdf.