(Authored by Anil Nair) The Maharashtra Legislative Assembly recently passed the Maharashtra Housing (Regulation and Development) Bill.  This is the first such Bill to be passed by any state, which sets up a housing regulator to regulate property transactions.  The Bill seeks to set up a Housing Regulatory Authority to provide for relief to flat purchasers against sundry abuses, malpractices and difficulties related to the construction, sale, management and transfer of flats. According to news reports, the government felt that existing laws were not effective in protecting the interests of the flat purchasers and allowed the promoters to avoid statutory obligations imposed on them.  The Maharashtra Ownership Flats (Regulation of the promotion of construction, sale, management and transfer) Act, 1963 did not provide for an effective implementing arm for its various statutory provisions, as the buyers could only approach consumer forum or civil court for acts of omission or commission regarding its provisions. The current Bill passed by the Maharashtra Assembly proposes to repeal the 1963 Act.  As per the Statement of Objects and Reasons of the Bill, the Regulatory Authority will strive to encourage growth and promotion of a healthy, transparent, efficient and competitive real estate market.  The Bill specifies several conditions to be fulfilled by the developer to further transparency and fairness.  All projects proposing to develop more than four flats or of land area exceeding 250 square meters have to submit and update details of the project on the website of the Housing Regulatory Authority.  Developers would be required to disclose detailed information regarding the project including:

  • building-wise time schedule of completion of each phase of the project,
  • time schedule for connecting the project with the municipal services such as sewerage, water supply, electricity, drainage etc.,
  • nature of fixtures and fittings with regard to the flooring and sanitary fittings including the brand or the price range if the items are unbranded.

Failure to give possession of the flat on the agreed date would require repayment of the full amount paid by the buyer with interest.  The Authority would also be empowered to penalise the developer up to an amount of one crore rupees for non-compliance with provisions in the Bill.  Among other initiatives to assist the real estate industry, the Housing Regulatory Authority would promote rating of projects and of promoters, by the association of promoters, to improve the confidence level of investors and consumers through self-regulation. The full text of the Bill is available on the Government of Maharashtra website.

Recently, the government issued letters de-allocating coal blocks of various companies, based on the recommendations of the  Inter Ministerial Group (IMG).  This post discusses the history behind the de-allocations, the parameters the IMG used while examining the progress of various coal blocks and the action that has been taken by the government. The Comptroller and Auditor General (CAG) released a performance audit report on 'Allocation of Coal Blocks and Augmentation of Coal Production' on August 17, 2012.  Some of the key findings of the Report were:

  • The government failed to conduct competitive bids for the allocation of coal blocks.  This resulted in a benefit of  Rs 1.86 lakh crore (approx.) to private allottees.  The government could have tapped some of this financial benefit by expediting the decision on competitive bidding for allocation of coal blocks.
  • The implementation schedule of a number of coal blocks has been delayed by one to ten years.  This schedule relates to the time frame within which the Mining Plan for the block has to be approved, various clearances have to be submitted, land acquired, etc.
  • From 2005, the Ministry of Coal (MoC) required the allottees to provide bank guarantees which would be encashed if they failed to meet the above mentioned milestones.  The CAG observed that there was a delay in introducing the bank guarantee and linking it with milestones.

The IMG on Coal was constituted for the periodic review of the development of coal blocks and end use plants.  The IMG had requested a status paper from the Coal Controller, MoC.  This has been submitted to the IMG but is not available.  The IMG will decide if private allottees have made substantial progress based on certain parameters.  The parameters used by IMG are:  approval of Mining Plan, status of environment and forest clearance, grant of mining lease and progress made in land acquisition. They are also examining the physical status of End Use Plant (EUP), investment made and the expected date of opening of the mine and commissioning of EUP. The IMG has made the following recommendations:

  • The coal blocks of companies that have not made substantial progress should be de-allocated.  Additionally, they have recommended the deduction of bank guarantee in the cases where the private companies have not reached the milestones as per the time line decided upon.  As of November 22, 2012, the IMG has recommended the de-allocation of the coal blocks listed in Table 1 and the deduction of bank guarantees for the coal blocks in Table 2.
  • Since, the system of bank guarantee was only introduced in March 2005, not all coal blocks had submitted a bank guarantee.  Where a bank guarantee has not been provided but there is substantial progress in meeting the milestones, the IMG may require the allottee to submit a bank guarantee.

[table id=1 /]

 

[table id=5 /]

 

Of the coal blocks that the IMG has recommended for de-allocation, until now the government has accepted the de-allocation of the following: Bramhadih block, Gourangdih, New Patrapara, Chinora block, Warora (Southern Part) block, Lalgarh (North) block, Bhaskarpara block, Dahegaon/Makardhokra-IV block, Gondkhari block and Ramanwara North block.  The government has accepted the deduction of bank guarantees for blocks such as Moitra, Jitpur, Bhaskarpara, Durgapur II/Sariya, Dahegaon/Makardhokra-IV, Marki Mangli II, III and IV, Gondhkari, Lohari, Radhikapur East, Bijahan and Nerad Malegaon. The letters issued by the government de-allocating coal blocks and deducting bank guarantees are available here.

For a detailed summary of the CAG Report, click here.