(Authored by Anil Nair) The Maharashtra Legislative Assembly recently passed the Maharashtra Housing (Regulation and Development) Bill.  This is the first such Bill to be passed by any state, which sets up a housing regulator to regulate property transactions.  The Bill seeks to set up a Housing Regulatory Authority to provide for relief to flat purchasers against sundry abuses, malpractices and difficulties related to the construction, sale, management and transfer of flats. According to news reports, the government felt that existing laws were not effective in protecting the interests of the flat purchasers and allowed the promoters to avoid statutory obligations imposed on them.  The Maharashtra Ownership Flats (Regulation of the promotion of construction, sale, management and transfer) Act, 1963 did not provide for an effective implementing arm for its various statutory provisions, as the buyers could only approach consumer forum or civil court for acts of omission or commission regarding its provisions. The current Bill passed by the Maharashtra Assembly proposes to repeal the 1963 Act.  As per the Statement of Objects and Reasons of the Bill, the Regulatory Authority will strive to encourage growth and promotion of a healthy, transparent, efficient and competitive real estate market.  The Bill specifies several conditions to be fulfilled by the developer to further transparency and fairness.  All projects proposing to develop more than four flats or of land area exceeding 250 square meters have to submit and update details of the project on the website of the Housing Regulatory Authority.  Developers would be required to disclose detailed information regarding the project including:

  • building-wise time schedule of completion of each phase of the project,
  • time schedule for connecting the project with the municipal services such as sewerage, water supply, electricity, drainage etc.,
  • nature of fixtures and fittings with regard to the flooring and sanitary fittings including the brand or the price range if the items are unbranded.

Failure to give possession of the flat on the agreed date would require repayment of the full amount paid by the buyer with interest.  The Authority would also be empowered to penalise the developer up to an amount of one crore rupees for non-compliance with provisions in the Bill.  Among other initiatives to assist the real estate industry, the Housing Regulatory Authority would promote rating of projects and of promoters, by the association of promoters, to improve the confidence level of investors and consumers through self-regulation. The full text of the Bill is available on the Government of Maharashtra website.

In law, the addition or deletion a single punctuation or a single word can have a major impact on the effect of that law.  One such example can be seen from the recommended changes in the Civil Liability for Nuclear Damage Bill, 2010 by Parliament’s Standing Committee. The Civil Liability for Nuclear Damage Bill, 2010 was introduced in the Lok Sabha on May 7, 2010.  The Bill was referred to the Parliamentary Committee on Science and Technology, Environment and Forests, which submitted its report on the Bill yesterday (August 18, 2010).  The Committee has made a number of recommendations regarding certain clauses in the Bill (See summary here).  One of these may have the effect of diluting the provision currently in the Bill.  The main recommendations pertain to:

  • Preventing the entry of private operators.
  • Allowing the government to increase the total liability for a nuclear incident by notification, but not decrease it.
  • Increasing the liability of the operator to Rs 1,500 crore from Rs 500 crore.
  • Increasing the time limit for claiming compensation to 20 years from 10 years.
  • Changing the provision giving operators a right of recourse against persons actually responsible for causing damage.

Clause 17 of the Bill which gives operators a right of recourse against those actually causing damage had been opposed as it was felt that it was not strong enough to hold suppliers liable in case the damage was caused by them.  Clause 17 gave a right of recourse under three conditions.  The exact clause is reproduced below: The operator of a nuclear installation shall have a right of recourse where — (a) such right is expressly provided for in a contract in writing; (b) the nuclear incident has resulted from the wilful act or gross negligence on the part of the supplier of the material, equipment or services, or of his employee; (c) the nuclear incident has resulted from the act of commission or omission of a person done with the intent to cause nuclear damage. Under this clause, a right of recourse exists when (a) there is a contract giving such a right, or (b) the supplier acts deliberately or in a grossly negligent manner to cause nuclear damage, or (c) a person causes nuclear damage with the intent to do so.  If any of the three cases can be proved by the operator, he has a right of recourse. The Committee has stated that “Clause 17(b) gives escape route to the suppliers of nuclear materials, equipments, services of his employees as their willful act or gross negligence would be difficult to establish in a civil nuclear compensation case.” It recommended that Clause 17(b) should be modified to cover consequences “of latent or patent defect, supply of sub-standard material, defective equipment or services or from the gross negligence on the part of the supplier of the material, equipment or service.” The Committee also recommended another change in Clause 17.  It recommended that clause 17(a) may end with “and”. This provision may dilute the right of recourse available to operators.  The modified clause 17 would read as: The operator of a nuclear installation shall have a right of recourse where — (a) such right is expressly provided for in a contract in writing; and, (b) the nuclear incident has resulted as a consequence of latent or patent defect, supply of sub-standard material, defective equipment or services or from the gross negligence on the part of the supplier of the material, equipment or services.; (c) the nuclear incident has resulted from the act of commission or omission of a person done with the intent to cause nuclear damage. This implies that for Clauses 17(b) or (c) to be applicable, the condition specified in clause 17(a) has to be compulsorily satisfied.  Two examples highlight the consequence of the recommended change in Clause 17(a) of the Bill:

  1. A person X deliberately commits sabotage in a nuclear plant and causes damage.  Under the Bill, the operator has recourse under Clause 17(c).  If the recommendation regarding clause 17 is accepted, the operator may also have to also prove the existence of a pre-existing contract with X in addition to clause 17(c).
  2. If a supplier supplies defective equipment, but does not have a contract in writing stating that he will be liable for damage caused by defective equipment, the operator may not have a right of recourse against the supplier under 17(b).

The effect of the changes recommended by the committee may thus dilute the provision as it exists in the Bill.  The table below compares the position in the Bill and the position as per the Standing Committee’s recommendations:

Right of recourse - The Bill gives operators a right to recourse under three conditions:  (a) if there is a clear contract; (b) if the damage is caused by someone with intent to cause damage; (c) against suppliers if damage is caused by their wilful act or negligence. In the Bill the three conditions are separated by a semi-colon.  The Committee recommended that the semi-colon in clause 17(a) should be replaced by “and”. This might imply that all three conditions mentioned need to exist for an operator to have recourse.
Right to recourse against suppliers exists in cases of “willful act or gross negligence on the part of the supplier”. (Clause 17) The Committee felt that the right of recourse against suppliers is vague.  It recommended that recourse against the supplier should be strengthened.  The supplier is liable if an incident has occurred due to (i) defects, or (ii) sub-standard material, or (iii) gross negligence of the supplier of the material, equipment or services. The variance with the Convention continues to exist.