In the recently concluded Monsoon Session of Parliament , the Parliamentary Standing Committee on Rural Development released a report on the implementation of the Mahatma Gandhi National Rural Development Act, 2005 (MGNREGA).  This blog provides a brief introduction to the key provisions of MGNREGA , followed by an overview of the major findings and recommendations of the Standing Committee.

I. MGNREGA: A brief introduction

A. Objectives: MGNREGA, which is the largest work guarantee programme in the world, was enacted in 2005 with the primary objective of guaranteeing 100 days of wage employment per year to rural households.  Secondly, it aims at addressing causes of chronic poverty through the 'works' (projects) that are undertaken, and thus ensuring sustainable development.  Finally, there is an emphasis on strengthening the process of decentralisation through giving a significant role to Panchayati Raj Institutions (PRIs) in planning and implementing these works.

B. Key features:

  • Legal right to work: Unlike earlier employment guarantee schemes, the Act provides a legal right to employment for adult members of rural households.  At least one third beneficiaries have to be women.  Wages must be paid according to the wages specified for agricultural labourers in the state under the  Minimum Wages Act, 1948, unless the central government notifies a wage rate (this should not be less than Rs 60 per day).  At present, wage rates are determined by the central government but vary across states, ranging from Rs 135 per day to Rs 214 per day.
  • Time bound guarantee of work and unemployment allowance: Employment must be provided with 15 days of being demanded failing which an ‘unemployment allowance’ must be given.
  • Decentralised planning: Gram sabhas must recommend the works that are to be undertaken and at least 50% of the works must be executed by them.  PRIs are primarily responsible for planning, implementation and monitoring of the works that are undertaken.
  • Work site facilities: All work sites should have facilities such as crèches, drinking water and first aid.
  • Transparency and accountability: There are provisions for proactive disclosure through wall writings, citizen information boards, Management Information Systems and social audits.  Social audits are conducted by gram sabhas to enable the community to monitor the implementation of the scheme.
  • Funding:  Funding is shared between the centre and the states.  There are three major items of expenditure – wages (for unskilled, semi-skilled and skilled labour), material and administrative costs.  The central government bears 100% of the cost of unskilled labour, 75% of the cost of semi-skilled and skilled labour, 75% of the cost of materials and 6% of the administrative costs.

MGNREGA was implemented in phases, starting from February 2006, and at present it covers all districts of the country with the exception of those that have a 100% urban population.  The Act provides a list of works that can be undertaken to generate employment related to water conservation, drought proofing, land development, and flood control and protection works.  Table 1 provides information regarding employment generation and expenditure under MGNREGA.

Table 1: MGNREGA: Key indicators

Year

Number of households provided employment (in crore)

Average number of person days of work per household

Total Expenditure (in lakh)

2006-07

2.10

43

8823.35

2007-08

3.39

42

15856.88

2008-09

4.51

48

27250.10

2009-10

5.25

54

37905.23

2010-11

5.49

47

39377.27

2011-12*

4.99

43

 38034.69

2012-13**

4.25

36

 28073.51

Source: Standing Committee on Rural Development; PRS. Note: *Provisional ** As on 31.01.2013

II. Findings and Recommendations of the Standing Committee on Rural Development

A. Achievements: The Standing Committee highlighted several achievements of MGNREGA in the seven years of its implementation, especially:

  • Ensuring livelihood for people in rural areas.
  • Large scale participation of women, Scheduled Castes and Scheduled Tribes (SCs/STs) and other traditionally marginalised sections of society.  SCs/STs account for 51% of the total person-days generated and women account for 47% of the total person-days generated.
  • Increasing the wage rate in rural areas and strengthening the rural economy through the creation of infrastructure assets.
  • Facilitating sustainable development, and
  • Strengthening PRIs by involving them in the planning and monitoring of the scheme.

B. Challenges: However, the Committee found several issues with the implementation of the scheme. As Table 1 (above) shows, the average number of days of employment provided to households has been lower than the mandated 100 days, and has been decreasing since 2010-11. Key issues that the Committee raised include

  • Fabrication of job cards: While as many as 12.5 crore households have been issued job cards out of an estimated 13.8 crore rural households ( as per the 2001 census), there are several issues related to existence of fake job cards, inclusion of fictitious names, missing entries and delays in making entries in job cards.
  • Delay in payment of wages: Most states have failed to disburse wages within 15 days as mandated by MGNREGA.  In addition, workers are not compensated for a delay in payment of wages.
  • Non payment of unemployment allowances: Most states do not pay an unemployment allowance when work is not given on demand.  The non-issuance of dated receipts of demanded work prevents workers from claiming an unemployment allowance.
  • Large number of incomplete works: There has been a delay in the completion of works under MGNREGA and inspection of projects has been irregular.  Implementing agencies were able to complete only 98 lakh works out of 296 lakh works.  As Table 2 shows, a large percentage of works remain incomplete under MGNREGA and the work completion rate appears to be decreasing in recent years.

Table 2: Work completion rate

Year

Work completion rate (%)

2006-07

46.34

2007-08

45.99

2008-09

43.76

2009-10

48.94

2010-11

50.86

2011-12*

20.25

2012-13*

15.02

Total                  33.22

Source: Standing Committee on Rural Development. Note: * As on 30.01.2013

  • Other key challenges include poor quality of assets created, several instances of corruption in the implementation of MGNREGA, and insufficient involvement of PRIs.

C. Recommendations: The Committee made the following recommendations, based on its findings:

  • Regulation of job cards: Offences such as not recording employment related information in job cards and unlawful possession of job cards with elected PRI representatives and MGNREGA functionaries should be made punishable under the Act.
  • Participation of women: Since the income of female workers typically raises the standard of living of their households to a greater extent than their male counterparts, the participation of women must be increased through raising awareness about MGNREGA.
  • Participation of people with disabilities: Special works (projects) must be identified for people with disabilities; and  special job cards must be issued and personnel must be employed to ensure their participation.
  • Utilisation of funds:  The Committee found that a large amount of funds allocated for MGNREGA have remained unutilised.  For example, in 2010-11, 27.31% of the funds remained unutilised.  The Committee recommends that the Department of Rural Development should analyse reasons for poor utilisation of funds and take steps to improve the same.  In addition, it should initiate action against officers found guilty of misappropriating funds under MGNREGA.
  • Context specific projects and convergence: Since states are at various stages of socio-economic development, they have varied requirements for development.  Therefore, state governments should be allowed to undertake works that are pertinent to their context.  There should be more emphasis on skilled and semi-skilled work under MGNREGA.  In addition, the Committee recommends a greater emphasis on convergence with other schemes such as the National Rural Livelihoods Mission, National Rural Health Mission, etc.
  • Payment of unemployment allowance: Dated receipts for demanded work should be issued so that workers can claim unemployment allowance.  Funds for unemployment allowance should be met by the central government.
  • Regular monitoring: National Level Monitors (NLMs) are deployed by the Ministry of Rural Development for regular and special monitoring of MGNREGA and to enquire into complaints regarding mis-utilisation of funds, etc.  The Committee recommends that the frequency of monitoring by NLMs should increase and appropriate measures should be taken by states based on their recommendations.  Additionally, social audits must mandatorily be held every six months.  The Committee observes that the performance of MGNREGA is better in states with effective social audit mechanisms.
  • Training of functionaries: Training and capacity building of elected representatives and other functionaries of PRIs must be done regularly as it will facilitate their involvement in the implementation of MGNREGA.

  The Enforcement of Security Interest and Recovery of Debts Laws and Miscellaneous Provisions (Amendment) Bill, 2016 is listed for discussion in Rajya Sabha today.[i]  The Bill aims to expeditiously resolve cases of debt recovery by making amendments to four laws, including the (i) Recovery of Debts Due to Banks and Financial Institutions Act, 1993, and (ii) the Securitisation and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002. Recovery of Debts Due to Banks and Financial Institutions Act, 1993 The 1993 Act created Debt Recovery Tribunals (DRTS) to adjudicated debt recovery cases.  This was done to move cases out of civil courts, with the idea of reducing time taken for debt recovery, and for providing technical expertise.  This was aimed at assisting banks and financial institutions in recovering outstanding debt from defaulters. Over the years, it has been observed that the DRTs do not comply with the stipulated time frame of resolving disputes within six months. This has resulted in delays in disposal, and a high pendency of cases before the DRTs. Between March 2013 and December 2015, the number of pending cases before the DRTs increased from 43,000 to 70,000.  With an average disposal rate of 10,000 cases per year, it is estimated that these DRTs will take about six to seven years to clear the existing backlog of cases.[ii] Experts have also observed that the DRT officers, responsible for debt recovery, lack experience in dealing with such cases.  Further, these officers are not adequately trained to adjudicate debt-related matters.[iii] The 2016 Bill proposes to increase the retirement age of Presiding Officers of DRTs, and allows for their reappointment.  This will allow the existing DRT officers to serve for longer periods of time.  However, such a move may have limited impact in expanding the pool of officers in the DRTs. The 2016 Bill also has a provision which allows Presiding Officers of tribunals, established under other laws, to head DRTs.  Currently, there are various specialised tribunals functioning in the country, like the Securities Appellate Tribunal, the National Company Law Tribunal, and theNational Green Tribunal.  It remains to be seen if the skills brought in by officers of these tribunals will mirror the specialisation required for adjudicating debt-related matters. Further, the 1993 Act provides that banks and financial institutions must file cases in those DRTs that have jurisdiction over the defendant’s area of residence or business.  In addition, the Bill allows cases to be filed in DRTs having jurisdiction over the bank branch where the debt is due. The Bill also provides that certain procedures, such as presentation of claims by parties and issue of summons by DRTs, can now be undertaken in electronic form (such as filing them on the DRT website). Securitisation and Reconstruction of Financial Assets and Enforcement of Security Interest Act, 2002 The 2002 Act allows secured creditors (lenders whose loans are backed by a security) to take possession over a collateral security if the debtor defaults in repayment.  This allows creditors to sell the collateral security and recover the outstanding debt without the intervention of a court or a tribunal. This takeover of collateral security is done with the assistance of the District Magistrate (DM), having jurisdiction over the security.  Experts have noted that the absence of a time-limit for the DM to dispose such applications has resulted in delays.[iv]  The 2016 Bill proposes to introduce a 30-day time limit within which the DM must pass an order for the takeover of a security.  Under certain circumstances, this time-limit may be extended to 60 days. The 2002 Act also regulates the establishment and functioning of Asset Reconstruction Companies (ARCs).  ARCs purchase Non-Performing Assets (NPAs) from banks at a discount.  This allows banks to recover partial payment for an outstanding loan account, thereby helping them maintain cash flow and liquidity.  The functioning of ARCs has been explained in Figure 1. Enforcement of security It has been observed that the setting up of ARCs, along with the use out-of-court systems to take possession of the collateral security, has created an environment conducive to lending.[iii]  However, a few concerns related to the functioning of ARCs have been expressed over the years.  These concerns include a limited number of buyers and capital entering the ARC business, and high transaction costs involved in the transfer of assets in favour of these companies due to the levy of stamp duty.[iii] In this regard, the Bill proposes to exempt the payment of stamp duty on transfer of financial assets in favour of ARCs.  This benefit will not be applicable if the asset has been transferred for purposes other than securitisation or reconstruction (such as for the ARCs own use or investment).  Consequently, the Bill amends the Indian Stamp Act, 1899. The Bill also provides greater powers to the Reserve Bank of India to regulate ARCs.  This includes the power to carry out audits and inspections either on its own, or through specialised agencies. With the passage of the Bankruptcy Code in May 2016, a complete overhaul of the debt recovery proceedings was envisaged.  The Code allows creditors to collectively take action against a defaulting debtor, and complete this process within a period of 180 days.  During the process, the creditors may choose to revive a company by changing the repayment schedule of outstanding loans, or decide to sell it off for recovering their dues. While the Bankruptcy Code provides for collective action of creditors, the proposed amendments to the SARFAESI and DRT Acts seek to streamline the processes of creditors individually taking action against the defaulting debtor.  The impact of these changes on debt recovery scenario in the country, and the issue of rising NPAs will only become clear in due course of time. [i] Enforcement of Security Interest and Recovery of Debts Laws and Miscellaneous Provisions (Amendment) Bill, 2016, http://www.prsindia.org/administrator/uploads/media/Enforcement%20of%20Security/Enforcement%20of%20Security%20Bill,%202016.pdf. [ii] Unstarred Question No. 1570, Lok Sabha, Ministry of Finance, Answered on March 4, 2016. [iii] ‘A Hundred Small Steps’, Report of the Committee on Financial Sector Reforms, Planning Commission, September 2008, http://planningcommission.nic.in/reports/genrep/rep_fr/cfsr_all.pdf. [iv] Financial Sector Legislative Reforms Commission, March 2013, http://finmin.nic.in/fslrc/fslrc_report_vol1.pdf.