In the recently concluded Monsoon Session of Parliament , the Parliamentary Standing Committee on Rural Development released a report on the implementation of the Mahatma Gandhi National Rural Development Act, 2005 (MGNREGA).  This blog provides a brief introduction to the key provisions of MGNREGA , followed by an overview of the major findings and recommendations of the Standing Committee.

I. MGNREGA: A brief introduction

A. Objectives: MGNREGA, which is the largest work guarantee programme in the world, was enacted in 2005 with the primary objective of guaranteeing 100 days of wage employment per year to rural households.  Secondly, it aims at addressing causes of chronic poverty through the 'works' (projects) that are undertaken, and thus ensuring sustainable development.  Finally, there is an emphasis on strengthening the process of decentralisation through giving a significant role to Panchayati Raj Institutions (PRIs) in planning and implementing these works.

B. Key features:

  • Legal right to work: Unlike earlier employment guarantee schemes, the Act provides a legal right to employment for adult members of rural households.  At least one third beneficiaries have to be women.  Wages must be paid according to the wages specified for agricultural labourers in the state under the  Minimum Wages Act, 1948, unless the central government notifies a wage rate (this should not be less than Rs 60 per day).  At present, wage rates are determined by the central government but vary across states, ranging from Rs 135 per day to Rs 214 per day.
  • Time bound guarantee of work and unemployment allowance: Employment must be provided with 15 days of being demanded failing which an ‘unemployment allowance’ must be given.
  • Decentralised planning: Gram sabhas must recommend the works that are to be undertaken and at least 50% of the works must be executed by them.  PRIs are primarily responsible for planning, implementation and monitoring of the works that are undertaken.
  • Work site facilities: All work sites should have facilities such as crèches, drinking water and first aid.
  • Transparency and accountability: There are provisions for proactive disclosure through wall writings, citizen information boards, Management Information Systems and social audits.  Social audits are conducted by gram sabhas to enable the community to monitor the implementation of the scheme.
  • Funding:  Funding is shared between the centre and the states.  There are three major items of expenditure – wages (for unskilled, semi-skilled and skilled labour), material and administrative costs.  The central government bears 100% of the cost of unskilled labour, 75% of the cost of semi-skilled and skilled labour, 75% of the cost of materials and 6% of the administrative costs.

MGNREGA was implemented in phases, starting from February 2006, and at present it covers all districts of the country with the exception of those that have a 100% urban population.  The Act provides a list of works that can be undertaken to generate employment related to water conservation, drought proofing, land development, and flood control and protection works.  Table 1 provides information regarding employment generation and expenditure under MGNREGA.

Table 1: MGNREGA: Key indicators

Year

Number of households provided employment (in crore)

Average number of person days of work per household

Total Expenditure (in lakh)

2006-07

2.10

43

8823.35

2007-08

3.39

42

15856.88

2008-09

4.51

48

27250.10

2009-10

5.25

54

37905.23

2010-11

5.49

47

39377.27

2011-12*

4.99

43

 38034.69

2012-13**

4.25

36

 28073.51

Source: Standing Committee on Rural Development; PRS. Note: *Provisional ** As on 31.01.2013

II. Findings and Recommendations of the Standing Committee on Rural Development

A. Achievements: The Standing Committee highlighted several achievements of MGNREGA in the seven years of its implementation, especially:

  • Ensuring livelihood for people in rural areas.
  • Large scale participation of women, Scheduled Castes and Scheduled Tribes (SCs/STs) and other traditionally marginalised sections of society.  SCs/STs account for 51% of the total person-days generated and women account for 47% of the total person-days generated.
  • Increasing the wage rate in rural areas and strengthening the rural economy through the creation of infrastructure assets.
  • Facilitating sustainable development, and
  • Strengthening PRIs by involving them in the planning and monitoring of the scheme.

B. Challenges: However, the Committee found several issues with the implementation of the scheme. As Table 1 (above) shows, the average number of days of employment provided to households has been lower than the mandated 100 days, and has been decreasing since 2010-11. Key issues that the Committee raised include

  • Fabrication of job cards: While as many as 12.5 crore households have been issued job cards out of an estimated 13.8 crore rural households ( as per the 2001 census), there are several issues related to existence of fake job cards, inclusion of fictitious names, missing entries and delays in making entries in job cards.
  • Delay in payment of wages: Most states have failed to disburse wages within 15 days as mandated by MGNREGA.  In addition, workers are not compensated for a delay in payment of wages.
  • Non payment of unemployment allowances: Most states do not pay an unemployment allowance when work is not given on demand.  The non-issuance of dated receipts of demanded work prevents workers from claiming an unemployment allowance.
  • Large number of incomplete works: There has been a delay in the completion of works under MGNREGA and inspection of projects has been irregular.  Implementing agencies were able to complete only 98 lakh works out of 296 lakh works.  As Table 2 shows, a large percentage of works remain incomplete under MGNREGA and the work completion rate appears to be decreasing in recent years.

Table 2: Work completion rate

Year

Work completion rate (%)

2006-07

46.34

2007-08

45.99

2008-09

43.76

2009-10

48.94

2010-11

50.86

2011-12*

20.25

2012-13*

15.02

Total                  33.22

Source: Standing Committee on Rural Development. Note: * As on 30.01.2013

  • Other key challenges include poor quality of assets created, several instances of corruption in the implementation of MGNREGA, and insufficient involvement of PRIs.

C. Recommendations: The Committee made the following recommendations, based on its findings:

  • Regulation of job cards: Offences such as not recording employment related information in job cards and unlawful possession of job cards with elected PRI representatives and MGNREGA functionaries should be made punishable under the Act.
  • Participation of women: Since the income of female workers typically raises the standard of living of their households to a greater extent than their male counterparts, the participation of women must be increased through raising awareness about MGNREGA.
  • Participation of people with disabilities: Special works (projects) must be identified for people with disabilities; and  special job cards must be issued and personnel must be employed to ensure their participation.
  • Utilisation of funds:  The Committee found that a large amount of funds allocated for MGNREGA have remained unutilised.  For example, in 2010-11, 27.31% of the funds remained unutilised.  The Committee recommends that the Department of Rural Development should analyse reasons for poor utilisation of funds and take steps to improve the same.  In addition, it should initiate action against officers found guilty of misappropriating funds under MGNREGA.
  • Context specific projects and convergence: Since states are at various stages of socio-economic development, they have varied requirements for development.  Therefore, state governments should be allowed to undertake works that are pertinent to their context.  There should be more emphasis on skilled and semi-skilled work under MGNREGA.  In addition, the Committee recommends a greater emphasis on convergence with other schemes such as the National Rural Livelihoods Mission, National Rural Health Mission, etc.
  • Payment of unemployment allowance: Dated receipts for demanded work should be issued so that workers can claim unemployment allowance.  Funds for unemployment allowance should be met by the central government.
  • Regular monitoring: National Level Monitors (NLMs) are deployed by the Ministry of Rural Development for regular and special monitoring of MGNREGA and to enquire into complaints regarding mis-utilisation of funds, etc.  The Committee recommends that the frequency of monitoring by NLMs should increase and appropriate measures should be taken by states based on their recommendations.  Additionally, social audits must mandatorily be held every six months.  The Committee observes that the performance of MGNREGA is better in states with effective social audit mechanisms.
  • Training of functionaries: Training and capacity building of elected representatives and other functionaries of PRIs must be done regularly as it will facilitate their involvement in the implementation of MGNREGA.

The last few days have seen repeated disruptions in Parliament. In an Opinion Editorial published in the Indian Express, Chakshu Roy of PRS Legislative Research discusses the impact of the current disruptions on Parliament. His analysis points to how disruptions are an opportunity lost  to hold the government accountable and to deliberate on significant legislative and policy issues. The second half of the budget session commenced last week with hardly any business transacted due to disruptions on different issues. This is not new. The 15th Lok Sabha has seen entire parliamentary sessions lost without any work being done. As it nears the end of its term, Parliament's productive time stands at 70 per cent, which is significantly lower than that of previous Lok Sabhas. As disruptions in Parliament have become routine, public reaction to such disruptions has also become predictable. Figures depicting the quantum of taxpayers' money lost every hour that Parliament does not function start doing the rounds, and the cry for docking the salary of disrupting members of Parliament becomes louder. What does not get adequate attention is the opportunity lost for holding the government accountable and deliberating on important legislative and policy issues. MPs are required to keep the government in check and oversee its functioning. One of the ways in which they do so is by asking ministers questions about the work done by their ministries. Ministers respond to such questions during the first hour of Parliament, which is known as question hour. During this hour, 20 questions are slotted for oral responses by ministers. Based on the response, MPs can cross-question and corner the minister by asking supplementary questions. On certain occasions, they are also able to extract assurances from the minister to take action on certain issues. When question hour is disrupted, not only are these opportunities lost, it also leads to ineffective scrutiny of the work done by the various ministries of the government. Last week, some of the questions that could not be orally answered related to four-laning of highways, performance of public sector steel companies, supply of food grains for welfare schemes, and generic versions of cancer drugs. In 2012, out of the 146 hours allocated for question hour in both Houses of Parliament, roughly only 57 hours were utilised. Since the beginning of the 15th Lok Sabha in 2009, approximately 43 per cent of the allocated time has been spent on question hour. When Parliament is disrupted regularly, its capacity to make laws is affected. Excluding routine financial legislation, since 2009, the government had planned to introduce 390 bills. So far, it has been able to introduce only 187 of them. It had also planned to have 365 bills scrutinised and passed by Parliament. So far, 96 of them have received parliamentary approval. Disruptions in Parliament also eat into the time available for discussing a bill in the house. In Lok Sabha, roughly 35 per cent of bills were passed with an hour or less of debate, a case being the sexual harassment bill, which was passed by Lok Sabha in September of last year in 16 minutes. Some would argue that since parliamentary committees scrutinise most bills in detail, there is no harm done if the bills are not debated in the House. However scrutiny of a bill behind closed doors is hardly a substitute for spirited debates on the merits and demerits of a bill on the floor of the House. Currently there are 115 bills awaiting parliamentary scrutiny and approval. Important social and economic legislation is currently pending before Parliament. The food security bill, the land acquisition bill, the companies and the goods and services tax bill are just a few of them. Out of the laundry list of pending bills, some are political and may be stuck in Parliament till consensus around them can be built. But there are a number of bills that are administrative in nature, and have no political undercurrents and are possibly not coming up for discussion because of the limited time that is available for legislative debate on account of frequent disruptions. In September 1997, to celebrate the golden jubilee of the country's Independence, a special session of Parliament was convened. At this special session, MPs had resolved to preserve and enhance the dignity of Parliament by adhering to the rules of procedure of Parliament relating to the orderly conduct of parliamentary proceedings. Last year, Parliament completed 60 years since its first sitting. To mark the occasion, another special session of both Houses was convened, where MPs had resolved to uphold the dignity, sanctity and supremacy of Parliament. Ensuring that the proceedings of both Houses run smoothly so that Parliament can discharge its responsibility effectively is the best way of ensuring its supremacy. The question that needs to be asked is whether our members of Parliament are ready to stand by the resolutions that they voluntarily adopted.