Applications for the LAMP Fellowship 2025-26 will open on December 1, 2024. Sign up here to be notified. Last date for submitting the applications is December 21, 2024.
In the recently concluded Monsoon Session of Parliament , the Parliamentary Standing Committee on Rural Development released a report on the implementation of the Mahatma Gandhi National Rural Development Act, 2005 (MGNREGA). This blog provides a brief introduction to the key provisions of MGNREGA , followed by an overview of the major findings and recommendations of the Standing Committee.
I. MGNREGA: A brief introduction
A. Objectives: MGNREGA, which is the largest work guarantee programme in the world, was enacted in 2005 with the primary objective of guaranteeing 100 days of wage employment per year to rural households. Secondly, it aims at addressing causes of chronic poverty through the 'works' (projects) that are undertaken, and thus ensuring sustainable development. Finally, there is an emphasis on strengthening the process of decentralisation through giving a significant role to Panchayati Raj Institutions (PRIs) in planning and implementing these works.
B. Key features:
MGNREGA was implemented in phases, starting from February 2006, and at present it covers all districts of the country with the exception of those that have a 100% urban population. The Act provides a list of works that can be undertaken to generate employment related to water conservation, drought proofing, land development, and flood control and protection works. Table 1 provides information regarding employment generation and expenditure under MGNREGA.
Table 1: MGNREGA: Key indicators
Year |
Number of households provided employment (in crore) |
Average number of person days of work per household |
Total Expenditure (in lakh) |
2006-07 |
2.10 |
43 |
8823.35 |
2007-08 |
3.39 |
42 |
15856.88 |
2008-09 |
4.51 |
48 |
27250.10 |
2009-10 |
5.25 |
54 |
37905.23 |
2010-11 |
5.49 |
47 |
39377.27 |
2011-12* |
4.99 |
43 |
38034.69 |
2012-13** |
4.25 |
36 |
28073.51 |
Source: Standing Committee on Rural Development; PRS. Note: *Provisional ** As on 31.01.2013
II. Findings and Recommendations of the Standing Committee on Rural Development
A. Achievements: The Standing Committee highlighted several achievements of MGNREGA in the seven years of its implementation, especially:
B. Challenges: However, the Committee found several issues with the implementation of the scheme. As Table 1 (above) shows, the average number of days of employment provided to households has been lower than the mandated 100 days, and has been decreasing since 2010-11. Key issues that the Committee raised include
Table 2: Work completion rate
Year |
Work completion rate (%) |
2006-07 |
46.34 |
2007-08 |
45.99 |
2008-09 |
43.76 |
2009-10 |
48.94 |
2010-11 |
50.86 |
2011-12* |
20.25 |
2012-13* |
15.02 |
Total | 33.22 |
Source: Standing Committee on Rural Development. Note: * As on 30.01.2013
C. Recommendations: The Committee made the following recommendations, based on its findings:
Authored by Vishnu Padmanabhan and Priya Soman The Budget speech may have already been scrutinised and the numbers analysed but the Budget process is far from complete. The Constitution requires expenditure from the government’s Consolidated Fund of India to be approved by the Lok Sabha (the Rajya Sabha does not vote, but can suggest changes). After the Finance Minister presents the Union Budget, Parliament holds a general discussion followed by a detailed discussion and vote on Demands for Grants. In the general discussion, the House discusses the Budget as a whole but no motions can be moved and no voting takes place. In the 15th Lok Sabha, the average time spent during the Budget Session on general discussion has been 13 hours 20 minutes so far. Following the general discussion, Parliament breaks for recess while Demands for Grants – the projected expenditure by different ministries - are examined by the relevant Standing Committees of Parliament. This year Parliament is scheduled to break for a month from March 22nd to April 22nd. After the break, the Standing Committees table their reports; the grants are discussed in detail and voted on. Last year, the total time spent on the Union Budget, on both general and detailed discussion was around 32 hours (or 18% of total time in the session), largely in line with the average time spent over the last 10 years (33 hours, 20% of total time). A unique feature of Indian democracy is the separate presentation and discussion for the Railway Budget. Including the Railway Budget the overall time spent on budget discussion last year was around 55 hours (30% of total time in the session).
Note: All data from Budget sessions; data from 2004 and 2009 include interim budget sessions. Source: Lok Sabha Resume of Work, PRS
During the detailed discussion, MPs can call for ‘cut motions’ to reduce the amounts of demands for grants made by a Ministry. This motion can be tabled in three ways: (i) ‘the amount of the demand be reduced to Re.1/’ signifying disapproval of the policies of that ministry; (ii) ‘the amount of the demand be reduced by a specified amount’, an economy cut signifying a disapproval of the amount spent by the ministry and (iii) ‘the amount of the demand be reduced by Rs.100/-', a token cut airing a specific grievance within the policy of the government. However in practice almost all demands for grants are clubbed and voted together (a process called guillotining). In 2012, 92% of demands for grants were guillotined. The grants for Ministries of Commerce and Industry, Health and Family Welfare, Home Affairs and Urban Development were the only grants taken up for discussion. Over the last 10 years, 85% of demands for grants have been voted for without discussion. The most frequently discussed demand for grants come from the Ministry of Home Affairs (discussed in 6 of the last 10 sessions) and the Ministry of Rural Development (5 times). Demand for grants for Defence, the largest spending Ministry, has only been voted after discussion once in the last 10 years.
Source: Lok Sabha Resume of Work, Union Budget documents, PRS
If the government needs to spend any additional money, it can introduce Supplementary Demands for Grants during the year. However if after the financial year government spending on a service exceeds the amount granted, then an Excess Demand for Grant has to be introduced and passed in the following year. The Budget process concludes with the introduction and passage of the Appropriation Bill authorising the government to spend money from the Consolidated Fund of India. In addition, a Finance Bill, containing the taxation proposals of the government is considered and passed by the Lok Sabha after the Demands for Grants have been voted upon.