In the recently concluded Monsoon Session of Parliament , the Parliamentary Standing Committee on Rural Development released a report on the implementation of the Mahatma Gandhi National Rural Development Act, 2005 (MGNREGA). This blog provides a brief introduction to the key provisions of MGNREGA , followed by an overview of the major findings and recommendations of the Standing Committee.
I. MGNREGA: A brief introduction
A. Objectives: MGNREGA, which is the largest work guarantee programme in the world, was enacted in 2005 with the primary objective of guaranteeing 100 days of wage employment per year to rural households. Secondly, it aims at addressing causes of chronic poverty through the 'works' (projects) that are undertaken, and thus ensuring sustainable development. Finally, there is an emphasis on strengthening the process of decentralisation through giving a significant role to Panchayati Raj Institutions (PRIs) in planning and implementing these works.
B. Key features:
MGNREGA was implemented in phases, starting from February 2006, and at present it covers all districts of the country with the exception of those that have a 100% urban population. The Act provides a list of works that can be undertaken to generate employment related to water conservation, drought proofing, land development, and flood control and protection works. Table 1 provides information regarding employment generation and expenditure under MGNREGA.
Table 1: MGNREGA: Key indicators
Year |
Number of households provided employment (in crore) |
Average number of person days of work per household |
Total Expenditure (in lakh) |
2006-07 |
2.10 |
43 |
8823.35 |
2007-08 |
3.39 |
42 |
15856.88 |
2008-09 |
4.51 |
48 |
27250.10 |
2009-10 |
5.25 |
54 |
37905.23 |
2010-11 |
5.49 |
47 |
39377.27 |
2011-12* |
4.99 |
43 |
38034.69 |
2012-13** |
4.25 |
36 |
28073.51 |
Source: Standing Committee on Rural Development; PRS. Note: *Provisional ** As on 31.01.2013
II. Findings and Recommendations of the Standing Committee on Rural Development
A. Achievements: The Standing Committee highlighted several achievements of MGNREGA in the seven years of its implementation, especially:
B. Challenges: However, the Committee found several issues with the implementation of the scheme. As Table 1 (above) shows, the average number of days of employment provided to households has been lower than the mandated 100 days, and has been decreasing since 2010-11. Key issues that the Committee raised include
Table 2: Work completion rate
Year |
Work completion rate (%) |
2006-07 |
46.34 |
2007-08 |
45.99 |
2008-09 |
43.76 |
2009-10 |
48.94 |
2010-11 |
50.86 |
2011-12* |
20.25 |
2012-13* |
15.02 |
Total | 33.22 |
Source: Standing Committee on Rural Development. Note: * As on 30.01.2013
C. Recommendations: The Committee made the following recommendations, based on its findings:
There has been much discussion about bringing the GDP growth on track and the need for expediting infrastructure projects in this regard. At the Planning Commission Meeting to approve the Twelfth Five Year Plan, last month, there were concerns about the implementation of such projects because of the delay in the grant of environment and forest clearances. In this context, there has been talk of setting up a singular body that will grant approvals for large infrastructure projects. News reports suggest that the government is considering forming a National Investment Approval Board (NIAB). The NIAB will be responsible for expediting the clearances for mega project proposals above a certain financial threshold. The Board would be headed by the Prime Minister and will have the authority to provide the ‘final decision’ on investment projects. According to news reports, the NIAB will be the final decision making body. The Ministry of Environment & Forests (MoEF) has raised concerns that this would create ambiguity in the current process of granting clearance for projects. While the formation of the NIAB is still being deliberated and discussed, it would be relevant to understand the process that the MoEF follows before granting clearance to a project and look at data on number of clearances granted and pending. The MoEF has developed certain processes to examine the potential environmental impact of new projects or expansion of existing projects. These are contained in the Environment Impact Assessment Notification, 2006. This notification empowers the Expert Appraisal Committees (EAC) to review the environmental impact of projects. The EAC carries out a combination of these steps depending on the classification of the project:
The MoEF considers the grant of environmental clearance to development projects in terms of the provisions of EIA Notification, 2006. From July 13, 2011 to July 12, 2012 the MoEF has given environmental clearances to 209 development projects. For a sector wise break up see Table 1. Table 1: Number of Environment Clearances Accorded
Sector | No. of projects accorded EC |
Industry (Steel & Cement) |
88 |
Thermal Power |
29 |
River Valley and Hydro-electric |
6 |
Coal Mining |
29 |
Non-Coal Mining |
25 |
National Highways |
32 |
Total |
209 |
Source: “Environmental Clearance accorded from 13.07.2011 to 12.07.2012”, MoEF A total of 593 proposals are pending for environmental clearance as on August 13, 2012.[i] It remains to be seen how the process of granting clearances as established by the MoEF will be reconciled with the expedited process of the NIAB.
[i] MoEF, Lok Sabha, Unstarred Question no. 637, August 13, 2012,