In the recently concluded Monsoon Session of Parliament , the Parliamentary Standing Committee on Rural Development released a report on the implementation of the Mahatma Gandhi National Rural Development Act, 2005 (MGNREGA).  This blog provides a brief introduction to the key provisions of MGNREGA , followed by an overview of the major findings and recommendations of the Standing Committee.

I. MGNREGA: A brief introduction

A. Objectives: MGNREGA, which is the largest work guarantee programme in the world, was enacted in 2005 with the primary objective of guaranteeing 100 days of wage employment per year to rural households.  Secondly, it aims at addressing causes of chronic poverty through the 'works' (projects) that are undertaken, and thus ensuring sustainable development.  Finally, there is an emphasis on strengthening the process of decentralisation through giving a significant role to Panchayati Raj Institutions (PRIs) in planning and implementing these works.

B. Key features:

  • Legal right to work: Unlike earlier employment guarantee schemes, the Act provides a legal right to employment for adult members of rural households.  At least one third beneficiaries have to be women.  Wages must be paid according to the wages specified for agricultural labourers in the state under the  Minimum Wages Act, 1948, unless the central government notifies a wage rate (this should not be less than Rs 60 per day).  At present, wage rates are determined by the central government but vary across states, ranging from Rs 135 per day to Rs 214 per day.
  • Time bound guarantee of work and unemployment allowance: Employment must be provided with 15 days of being demanded failing which an ‘unemployment allowance’ must be given.
  • Decentralised planning: Gram sabhas must recommend the works that are to be undertaken and at least 50% of the works must be executed by them.  PRIs are primarily responsible for planning, implementation and monitoring of the works that are undertaken.
  • Work site facilities: All work sites should have facilities such as crèches, drinking water and first aid.
  • Transparency and accountability: There are provisions for proactive disclosure through wall writings, citizen information boards, Management Information Systems and social audits.  Social audits are conducted by gram sabhas to enable the community to monitor the implementation of the scheme.
  • Funding:  Funding is shared between the centre and the states.  There are three major items of expenditure – wages (for unskilled, semi-skilled and skilled labour), material and administrative costs.  The central government bears 100% of the cost of unskilled labour, 75% of the cost of semi-skilled and skilled labour, 75% of the cost of materials and 6% of the administrative costs.

MGNREGA was implemented in phases, starting from February 2006, and at present it covers all districts of the country with the exception of those that have a 100% urban population.  The Act provides a list of works that can be undertaken to generate employment related to water conservation, drought proofing, land development, and flood control and protection works.  Table 1 provides information regarding employment generation and expenditure under MGNREGA.

Table 1: MGNREGA: Key indicators

Year

Number of households provided employment (in crore)

Average number of person days of work per household

Total Expenditure (in lakh)

2006-07

2.10

43

8823.35

2007-08

3.39

42

15856.88

2008-09

4.51

48

27250.10

2009-10

5.25

54

37905.23

2010-11

5.49

47

39377.27

2011-12*

4.99

43

 38034.69

2012-13**

4.25

36

 28073.51

Source: Standing Committee on Rural Development; PRS. Note: *Provisional ** As on 31.01.2013

II. Findings and Recommendations of the Standing Committee on Rural Development

A. Achievements: The Standing Committee highlighted several achievements of MGNREGA in the seven years of its implementation, especially:

  • Ensuring livelihood for people in rural areas.
  • Large scale participation of women, Scheduled Castes and Scheduled Tribes (SCs/STs) and other traditionally marginalised sections of society.  SCs/STs account for 51% of the total person-days generated and women account for 47% of the total person-days generated.
  • Increasing the wage rate in rural areas and strengthening the rural economy through the creation of infrastructure assets.
  • Facilitating sustainable development, and
  • Strengthening PRIs by involving them in the planning and monitoring of the scheme.

B. Challenges: However, the Committee found several issues with the implementation of the scheme. As Table 1 (above) shows, the average number of days of employment provided to households has been lower than the mandated 100 days, and has been decreasing since 2010-11. Key issues that the Committee raised include

  • Fabrication of job cards: While as many as 12.5 crore households have been issued job cards out of an estimated 13.8 crore rural households ( as per the 2001 census), there are several issues related to existence of fake job cards, inclusion of fictitious names, missing entries and delays in making entries in job cards.
  • Delay in payment of wages: Most states have failed to disburse wages within 15 days as mandated by MGNREGA.  In addition, workers are not compensated for a delay in payment of wages.
  • Non payment of unemployment allowances: Most states do not pay an unemployment allowance when work is not given on demand.  The non-issuance of dated receipts of demanded work prevents workers from claiming an unemployment allowance.
  • Large number of incomplete works: There has been a delay in the completion of works under MGNREGA and inspection of projects has been irregular.  Implementing agencies were able to complete only 98 lakh works out of 296 lakh works.  As Table 2 shows, a large percentage of works remain incomplete under MGNREGA and the work completion rate appears to be decreasing in recent years.

Table 2: Work completion rate

Year

Work completion rate (%)

2006-07

46.34

2007-08

45.99

2008-09

43.76

2009-10

48.94

2010-11

50.86

2011-12*

20.25

2012-13*

15.02

Total                  33.22

Source: Standing Committee on Rural Development. Note: * As on 30.01.2013

  • Other key challenges include poor quality of assets created, several instances of corruption in the implementation of MGNREGA, and insufficient involvement of PRIs.

C. Recommendations: The Committee made the following recommendations, based on its findings:

  • Regulation of job cards: Offences such as not recording employment related information in job cards and unlawful possession of job cards with elected PRI representatives and MGNREGA functionaries should be made punishable under the Act.
  • Participation of women: Since the income of female workers typically raises the standard of living of their households to a greater extent than their male counterparts, the participation of women must be increased through raising awareness about MGNREGA.
  • Participation of people with disabilities: Special works (projects) must be identified for people with disabilities; and  special job cards must be issued and personnel must be employed to ensure their participation.
  • Utilisation of funds:  The Committee found that a large amount of funds allocated for MGNREGA have remained unutilised.  For example, in 2010-11, 27.31% of the funds remained unutilised.  The Committee recommends that the Department of Rural Development should analyse reasons for poor utilisation of funds and take steps to improve the same.  In addition, it should initiate action against officers found guilty of misappropriating funds under MGNREGA.
  • Context specific projects and convergence: Since states are at various stages of socio-economic development, they have varied requirements for development.  Therefore, state governments should be allowed to undertake works that are pertinent to their context.  There should be more emphasis on skilled and semi-skilled work under MGNREGA.  In addition, the Committee recommends a greater emphasis on convergence with other schemes such as the National Rural Livelihoods Mission, National Rural Health Mission, etc.
  • Payment of unemployment allowance: Dated receipts for demanded work should be issued so that workers can claim unemployment allowance.  Funds for unemployment allowance should be met by the central government.
  • Regular monitoring: National Level Monitors (NLMs) are deployed by the Ministry of Rural Development for regular and special monitoring of MGNREGA and to enquire into complaints regarding mis-utilisation of funds, etc.  The Committee recommends that the frequency of monitoring by NLMs should increase and appropriate measures should be taken by states based on their recommendations.  Additionally, social audits must mandatorily be held every six months.  The Committee observes that the performance of MGNREGA is better in states with effective social audit mechanisms.
  • Training of functionaries: Training and capacity building of elected representatives and other functionaries of PRIs must be done regularly as it will facilitate their involvement in the implementation of MGNREGA.

The Minister of Railways, Dinesh Trivedi, presented the Railways Budget 2012 to Parliament on 14th March.  While commenting on the financial position of Railways, the Minister said that 'the Indian Railways are passing through a difficult phase'. The Operating Ratio for the closing year is now estimated to equal 95%. This is significantly higher than the 91.1% figure budgeted last year. Operating Ratio is a metric that compares operating expenses to revenues. A higher ratio indicates lower ability to generate surplus. Surplus is used for capital investments such as laying of new lines, deploying more coaches etc. Therefore, a smaller surplus affects the Railway’s capability to make such investments. Budget v/s Revised estimates 2011-12 Budget 2011-12 had estimated the performance of Railways for the financial year. Revised estimates have now been submitted. Taken together, these two figures help in comparing actual performance against targets. Some observations are enumerated below:

  • Total receipts decreased by Rs 2,746 crore.
  • Total expenditure increased by Rs 2,102 crore.
  • Operating Ratio increased from 91.1% to 95%. This implies a decrease in surplus.
  • Appropriations to the ‘Development Fund’ and the ‘Capital Fund’ decreased from Rs 5,258 crore to Rs 1,492 crore (a decrease of 72%). The ‘Development Fund’ finances expenditure such as passenger amenities; the ‘Capital Fund’ is used for capital augmentation such as laying of new lines.

Budget estimates 2012-13 In 2012-13, Railways plan to improve Operating Ratio to 84.9% and to increase surplus to Rs 15,557 crore. This is more than 10 times the surplus generated in 2011-12 (Revised Estimates). The effective increase in freight rates is estimated to average 23%. During this time, passenger fares are also estimated to increase by an effective average rate of 19%. [1] Infrastructure Performance during the 11th Plan Under the 11th Five Year Plan, the total plan expenditure for Railways had been approved at Rs 2,33,289 crore. The Outcome Budget shows that the actual expenditure is only likely to be Rs 1,92,291 crore. Thus, expenditure will fall short by Rs 40,998 crore. This gaps exists despite a significant increase in the Gross Budgetary Support approved by Parliament. Plan expenditure during 2007-12 (In Rs Crore)

 

Approved Expenditure

Actual Expenditure

Gross Budgetary Support

63,635

75,979

Internal Resources

90,000

67,763

Extra Budgetary Support

79,654

48,549

Total

2,33,289

1,92,291

The Standing Committee on Railways, in its 11th report presented in August 2011, had sought an explanation from the Ministry. According to the Ministry, lower mobilization of internal resources and lack of extra budgetary support are the main reasons for the shortfall.  Internal resource mobilization has been low because of (i) impact of the 6th Pay Commission; and (ii) slow growth in freight earnings due to the economic slowdown. Extra budgetary resources have been low due to non-materialization of funds through the Public-Private Partnership route. Proposals for the 12th Plan Two recent committees – Kakodkar Committee on Railway Safety and the Pitroda Committee on Railway Modernization – have called for large investments in the next five years. The Kakodkar Committee has recommended an investment of Rs 1,00,000 crore in the next five years to improve safety; the Pitroda Committee has recommended an expenditure of Rs 3,96,000 crore in the next five years on modernization. The Railway sub-group of the 12th Five Year Plan has also estimated a requirement of Rs 4,42,744 crore for various other investments proposed to be undertaken during the Plan period. [2] All three groups have called for significant investments in infrastructure augmentation in the next five years. Budget proposals 2012-13 According to the Minister’s speech, the Annual Plan outlay for the year 2012-13 has been set at Rs 60,100 crore. The plan would be financed through:

  • Gross Budgetary Support of Rs 24,000 crore
  • Railway Safety Fund of Rs 2,000 crore
  • Internal Resources of Rs 18,050 crore
  • Extra Budgetary Resources of Rs 16,050 crore. Of this, Rs 15,000 crore would be borrowed from the market through IRFC (Indian Railway Finance Corporation).

What happens now? The Budget is likely to be discussed in the two Houses within the next few days.  Post the discussion, the Ministry's proposals will be put to vote.  Once passed, the Ministry can put its proposals into action. For more details on the Railway Budget, including the projects proposed this year and the status of proposals made last year, please see our analysis here. To understand some of the challenges faced by the Indian Railways, see our blog post from last year. Notes: [1] The ‘effective average fare’ has been calculated by dividing the total income from the segment (freight/ passenger) by the total traffic (in NTKM/ PKM).  This would vary with changes in fares as well as the usage by different categories of users (including the proportion of tickets booked through Tatkal). [2] Source: Report of the Expert Group on Railway Modernization (Chairman: Sam Pitroda)